Slide 1: Maricunga Project Information Memorandum May 2020
MARICUNGA PROJECT INFORMATION MEMORANDUM May 2020
Slide 2: A World Class Asset
MARICUNGA PROJECT A World Class Asset Maricunga is Chile’s highest grade and most advanced lithium project outside the Salar de Atacama. 2019 Definitive Feasibility Study (DFS) by WorleyParsons supports 20,000 tonnes per annum production of LCE over 20 years. DFS shows after-tax NPV of US$908 millio
Slide 3: An Overview
MARICUNGA PROJECT An Overview Maricunga EIA has been approved by the Chilean Government in February 2020. Maiden ore reserve estimate of 742,000 tonnes LCE exceeds 20-year mine life production needs, and meets JORC and NI 43-101 standards. Potential to expand resources and reserves below the existin
Slide 4: Joint Venture Structure
MARICUNGA PROJECT Joint Venture Structure Over US$60 million has been invested in the project to date All the mining concessions are held by the joint-venture company, Minera Salar Blanco (“MSB”) The Board for the Maricunga JV is comprised of six (6) board members with representation by Lithium Powe
Slide 5: CODELCO Agreement
MARICUNGA PROJECT CODELCO Agreement Minera Salar Blanco S.A. entered into a non- binding Memorandum of Understanding (“MOU”) in August 2019 with CODELCO, the Chilean State-owned mining company MOU to define terms for the negotiation of a definitive agreement to form a new joint venture (“JV”) allowi
Slide 6: Among the Most Efficient Producers Globally
MARICUNGA PROJECT Among the Most Efficient Producers Globally Roskill’s analysis (as of January 2019) of the lithium cost curve in 2027 of all lithium producers shows total production costs (incl. royalties) in the lowest quartile for the Maricunga project 6
Slide 7: Lithium Carbonate Production Cost - Producers in Chile
MARICUNGA PROJECT Lithium Carbonate Production Cost - Producers in Chile 7
Slide 8: Hydro-Geological Model
MARICUNGA PROJECT Hydro-Geological Model The calibrated reserve model is used to simulate a brine extraction system that will meet the brine feed requirements for the evaporation ponds for an annual lithium carbonate (LCE) production target of 20,000 TPY over a 20-year project life. It is assumed th
Slide 9: Mining Resources (Drilling Results)
MARICUNGA PROJECT Mining Resources (Drilling Results) Results from the drilling program averaged 1,167 mg/l Li and 8,500 mg/l K Extensive Sonic and RC drilling 4,700m plus and 1,000 brine samples plus, including 300 core samples for drainable porosity 360m Deeper drilling for increase in mining reso
Slide 10: Measured and Indicated Resource - Lithium and Potassium
MARICUNGA PROJECT Measured and Indicated Resource-Lithium and Potassium (metric tonnes) Lithium is converted to lithium carbonate with a conversion factor of 5.32 Potassium is converted to potash with a conversion factor of 1.91 10
Slide 11: LCE Mining Reserve
MARICUNGA PROJECT LCE Mining Reserve (metric tonnes) Prepared in accordance with the guidelines of National Instrument 43- 101 Brine production reserve for LCE production: 58% Li process recovery efficiency Brine production initiates on the mining concessions constituted under mining concession owne
Slide 12: MSB Exploration Target
MARICUNGA PROJECT MSB Exploration Target (metric tonnes) Based on the results of borehole S-19, an exploration target of 1.0 to 2.5 Mt of lithium carbonate equivalent (LCE) and 2.9 to 6.6 Mt of potassium chloride (KCl) has been identified (below the current resource) between a depth of 200 m and 400
Slide 13: Future Growth Potential
MARICUNGA PROJECT Future Growth Potential Current Mining Resource includes all concessions down to a depth of 200 m Potential for significant growth below 200 m as evidenced by hole S-19 which terminated in high-grade brine assaying 877 mg/L Li Geophysical & seismic surveys indicate the basin extend
Slide 14: A High Quality Finished Product
MARICUNGA PROJECT A High Quality Finished Product Definitive Feasibility Study (DFS) by WorleyParsons completed in Jan 2019, indicates Maricunga to be a low-cost lithium producer with attractive economics. Optimization of lithium production to develop the lowest cost process with highest possible re
Slide 15: CAPEX & OPEX
MARICUNGA PROJECT CAPEX & OPEX Capital cost from January 2019 DFS at US$563M includes 12.5% contingency Capex cost includes an estimated $70M of refundable VAT per MSB assumptions Operating costs are in the lowest quartile of the global cost curve at US$3,772 per metric tonne Lithium Carbonate 15
Slide 16: Project Infrastructure
MARICUNGA PROJECT Project Infrastructure Wellfield & pipelines to evaporation ponds Evaporation ponds – off salar to the north to allow for easier construction Water supply & treatment Electricity supply & transmission lines – multiple options including accessible 23 KV powerline borders the project
Slide 17: Project Infrastructure Flowchart
MARICUNGA PROJECT Project Infrastructure Flowchart 17
Slide 18: All Critical Project Infrastructure Secured
MARICUNGA PROJECT All Critical Project Infrastructure Secured The project is located close to critical roads and port infrastructure: 170 km northeast of Copiapó and 250 km from the Chilean Coast. Secured critical power & water infrastructure with long-term contracts Process Water – secured rights t
Slide 19: Process Diagram – Salt removal Plant
MARICUNGA PROJECT Process Diagram – Salt removal Plant 19
Slide 20: Lithium Carbonate Plant
MARICUNGA PROJECT Lithium Carbonate Plant Process includes: 1. Solvent extraction of boron 2. Precipitation CaCO3 3. Precipitation of Mg(OH)2 and CaCO3 4. Final removal of calcium, magnesium and heavy metals by ion exchange resins 5. Li2CO3 precipitation crystallization (Li2CO3 crystallizer) 6. Li2C
Slide 21: Process Diagram – Lithium Carbonate Plant (Schematic One)
MARICUNGA PROJECT Process Diagram – Lithium Carbonate Plant (Schematic One) 21
Slide 22: Process Diagram – Lithium Carbonate Plant (Schematic Two)
MARICUNGA PROJECT Process Diagram – Lithium Carbonate Plant (Schematic Two) 22
Slide 23: MSB Receives Environmental Approval for Maricunga Lithium Project
MARICUNGA PROJECT MSB Receives Environmental Approval for Maricunga Lithium Project News Release - EIA Approval received Feb 05, 2020 Minera Salar Blanco S.A. (“MSB”), has received environmental impact assessment (“EIA”) for the Maricunga project in the Atacama Region of northern Chile. The Chilean
Slide 24: MSB Receives Environmental Approval for Maricunga Lithium Project
MARICUNGA PROJECT MSB Receives Environmental Approval for Maricunga Lithium Project News Release - EIA Approval received Feb 05, 2020 The process involved in-depth data gathering, a variety of environmental and engineering studies and monitoring campaigns including a comprehensive 11,400-page docume
Slide 25: Project Economic Analysis - 2019 DFS
MARICUNGA PROJECT Project Economic Analysis - 2019 DFS The MSB project has an after tax NPV (8%) of US$940M. The after tax IRR is 26.7%. The construction period including commissioning and startup covers 3 years. Payback of project requires only the first 4 years of operations out of the 20 year pro
Slide 26: Project Cash Flow - 2019 DFS
MARICUNGA PROJECT Project Cash Flow - 2019 DFS Project life from DFS is 20 years from plant commissioning and startup The mining resource base and process recoveries could support a longer project life The current mining license is for 20,000 metric tonnes per year for 20 years of production 26
Slide 27: Highest Grade Undeveloped Lithium Project
MARICUNGA PROJECT Highest Grade Undeveloped Lithium Project 27