  1. Slide 1: 6th Energy in Western Australia Conference

    6th ENERGY IN WESTERN AUSTRALIA CONFERENCE 17-18 November 2004 --------- Michael McCormack Chief Operating Officer Australian Pipeline Trust

  2. Slide 2: Australian Pipeline Trust

    Australian Pipeline Trust < ASX public listing (ASX ticker - APA) < Ownership: 30% AGL, 10% Petronas, 60% Public < Diversified portfolio of gas pipelines < Aim to expand our national presence < Infrastructure investment Business 2

  3. Slide 3: Profitability Since Float

    Profitability Since Float Net Profit after Tax and $M minorities (NPATM) 2004 NPATM: 140 121.3 +195.50% from pcp. 120 2004 NPATM: Normalised +9.6% from pcp. 100 80 60 45.0 37.1 41.0 40 30.7 20 0 2001 2002 2003 2004 2004 Actual Normalised 3

  4. Slide 4: Gas Pipelines 2004

    Gas Pipelines 2004 APT pipelines Other pipelines AGT CGP GGT RBP MWP MSP CWP PGP APT Pipelines 2004 Amadeus Gas - AGT Carpentaria Gas Transmission - CGP Central West - CWP Goldfields Gas Transmission - GGT Mid West Pipeline - MWP Moomba to Sydney - MSP 4 7 Gas - PGP Parmelia Roma to Brisbane - RBP

  5. Slide 5: Western Australia

    Western Australia Broome NORTH WEST SHELF Port Hedland Dampier Onslow Newman GOLDFIELDS GAS TRANSMISSION Carnarvon PIPELINE Mt Magnet DONGARA Geraldton PROCESSING Windimurra FACILITY Kalgoorlie PARMELIA PIPELINE MONDARRA PERTH Esperance FACILITY 5

  6. Slide 6: Benefits of SCP Group Acquisition

    Benefits of SCP Group Acquisition Advancing Strategic Goals < Enhanced footprint in WA < Positive financial impact on APT < Diversification of APT’s portfolio < Sound long term prospects 6

  7. Slide 7: Portfolio Diversification

    Portfolio Diversification APT 2004 Revenues APT 2004 Revenues Pro forma pre-acquisition Pro forma post-acquisition Other Other Parmelia 4% 3% 7% GGT MSP 22% 32% (55% SCP MSP revenue 41% share) (100% SCP GGT revenue 32% share) CGP 12% AGT 7% AGT CGP RBP RBP 9% 9% 10% 12% Note: GGT revenues shown on a

  8. Slide 8: Goldfields Gas Pipeline (GGT)

    Goldfields Gas Pipeline (GGT) Growth Prospects < Projects under active consideration: – Thunderbox Gold – Esperance Lateral – Hamersley Iron Ore at Paraburdoo – Murrin Murrin Expansion < Spot market development: – Arising from potential shortage of gas transportation on DBNGP – Power generated in Ka

  9. Slide 9: Parmelia Pipeline

    Parmelia Pipeline Operation Overview < Capacity of pipeline 70 TJ/d, expandable up to 120 TJ/d < Pipeline traverses industrial corridors of Perth and Kwinana through to Pinjarra < Currently connected to major WA gas users – Alcoa and Western Power – Western Mining – BP, TiWest and Hismelt < Connecte

  10. Slide 10: Parmelia Pipeline

    Parmelia Pipeline Strong Growth Prospects < DBNGP By-Pass Contracts – Bypass services to DBNGP customers – Flexibility for peak loads (Mondarra storage facility) < Alinta Distribution System By-Pass Contracts – Alinta Network customers can be connected directly 10

  11. Slide 11: Parmelia Pipeline

    Parmelia Pipeline Strong Growth Prospects < Alinta Network Interconnection – Alinta Network distributes approximately 30 PJ a year – APT Parmelia has capability to deliver gas to customers via • Interconnection to Perth northern network • Proposed interconnection to Perth southern network – Security

  12. Slide 12: Pipeline Capacity to Perth & Kwinana

    Pipeline Capacity to Perth & Kwinana Managing Deliverability < DBNGP – Firm capacity fully contracted < Parmelia pipeline – 30-40 TJ/d spare firm capacity – 50 TJ/d developable capacity 12

  13. Slide 13: Perth Basin Production

    Perth Basin Production Opportunities Continue < ARC currently drilling < Origin/ ARC joint venture expected to drill several new wells in the near future < Origin to complete drilling of Tarantula field 13

  14. Slide 14: Parmelia Pipeline

    Parmelia Pipeline Experienced Suppliers to SW Market < 30 years experience, covering whole gas chain: production, transportation, distribution, and supply < Highlights: – Commercialisation of Mondarra gas storage facilities – New lateral connections to industrial customers and distribution network –

  15. Slide 15: Parmelia Pipeline

    Parmelia Pipeline Access into Perth Distribution System < Parmelia first gas pipeline in WA and sole supplier 1972- 1985, discontinued due to commissioning of DBGNP < First re-connection completed July 2000 into northern distribution network < Enhances security of supply < Permanent interconnection

  16. Slide 16: Mondarra Gas Storage Facility

    Mondarra Gas Storage Facility Operation Overview < Since 1996, WA’s only natural gas storage facility < Connected to both Parmelia and DBNGP < Load management and peaking services < Capacity between 6-9 PJ < Emergency gas supply 16

  17. Slide 17: Mondarra Gas Storage Facility

    Mondarra Gas Storage Facility Current Development Features < Tailored to suit customer requirements < Deliverability: currently up to 10 TJ/d < Injectivity: currently up to 10 TJ/d < Further development potential to 150 TJ/d < Mondarra Junction: by 2005, capacity to increase to 100TJ/d 17

  18. Slide 18: APT Strategy in WA

    APT Strategy in WA Major Player < Gas Transport - Expand our business through opportunities that increase utilisation and expansion of our existing pipelines. < Storage - Develop and implement opportunities to maximise utilisation of the Mondarra Storage facility as part of the energy equation for t

  19. Slide 19: Goldfields Pipeline (GGT)

    Goldfields Pipeline (GGT) Code Process < 1999: Access Arrangement submitted, 2004: Amended Draft Decision < Awaiting finalised Access Arrangement following GGTJV submission on Amended Draft Decision < Revised Access Arrangement lodged yesterday < APT seeks fair regulation and recognition of State Ag

  20. Slide 20: Conclusion

    Conclusion: < APT is an Australian company, investing in WA for the long term < Goldfields Pipeline serves a world class minerals province - an important asset < Parmelia business faces a difficult battle with DBGNP - fierce competition, but APT is in WA to win business < Focus on developing Parmeli

  21. Slide 21: We Deliver

    We Deliver www.pipelinetrust.com.au

Australian Pipeline Trust — 6th Energy in Western Australia Conference 2004 on 6ix