  1. Slide 1: Northwest Pipeline Sundance Trail Expansion Project

    Northwest Pipeline Sundance Trail Expansion Project Greasewood/Meeker to Opal February 2008 © 2008 The Williams Companies, Inc. All rights reserved.

  2. Slide 2: Sundance Trail Expansion Project

    Sundance Trail Expansion Project > 150,000 Dth/day expansion* • Utilize available capacity on WY the mainline, CHC lateral and Opal Hub Piceance lateral Kern River – Muddy Creek • Construct ~16-miles of 30- CIG – Green River inch loop mainly between Clay Basin Green River and Muddy Piceance Lateral

  3. Slide 3: CHC Lateral and Piceance Lateral Descriptions

    CHC Lateral and Piceance Lateral Descriptions NWP – Piceance CHC Lateral (Meeker Hub) Lateral > 29-mile, 20-inch Lateral from Meeker Hub to interconnect with REX NW P mainline near Sand Springs WIC White River Hub Rangely • Targeted In-Service Date of November 2009 Meeker Plant Greasewood > ~150,000

  4. Slide 4: Sundance Trail Expansion Services Offered

    Sundance Trail Expansion Services Offered > Greasewood/Meeker to Opal Firm Transportation Service (approximately 150,000 Dth/d) • Firm transportation directly from receipt points at the Meeker Hub (~150,000 Dth/d) or the Greasewood Hub (up to 22,327 Dth/d) for delivery to the Opal Hub or other deliv

  5. Slide 5: Contacts

    Contacts Please feel free to contact one of the following with any questions: Larry Larsen (801) 584-6645 Larry.C.Larsen@Williams.com Hank Henrie (801) 584-6625 Hank.L.Henrie@Williams.com © 2008 The Williams Companies, Inc. All rights reserved. 5