Slide 1: Kurnell community update
ner 5 \ \ EOE Mita a \ E ws, | | ‘ by a mes | ae | : ' es Us Hy] Kurnell community upd 4 June 2022 pee
Slide 2: Agenda
Agenda Item Presenter Introductions Andrew Brewer Remediation program update Jos Kusters Testing update WSP Outcome of Ampol investigation Andrew Brewer / Alan Colwell Q&A All AMPOL
Slide 3: Remediation zones map
Zone 1 Zone 3 West Zone 8 Zone 3 East Zone 4 Zone 5 Zone 2 Zone 6 Zone 7
Slide 4: Remediation progress by zone
Remediation progress by zone Remediation works are well progressed, locations with remaining impacts will be addressed in the coming weeks — we expect completion to be reached around the middle of June x remediation 5 5 a Bulk remediation complete (tern stele ai Venies Sunes ene] Cersxatin Coals hit
Slide 5: Remediation validation sampling results
Remediation validation sampling results The number of samples so far - Between 21 April and 27 May, 1042 samples have been sent for analysis as part of the remediation work - Of the samples above, results for 546 samples have been released to the public, the remaining will be released as they are re
Slide 6: Other testing - update
Other testing - update Private property sampling * We have sampled at 30 residential properties * Reports have been sent out to 27 properties Ambient air sampling * Results have been shared with the public — the results did not indicate any risk to human health * Data for private properties have bee
Slide 7: Events and our response to date
Events and our response to date On Thursday 7 April the wastewater separators at our Kurnell terminal overflowed following heavy rain. The overflow caused the discharge of hydrocarbon residues with storm water onto Captain Cook Drive and surrounding areas, including local waterways in Kurnell Events
Slide 8: Positive progress on works in community
Positive progress on works in community Ampol thanks for the community for working with us on a number of activities to improve amenity in Kurnell - Beautification of the shopping centre garden - New driveways installed for Men's Shed and Girl Guides Hall with an accessibility ramp for the Girl Guid
Slide 9: Investigation — outline and introduction
Investigation — outline and introduction The investigation was undertaken by a senior Ampol team located in a separate part of Ampol's business. Alan Colwell, Project Manager at our Lytton refinery, led the investigation and is here tonight The investigation team interviewed key personnel involved i
Slide 10: Cause of incident
10 Cause of incident The following conclusions have been reached from the investigation: =~ A1in100-year rainfall major storm event, coupled with high groundwater levels and a peak high tide, combined to overwhelm the stormwater discharge capacity and the wastewater treatment plant = Stormwater reac
Slide 11: Rain and groundwater conditions
Rain and groundwater conditions a Rainfall at the start of 2022 well exceeded regular rain patterns. January-March 2022 received 968mm of rainfall compared to an historical mean of 336mm. This meant groundwater levels were high. Previous analysis shows that groundwater levels at Kurnell Terminal tak
Slide 12: Daily rainfall at the Kurnell terminal
12 Daily rainfall at the Kurnell terminal Kurnell terminal received solid rain volumes from 1-9 March and then again from 25 March - 1 April. Rainfall in the morning and afternoon of 6 April 2022 (39mm between 12.01am to 7.00pm) provided fresh surface water. At the time of major storm event (between
Slide 13: Major storms event — 6-7 April 2022
Major storms event — 6-7 April 2022 13 = On the evening of 6 April 2022, a major storms event occurred over Kurnell = Wide ranging rain and storms battered the greater Sydney region through the evening, with Kurnell experiencing the full brunt of the conditions =" The Kurnell Terminal rain gauge rec
Slide 14: Tide in Botany Bay
4 Tide in Botany Bay " Tidal data from Botany Bay is shown in the figure below, with peak high tide of 1.60 metres on 6 April 2022 at 11:46pm * The peak high tide coincided with the timing of the storm event at Kurnell. The stormwater discharge from the Ampol Terminal Catchment B drains to Quibray B
Slide 15: Through the evening, heavy rain was experienced.
Through the evening, heavy rain was experienced.
Slide 16: Through the evening, heavy rain was experienced.
Through the evening, heavy rain was experienced.
Slide 17: Summary of critical events
7 Summary of critical events 12:30am 12:30am 1:30am 2:50am 3:00am 3:50am 6:1am 6:15am Hydrocarbon breach of boundary. Clear and strong smell of hydrocarbon was evident with hydrocarbon resting on the stormwater surface as it flowed South to North, towards intersection of Captain Cook Drive and Solan
Slide 18: Summary of critical events
18 Summary of critical events 4:00 - 9:00am 10:00am - 12:00pm 12:00pm 1:00 - 6:00pm 2:00pm 5:43pm /\ AMPOL Ampol works to offer support with hydrocarbon mitigation on public land. Site walk of Captain Cook Drive, Marton Park wetlands, Quibray bay wetlands between Ampol, EPA and HazMat. Hydrocarbon f
Slide 19: Hydrocarbon spill volume
19 Hydrocarbon spill volume The original hydrocarbon spill volume notice of ZOOL calculated on the morning of the incident is no longer considered accurate. The investigation concluded that the hydrocarbon release volume can be estimated at 9,200L ® Initial notification and estimation by Ampol was b
Slide 20: Hydrocarbon released in incident
20 Hydrocarbon released in incident Review of the hydrocarbon properties demonstrated the type of hydrocarbon released was more than 99% diesel * It is recognised that the release had a black colour and sour odour. The black type appearance of the material is the result of approximately 0.5% of the
Slide 21: Changes implemented to prevent re-occurrence
21 Changes implemented to prevent re-occurrence The investigation found interim steps already taken by the Kurnell team to prevent re- occurrence link well with key findings of report. Steps already taken by the Ampol Kurnell team include: Sourcing additional diesel driven pumps to keep stormwater p
Slide 22: Longer-term actions to prevent re-occurrence
Actions Completion Apr-22 May-22 Jun-22 Jul-22 Aug-22 Sep-22 Oct-22 Nov-22 Dec-22 Longer-term Actions to Prevent Re-occurrence Dec-22 Conduct design review of Storm Water System & Oily Water System & Dec-22 assess options to segregate the two systems Improve maintenance and cleaning frequency and pr
Slide 23: What's next
What's next Ampol will continue to deliver on workstreams identified and communicated to the community Develop and implement an EPA rted ongoing community environmental monitoring plan Commission EPA impa nts in the nmunity Community Engagement Focus on the root cause and contributing factors of the