Pure Gold Mining — Technical Presentation (September 2017)
16 slides from Pure Gold Mining's technical presentation, September 2017
Slide 1: September 2017 PGM:TSX-V
September 2017 PGM:TSX-V
Slide 2: Madsen Gold Project Preliminary Economic Assessment
Madsen Gold Project Preliminary Economic Assessment September 2017
Slide 3: Forward Looking Statement
FORWARD LOOKING STATEMENT Cautionary Statement on Forward-Looking Information & Statements This presentation contains certain forward-looking information and statements which may not be based on fact, including without limitation, statements regarding the Company’s expectations in respect of its fut
Slide 4: PEA is preliminary in nature and includes inferred mineral resources
The Preliminary Economic Assessment (“PEA”) is preliminary in nature and includes inferred mineral resources that are too speculative geologically to have economic considerations applied to them that would enable them to be categorized as mineral reserves. There is no certainty that PEA results will
Slide 5: Investor Conference Call
Investor Conference Call Pure Gold Participants • Darin Labrenz, President and CEO • Christopher Lee, Chief Geoscientist • Sean Tetzlaff, Chief Financial Officer • Phil Smerchanski, Vice President of Exploration • Ken Donner, Vice President of Operations • Adam Buchanan, Manager, Investor Relations
Slide 6: Madsen Gold Project - Red Lake Mining District
Red Lake Mining District CANADIAN HIGH GRADE GOLD BELT Madsen Gold Project 2.45 million oz HISTORICAL PRODUCTION (1) 1.65 million oz INDICATED RESOURCE (2) 0.18 million oz INFERRED RESOURCE (2) Current Mineral Resource(2): 1,648,000 ozs at 8.9 g/t Gold in 5.79 Mt Indicated 178,000 ozs at 9.4 g/t Gol
Slide 7: Preliminary Economic Assessment
Madsen Gold Project PRELIMINARY ECONOMIC ASSESSMENT • Total gold production of ~911,500 2017 PEA (1) ounces over a 14 year mine life at an average diluted head grade of 10.3 g/t Pre-Tax / After-Tax IRR gold (1) 54% / 47% Underground mining operation with Pre-Tax / After-Tax NPV5% $365 / $258 acces
Slide 8: Significant Infrastructure in Place
Madsen Mine & Mill SIGNIFICANT INFRASTRUCTURE IN PLACE 7
Slide 9: Current Mineral Resource
Madsen Gold Project CURRENT MINERAL RESOURCE Resource Grade Contained Gold Tonnes Classification g/t Au (oz.) Indicated 5,785,000 8.9 1,648,000 Inferred 587,000 9.4 178,000 The updated mineral resource estimate for Madsen is reported at a 4.0 g/t Au cut-off effective August 2, 2017 (1). Mineral Reso
Slide 10: Key Technical Assumptions
Madsen Gold Project KEY TECHNICAL ASSUMPTIONS • The mine plan includes utilization of existing mining, milling, and tailings management infrastructure, with further development of the ramp to accommodate an underground mining operation • Trade off study completed to realize value of the 8 Zone resou
Slide 11: Capital Costs
Madsen Gold Project CAPITAL COSTS Madsen Life of Mine Capital 60.0 50.0 • Initial capital of $50.9 million • Sustaining capital of $134.7 million 40.0 C$ Millions 30.0 20.0 10.0 0.0 Yr -1 Yr 1 Yr 2 Yr 3 Yr 4 Yr 5 Yr 6 Yr 7 Yr 8 Yr 9 Yr 10 Surface Infrastructure Mining Infrastructure Mobile Equipment
Slide 12: Operating Costs
Madsen Gold Project OPERATING COSTS Operating Unit Costs 250.00 200.00 150.00 $/t processed 100.00 50.00 - yr-1 yr 1 yr 2 yr 3 yr 4 yr 5 yr 6 yr 7 yr 8 yr 9 yr 10 yr 11 yr 12 yr 13 yr 14 Mining Power Processing G&A Operating Costs $/t processed $/oz US$/oz Mining Cost $155 $511 $409 Processing Cost
Slide 13: Project Details
PROJECT DETAILS Parameters • Underground mining via a combination of conventional cut & fill and shrinkage methods • $50.9 million in pre-production capital costs over a 12-month period Majority of cost for mill upgrades, ramp and surface development New ventilation and dewatering system which w
Slide 14: Project Enhancement Opportunities
Madsen Gold Project PROJECT ENHANCEMENT OPPORTUNITIES Resource Expansion Potential • Satellite resources to be disclosed in Q417 • Potential expansions of Madsen Mine Optimization of Mine Plan • Investigate mechanized cut and fill and long hole mining methods • Review ramp sequencing to optimize cap
Slide 15: Next Steps
Madsen Gold Project NEXT STEPS • Project Development schedule, which will provide a critical path to a production decision • Continued underground drilling from the existing Madsen ramp, to test extensions to the current mineral resource • Continued surface drilling aimed at identifying and extendin
Slide 16: Corporate Inquiries: Darin Labrenz
Corporate Inquiries: Darin Labrenz President & CEO t: 604.646.8000 info@puregoldmining.ca PGM:TSX-V 1900 – 1055 West Hastings Street Vancouver, BC V6E 2E9 www.puregoldmining.ca