  1. Slide 1: BW Offshore Q2 2012 presentation

    Slide 1: BW Offshore Q2 2012 presentation

    BW Offshore Q2 2012 presentation 30 August 2012

  2. Slide 2: Disclaimer

    Slide 2: Disclaimer

    Disclaimer This Presentation has been produced by BW Offshore Limited ( “BW Offshore”) exclusively for information purposes. This presentation may not be redistributed, in whole or in part, to any other person. This document contains certain forward-looking statements relating to the business, finan

  3. Slide 3: Highlights

    Slide 3: Highlights

    Highlights Q2 2012 EBITDA of USD 26.9 million Papa Terra project USD 50 million in negative contribution BW Athena and BW Joko Tole accepted and in operation Contract extensions for Petróleo Nautipa and Berge Helene Operational contract with Statoil Dividend payment of USD 0.01 per share 30 August 2

  4. Slide 4: Operation

    Slide 4: Operation

    OPERATION

  5. Slide 5: Operational highlights

    Slide 5: Operational highlights

    Operational highlights Uptime HSSEQ performance 100.0% 98.0% − Lost time injuries (LTI) < 1.0 96.0% 94.0% Fleet uptime 92.0% 90.0% − Q2 2012 uptime of 98.1% 88.0% 86.0% Petróleo Nautipa contract extension 84.0% 82.0% 80.0% − Firm period until 2020 2005 2006 2007 2008 2009 2010 2011 2012 YTD − Option

  6. Slide 6: Fleet actions and performance

    Slide 6: Fleet actions and performance

    Fleet actions and performance Re-classification programs with Three units are approaching extensive steel replacement, end of contracts and option equipment renewals and periods. Potential for further various upgrades have extensions and in-situ renewal weakened fleet performance programs are explor

  7. Slide 7: BW Athena

    Slide 7: BW Athena

    BW Athena Accepted by client on 8 June Three year firm contract − Options for additional five years Start-up in line with expectations, but some running-in problems related to utility systems Source: Ithaca 30 August 2012 7

  8. Slide 8: BW Joko Tole

    Slide 8: BW Joko Tole

    BW Joko Tole Accepted by client on 31 May Ten year firm contract − Options for additional four years Start-up better than expectations and 100% uptime from first day 30 August 2012 8

  9. Slide 9: O&M contract with Statoil, Brazil

    Slide 9: O&M contract with Statoil, Brazil

    O&M contract with Statoil, Brazil Reimbursable operation and maintenance contract for the FPSO Peregrino − Firm period until 2018 − Options until 2033 BW Offshore will take over operation after a six month transition period − Statoil and Sinochem acquired the vessel from Maersk in June − Unit curren

  10. Slide 10: Fleet overview

    Slide 10: Fleet overview

    Fleet overview U ni t Typ e C o nt r act 2009 2 0 10 2 0 11 2 0 12 2 0 13 2 0 14 2 0 15 2 0 16 2 0 17 2 0 18 2 0 19 2 02 0 2 0 21 20 2 2 2 02 3 2 0 24 2025 Sendje B erge FPSO Lease A ddax/ Sinopec, Nigeria: 2005-2013 Berge Helene FPSO Lease Pet ronas, M aurit ania: 2006-2015 (2021) Yùum K'ak'Náab FP

  11. Slide 11: Papa Terra project status

    Slide 11: Papa Terra project status

    Papa Terra project status STATUS Progress 98% at end July 2012 Planned start-up July 2013 Main issues: Current contract loss USD 25 mill − Commissioning of boiler for propulsion − No allowance made for LD in projected − Minimize carry over to Brazil cost IDENTIFIED REASONS ACTIONS Much larger conver

  12. Slide 12: Finance

    Slide 12: Finance

    LL O = < < Ta

  13. Slide 13: Financial highlights

    Slide 13: Financial highlights

    Financial highlights Q2 2012 EBITDA of USD 26.9 million − Negative contribution from P-63 (Papa Terra) project − BW Athena and BW Joko Tole contribution in June − Insurance settlement related to Ningaloo Vision Last installment of USD 100 million from Apache Energy received in July (Q3 2012) 30 Augu

  14. Slide 14: P&L

    Slide 14: P&L

    P&L USD million Q2 12 Q1 12 Q2 11 2011 Operating revenue 222.5 217.5 228.6 846.2 Operating expenses -195.9 -148.4 -141.7 -534.0 Share of profit from associates 0.3 0.1 0.0 -0.3 EBITDA 26.9 69.2 86.9 311.9 Depreciation -53.5 -43.6 -45.0 -178.6 Amortisations -0.7 -0.6 -1.0 -4.5 Gain (loss) on sale of

  15. Slide 15: Balance sheet

    Slide 15: Balance sheet

    Balance sheet Equity ratio 31.2 % Net interest bearing debt USD 1,754.6 million USD million 30.06.12 31.03.12 30.06.11 31.12.11 Total non-current assets 3 067.9 3 055.1 3 334.1 3 009.6 Assets of disposal group held for sale - - 7.1 185.0 Total current assets 422.2 401.9 428.4 607.0 Total assets 3 49

  16. Slide 16: Debt and installment profile

    Slide 16: Debt and installment profile

    Debt and installment profile Gross debt of USD 1,863.6 million per 30 June 2012 Gross debt (USD million) Installments (USD million) 2000 500 1800 450 400 1600 Bond 350 Bond 1400 Petroleo CIRR 300 1200 Nautipa Petroleo Nautipa Umuroa 250 1000 Umuroa 200 RCF 800 RCF 150 Term loan/NV 600 Term loan Term

  17. Slide 17: Orderbook

    Slide 17: Orderbook

    Orderbook Orderbook of USD 7.9 billion − Whereof USD 4.2 billion are firm contracts New orders of USD 900 million in Q2 High value cashflow and backlog from solid counterparties Orderbook (USD million) Clients 8 000 7 000 NOC Petrobras 25 % 6 000 30 % 5 000 4 000 3 000 2 000 1 000 0 E&P Firm Option

  18. Slide 18: Market & Summary

    Slide 18: Market & Summary

    MARKET & SUMMARY J | 7

  19. Slide 19: Market

    Slide 19: Market

    Market Limited number of contract awards during first half 2012 Number of future field developments remains high, but low short term bidding activity Continue disciplined approach to pricing and terms FPSO supply and demand (based on existing projects only) Source: ODS/IHS, Pareto 30 August 2012 19

  20. Slide 20: Selected opportunities

    Slide 20: Selected opportunities

    Selected opportunities Indicated Project Name Operator Country award Madura FPSO CNOOC Indonesia Q4 2012 Ayatzil-Tekel FPSO Pemex Mexico Q1 2013 Catcher FPSO Premier Oil UK North Sea Q2 2013 Ande Ande FPSO AWE Indonesia Q2 2013 Atlanta/Olivia FPSO QGEP Brazil Q2 2013 Leviathan FPSO Noble Energy Isra

  21. Slide 21: Summary

    Slide 21: Summary

    Summary Completing Papa Terra project has top priority Focus on operations on existing units Negotiating potential extensions Continue market activities 30 August 2012 21

  22. Slide 22: Q&A

    Slide 22: Q&A

    Q&A 22 Picture:: Petrobras

  23. Slide 23: Further information

    Slide 23: Further information

    Further information: www.bwoffshore.com IR contact: Kristian Flaten, Vice President IR and Corporate Finance kristian.flaten[a]bwoffshore.com 30 August 2012 23