    For personal use only WEST AFRICAN RESOURCES LTD Presentation Euroz Conference WEST AFRICA’S EMERGING GOLD PRODUCER 10 March 2020

  2. Slide 2: Important Notice and Disclaimer

    IMPORTANT NOTICE IMPORTANT NOTICE AND DISCLAIMER COMPETENT PERSONS STATEMENT For personal use only This presentation contains “forward-looking information” within the meaning of securities legislation, including information relating to Information in this presentation that relates to exploration res

  3. Slide 3: West African Resources: 4 Years Since Discovery

    WEST AFRICAN RESOURCES 4 YEARS SINCE DISCOVERY For personal use only March 2016 June 2018 November 2018 December 2018 Discovery 1st DFS for CIL, Ordered mills, awarded WAF raises M1 South Open-pit and engineering contract to A$365m debt and underground mining Lycopodium, equity to fully TAN16-RC122

  4. Slide 4: West Africa's Emerging New Gold Producer

    WEST AFRICA’S EMERGING NEW GOLD PRODUCER  Build complete and commissioning underway For personal use only  On target for +300,000 ounces gold in first 12 months of production at lowest quartile AISC <US$500/oz  Fully-funded, unhedged on track for Q2 2020 production from open-pit oxide and free-mi

  5. Slide 5: Why Burkina Faso?

    WHY BURKINA FASO?  Underlain by Birimian gold bearing rocks For personal use only  1.7 Moz gold production in 2018  Sanbrado the 14th commercial gold mine in 14 years  Historically stable government and community support for gold mining  Sanbrado located in relatively secure south-central Burki

  6. Slide 6: Capital Structure and Analyst Coverage

    CAPITAL STRUCTURE AND ANALYST COVERAGE ASX: WAF Analyst Coverage2 Total Ordinary Shares on Issue 870.5m Argonaut James Wilson For personal use only Options and performance rights on issue 15.7m Euroz Andrew Clayton Top 20 Shareholders 58% Hartleys Mike Millikan Cash at 29 February 2020 US$41m Macqua

  7. Slide 7: Experienced Board and Management

    EXPERIENCED BOARD AND MANAGEMENT For personal use only BOARD OF DIRECTORS SENIOR MANAGEMENT RICHARD HYDE SIMON STORM MATTHEW WILCOX LUKE HOLDEN Executive Chairman & Non-Executive Chief Development GM Sanbrado Operations Chief Executive Officer Director & Co-Sec Officer Process Manager Founder, Geolo

  8. Slide 8: March 2019

    SANBRADO GOLD PROJECT For personal use only March 2019 8

  9. Slide 9: Project Status 100% Complete

    SANBRADO GOLD PROJECT For personal use only March 2020 Project Status 100% COMPLETE Build complete, commissioning underway on schedule for Q2 2020 gold production 9

  10. Slide 10: Key Project Metrics

    SANBRADO GOLD PROJECT KEY PROJECT METRICS  High-grade UG and open-pit operation with For personal use only conventional 2.2Mtpa SABC CIL plant  MRE of 3.1 Moz Au 2.4 Moz Au (Indicated) & 0.7 Moz Au (Inferred)  1.7 Million ounce Probable Reserve Underground: 0.65 Moz at 10.2 g/t gold Open-pits: 1.

  11. Slide 11: M1 South Deposit

    SANBRADO GOLD PROJECT M1 SOUTH DEPOSIT April 2019 MRE  For personal use only Open Pit 0-100m – 183koz at 6.3 g/t Au 178koz at 6.4 g/t gold (Indicated) 5koz at 5.2 g/t gold (Inferred)  Underground 100-700m – 814koz at 19.5 g/t Au 697koz at 21.9 g/t gold (Indicated) 117koz at 11.2 g/t gold (Inferred

  12. Slide 12: M1 South Deposit: +700m and still going strong

    SANBRADO GOLD PROJECT M1 SOUTH DEPOSIT For personal use only +700m and still going strong  Recent drilling beneath reserves include: – TAN18-DD228: 25m at 15 g/t Au from 862m including 5.5m at 40.4 g/t Au – Step-down drilling to commence in March 2020 TAN18-DD228 670m bsl 12

  13. Slide 13: M5 Deposit

    SANBRADO GOLD PROJECT M5 DEPOSIT For personal use only April 2019 Mineral Resource Estimate  51.3Mt at 1.2 g/t Au for 2.0 Moz Au  36.6Mt at 1.2 g/t Au for 1.47Moz Au (Ind) Open-pit Mining Underway  14.6Mt at 1.1 g/t Au for 0.52Moz Au (Inf) April 2019 Probable Reserves at US$1200/oz  6 months of

  14. Slide 14: Annual Production – April 2019 DFS + UG Potential After Y6

    SANBRADO GOLD PROJECT ANNUAL PRODUCTION – APRIL 2019 DFS + UG POTENTIAL AFTER Y6 400,000 For personal use only 350,000  M1 South OP 2 years, M5 OP 10 years  M1 South UG 6.5 years, Y1-6 average 100Koz gold 300,000  TAN18-DD228: 25m at 15 g/t Au from 862m including 5.5m at 40.4 g/t Au 220m beneath

  15. Slide 15: Project Status 100% Complete

    Project Status 100% For personal use only COMPLETE SANBRADO GOLD PROJECT 15

  16. Slide 16: For personal use only

    SANBRADO GOLD PROJECT For personal use only Clockwise from top left: ROM bin apron feeder and primary crusher, 17MW power station, 16 CV1 ore stockpile full capacity, mine services area,

  17. Slide 17: For personal use only

    SANBRADO GOLD PROJECT For personal use only Clockwise from top left: 270 person camp, tailings storage facility, underground portal and storage 17 ponds, 2 million cubic metre water storage dam

  18. Slide 18: M1 South Underground Development Progress

    M1 SOUTH UNDERGROUND DEVELOPMENT PROGRESS For personal use only 1 2  Decline +180m below surface level  Total development +1,500m  First development ore expected March 2020  First stoping ore expected September 2020 3 4 18

  19. Slide 19: E & S Commitments

    SANBRADO GOLD PROJECT E & S COMMITMENTS For personal use only Environmental and Social  Baseline studies for the ESIA and RAP were undertaken from 2015 to 2018. Environmental and RAP approvals were granted in 2018. WAF management meeting local stakeholders post  Environmental permit was granted in

  20. Slide 20: Equipe Sanbrado

    EQUIPÉ SANBRADO For personal use only 1,350 WORKERS ON SITE 95% BURKINABÉ 5% EXPATRIATE Clockwise from top left: Underground team, CSR dept, Construction team, construction contractors. 20

  21. Slide 21: Near-Term Catalysts

    NEAR-TERM CATALYSTS ON BUDGET AND ON SCHEDULE FOR GOLD PRODUCTION EARLY Q2 2020 For personal use only Commence major earthworks and civils Q1 2019  Complete pipeline and 2M3 water storage facility Q2 2019  First draw from US$200m Taurus Debt Facility Q2 2019  Award open-pit mining contract Q3 201

  22. Slide 22: Mineral Resources and Reserves

    MINERAL RESOURCES AND RESERVES Cutoff Indicated Resource Inferred Resource Total SANBRADO GOLD For personal use only (Au g/t) Grade Grade Grade PROJECT MINERAL Tonnes Au Oz Tonnes (Au Au Oz Tonnes Au Oz (Au g/t) (Au g/t) RESOURCES g/t) April 2019 M1 South U/G >180mRL 3 1,000,000 21.9 697,000 300,000

  23. Slide 23: West African Resources Ltd

    For personal use only W E S T A F R I C A N R E S O U R C E S LT D A S X : WA F WE S T A F R I C A’ S E M E R G I N G G O L D P R O D U C E R 23 W W W. W E S TA F R I C A N R E S O U R C E S . C O M