Anglo American — Corporate Update (January 2013)

18 slides from Anglo American's corporate update, Jan 29, 2013

  1. Slide 1: Minas-Rio Review

    MINAS-RIO REVIEW 29 January 2013

  2. Slide 2: Cautionary Statement

    CAUTIONARY STATEMENT Disclaimer: This presentation has been prepared by Anglo American plc (“Anglo American”) and comprises the written materials/slides for a presentation concerning Anglo American. By attending this presentation and/or reviewing the slides you agree to be bound by the following con

  3. Slide 3: Business case as presented at time of purchase

    BUSINESS CASE AS PRESENTED AT TIME OF PURCHASE “Rationale for acquiring the project(1) – Board made a long term strategic decision to substantially grow our iron ore portfolio – one of the cornerstones of Anglo’s strategy – Minas-Rio provides quality product on a huge scale – Differentiated product

  4. Slide 4: Business case for Minas-Rio remains intact

    BUSINESS CASE FOR MINAS-RIO REMAINS INTACT Good future fundamentals Significant increase in resource • Medium to long term fundamentals for iron ore remain • Delineated 5.8 bn from 1.2 bn tonnes of Mineral Resources robust 180.0 160.0 ~5x 140.0 5.8 Average spot price 120.0 Fe US$/t 100.0 Consensus l

  5. Slide 5: Business case for Minas-Rio remains intact (cont.)

    BUSINESS CASE FOR MINAS-RIO REMAINS INTACT (CONT.) Maintains a low cost position High quality & low contaminant product 160 10% 150 140 Australia - high quality 130 8% Australia - 120 medium quality India Other Africa 110 CIS CIF cost China (US$/t) 100 Alumina + silica content 6% 90 80 China (1) Nor

  6. Slide 6: ... but Brazil is a developing country

    ... BUT BRAZIL IS A DEVELOPING COUNTRY Evolving regulatory environment - Cost pressures and skill shortages in Brazil a challenge for many projects are real in Brazil 310 12 Brazilian components escalation (index 2006 =100) Project Capex Delay escalation (months) 280 (%) 10 Brazilian unemployment ra

  7. Slide 7: Project Overview

    PROJECT OVERVIEW Mine and Beneficiation (Minas Gerais) Port (RJ) Pipeline 525 km 5.8b US$c.30/t 26.5 Mtpa initially 68% Fe Resources Cash cost (FOB) Up to 90 Mtpa in expansion Pellet feed 7

  8. Slide 8: Continuing progress during the past 12 months

    CONTINUING PROGRESS DURING THE PAST 12 MONTHS At end of 2012 At end 2011 Beneficiation plant • Earthworks nearing completion 92% 79% • Concrete poured 79,000 m3 29,000 m3 • Release of caves for construction 4 of 4 (September 2012) 2 of 4 • Tailings dam land access 21 of 21 secured 8 of 21 secured •

  9. Slide 9: Capex escalation reconciliation

    CAPEX ESCALATION RECONCILIATION $bn 0.6 0.8 0.5 0.2 0.3 1.0 8.8 8.2 5.8 Approved FOOS delay Impact of Escalation FX net of Capex review Revised Contingency Revised budget licences and and price hedge items budget budget incl. agreements amendments contingency 9

  10. Slide 10: Key short term schedule risks

    KEY SHORT TERM SCHEDULE RISKS FOOS date impact Context In the event of a 3-6 month Comments delay (from cut-off date) Mine • Active engagement with • Cave impacts the pre-stripping H1 2015 authorities • Cave 1 suppression activities (rainy season) • Authorisation anticipated in H1 and Mine Access •

  11. Slide 11: Improving project delivery

    IMPROVING PROJECT DELIVERY Efficiency Licensing and Permitting  Group reorganisation to allow Iron Ore Brazil (IOB) team  Licence office established to monitor and track licences, to solely focus on Minas-Rio project delivery permits and conditionings in advance of construction activities  IOB or

  12. Slide 12: Impairment considerations

    IMPAIRMENT CONSIDERATIONS Impairment considerations Carrying value • Base case valuation for impairment test does not Carrying value at 31 December 2012 $bn include the potential value from future Acquisition cost(1) 5.2 expansions to 90 Mtpa Capex to date 3.8 • Full impairment test included sensiti

  13. Slide 13: Key messages

    KEY MESSAGES • Medium and long term attractiveness and strategic • INSERT PHOTO positioning of Minas-Rio remains intact • Cost and schedule review completed, including a detailed re-evaluation of all aspects of the outstanding schedule, with a focus on maximising value and mitigating risk • Good pro

  14. Slide 14: Appendix

    AngloAmerican APPENDIX

  15. Slide 15: Beneficiation plant: current status and points of attention

    BENEFICIATION PLANT Current status and points of attention Key stats 53% complete 92% of beneficiation plant earthworks completed 43 of 187 transmission line towers released for construction 79,000 m3 of concrete poured to date ~4,000 people at site  Continuous focus on government relations LICENSI

  16. Slide 16: Pipeline: current status and points of attention

    PIPELINE Current status and points of attention Key stats 66% complete 76% cleared for pipe laying > 247 km ; ~50% of pipe laid 95% of 1,555 properties realised ~6,000 people at site FRONT 1 LICENCES  Complete relocation of legal reserves  Conclude final arrangements in partnership with Minas Gera

  17. Slide 17: Port: current status and points of attention

    PORT Current status and points of attention Key stats 52% complete 100% stackers and reclaimer erected 77% of Filtration Plant completed ~1,500 people at site BREAKWATER  Mobilise breakwater construction  Complete electromechanical activities CONSTRUCTION  Installation of ship loader PORT OPERATI

  18. Slide 18: Pre-operations: current status and points of attention

    PRE-OPERATIONS Current status and points of attention Key stats 46% complete 5.8 bn tons of mineral resources 1.4 bn tons of ore reserves 24h / 365d work shift 80 Mtpa material handled 5,400 employees CAVES / PRE-STRIPPING  Integrated planning with licensing team  Execute work plan to optimise str