Denison Mines Corp. · TSX:DML
Denison Mines — Investor Presentation (March 2017)
20 slides from Denison Mines's investor presentation, March 2017
Slide 1: Denison Mines Corp. Investor Update
Denison Mines Corp. Uranium Development & Exploration in the Athabasca Basin Investor Update March 2017 TSX: DML | NYSE MKT: DNN
Slide 2: Cautionary Statements & References
Cautionary Statements & References Cautionary Statements: This presentation includes forward-looking information or forward-looking statements under Canadian and U.S. securities laws that involve risks, uncertainties and other factors that could cause actual results to differ materially from those e
Slide 3: Uranium Development & Exploration: Wheeler River
Uranium Development & Exploration Northern Saskatchewan, Canada Wheeler River TSX: DML | NYSE MKT: DNN | 3
Slide 4: Wheeler River PEA: +20% IRR at US$44/lb U3O8
Wheeler River PEA : +20% IRR at US$44/lb U3O8 (1) STRATEGY: Co-development of the high-grade Gryphon and Phoenix deposits as a single underground mining operation, leveraging existing regional infrastructure, including assumed processing at Denison’s 22.5% owned McClean Lake mill Price Protected: 20
Slide 5: Wheeler River: CAD$1.4B NPV at US$62.60/lb U3O8
Wheeler River: CAD$1.4B NPV at US$62.60/lb U3O8 2016 Wheeler River Project Preliminary Economic Assessment(1) (100%) Assumptions / Financial Results Base Case Production Case Uranium Price US$44.00 US$62.60 Exchange Rate (CAD:USD) 1.35 1.35 Discount Rate 8.00% 8.00% Initial Capital Costs (100%) CAD$
Slide 6: One Project, Two High-Grade Deposits
One Project, Two High-Grade Deposits 2015 Wheeler River Property Mineral Resource Estimate Summary(1) Million lbs Million lbs Grade U3O8 U3O8 Deposit Category Tonnes (%U3O8) (100%) (Denison) Gryphon Inferred 834,000 2.3 43.0 25.8 Phoenix Indicated 166,000 19.1 70.2 42.1 Phoenix Inferred 9,000 5.8 1.
Slide 7: Wheeler River: Strategic Development Plan
Wheeler River: Strategic Development Plan Phase 2: Phoenix Production Phase 1: Gryphon Production • Underground freezing + Jet Bore mining • Conventional underground mining • 9 years at 7.0M lbs U3O8 / year (73t/d) (1) • 7 years at 6.0M lbs U3O8 / year (399t/d) (1) • Drift to Phoenix while mining Gr
Slide 8: Wheeler PEA Assumes Processing at 22.5% Owned McClean Lake Mill
(1) See IMPORTANT CAUTION REGARDING PEA on slide 4. Licensed Capacity: 24M lbs/yr U3O8 18M lbs/yr reserved for Cigar Lake 6M lbs/yr expected excess capacity Positive Processing Metallurgical Test Gryphon (97% recovery) Phoenix (98.1% recovery) PEA Includes Minor Wheeler PEA1 Assumes processing at Mi
Slide 9: Eastern Athabasca Basin: Reduced Risk Profile
Eastern Athabasca Basin: Reduced Risk Profile Existing Infrastructure Existing milling facility with excess capacity expected Existing provincial highways and provincial power grid Established mining jurisdiction and Gryphon social infrastructure 3 licensed uranium mills Provincial power g
Slide 10: DML's Initial CAPEX Estimated at CAD$336M
DML’s Initial CAPEX Estimated at CAD$336M 2016 Wheeler River Project Preliminary Economic Assessment(1) Capital Costs (CAD$ millions) Initial Sustaining Total Surface Infrastructure $166 $7 $174 Mine $220 $334 $554 Mineral Processing $19 $60 $79 Owners Costs $25 $0 $25 Decommissioning $0 $40 $40 Sub
Slide 11: Wheeler River: Avg. Operating Cost US$19.01
Wheeler River: Avg. Operating Cost US$19.01 2016 Wheeler River Project Preliminary Economic Assessment(1) Operating Costs (CAD$/lb U3O8) Gryphon Phoenix Mining $3.45 $17.45 Surface Transportation $1.63 $0.85 Mineral Processing (including tolling) $10.03 $8.03 General & Administration $4.17 $3.57 Tot
Slide 12: Looking Ahead at Wheeler River
Looking Ahead at Wheeler River PFS Preliminary Feasibility Project Assessment 2017-18 Production Study Construction 2019 2021-22 2025 2017 Budget: CAD$12.5M Denison’s Share: CAD$9.4M (75%) (Cameco funding 15%, JCU funding 10%) Agreement to increase ownership from 60% to up to ~66% by end of 2018
Slide 13: Mineralization at Gryphon Continues to Grow
Mineralization at Gryphon Continues to Grow Discovery of D Series Lenses Expansion of A and B Series lenses ~330 metres along strike Remain open to NE + SW Significant intersections Outside of current NI 43-101 up-dip and down-dip on mineral resource estimate the shallower, southwest portion
Slide 14: Mineralization at Gryphon Continues to Grow
Mineralization at Gryphon Continues to Grow WR-673 0.34% U3O8 over 7.5 m WR-675 WR-672A 1.38% U3O8 over 1.0 m 1.05% U3O8 over 1.0 m WR-507D2 19.31% U3O8 over 1.0 m WR-602D1 Notes: 0.94% U3O8 over 10.5 m, incl. 1. Results are reported as U3O8 weight % derived from 3.25% U3O8 over 1.5 m chemical assay
Slide 15: DML's Uniquely Diversified Asset Base
DML’s Uniquely Diversified Asset Base • Denison’s Flagship property in • Strategic high-grade AB uranium mill eastern Athabasca Basin (AB) • 6 M lbs/year excess • Gryphon + Phoenix milling capacity co-development • Currently toll milling • PEA completed 1H16 Wheeler McClean Cigar Lake ore with 20.4%
Slide 16: Portfolio Expands to Western Athabasca Basin
Portfolio Expands to Western Athabasca Basin Strategic Acquisition Denison acquired 80% interest in the Hook-Carter property from ALX Uranium Corp. Also acquired Coppin Lake project to consolidate Hook-Carter property 38 land claims = 19,572 hectares Significantly underexplored, with only 8
Slide 17: Denison & GoviEx Combine African Assets
Denison & GoviEx Combine African Assets ~25% Stake In GoviEx (TSX-V: GXU) Denison’s African Assets Transaction gives Denison exposure to GoviEx’s flagship Madaouela project in Niger, while finding a strategic home for Denison’s African assets Madaoulea is one of the world’s most advanced uranium
Slide 18: Investment Highlights
• Flagship Wheeler River Project (60%) – Gryphon + Phoenix Deposits have potential to generate +20% pre-tax IRR per PEA • Strategic ownership of the McClean Lake uranium mill (22.5%) • 350k+ hectares of strategic ground in the eastern Athabasca Basin • Significant internal sources of cash flow – Min
Slide 19: Corporate Information
Corporate Information Market Summary Management & Directors Exchanges TSX: DML, NYSE MKT: DNN Lukas Lundin (Executive Chairman) Shares Outstanding(1) 533.4 M David Cates (President & CEO) Warrants(1) nil Mac McDonald (VP Finance & CFO) Options(1) 7.4 M Peter Longo (VP Project Development) Fully Dilu
Slide 20: Investor Update
Investor Update TSX: DML NYSE MKT: DNN Phone: Email: Online: 416.979.1991 x366 info@denisonmines.com denisonmines.com or 1.888.689.7842 @DenisonMinesCo