Slide 1: Boral Berrima Cement – Whole of Community Meeting
Build something great™ BORAL BERRIMA CEMENT > ‘Whole of Community’ Meeting 2 August 2018 E2 Events Berrima
Slide 2: Agenda
Agenda ˃ Welcome, introductions, safety moment, administration ˃ Year in Review: Production and Safety ˃ Solid Waste Derived Fuels Project: Update ˃ Year in Review: Environment ˃ Year in Review: Community ˃ General Business
Slide 3: Introductions and safety moment
Introductions and safety moment ˃ Stuart Hutchings Operations Manager (NSW), Boral Cement ˃ Ibrahim Muharrem Environment Manager, Boral Cement ˃ David Spears Senior Project Manager, Boral Cement Engineering Services ˃ Michael Curley Occupational Health & Safety Manager, Boral Cement ˃ Madeline Westn
Slide 4: Administration
Administration ˃ Previous community meeting ˃ 27 July 2017 ˃ Note: Presentations from previous meetings are available from the Cement Works website – www.boral.com.au/berrimacement ˃ Any matters arising? ˃ Apologies for this meeting
Slide 5: Year in Review: Production and Safety
Build something great™ BORAL BERRIMA CEMENT > Year in Review: Production and Safety
Slide 6: Year in Review – Safety
Year in Review – Safety ˃ Safety at Berrima is focussed on high risk areas. ˃ Leading KPIs: ↑50% active monitoring, ↑30% Berrima Employee & Contractor Injury Count hazard reporting over last two years. Lost time injuries (LTI) and medical treatment injuries (MTI) ˃ My Lock, My Life: Improved isolati
Slide 7: Year in Review – Production
Year in Review – Production ˃ Production and Sales ˃ It has been another strong year in terms of production and sales at Berrima. ˃ Equivalent grey clinker production in FY18 was 1.482 mtpa, the second highest production since the kiln upgrade of 2004. ˃ 1.384 mtpa grey clinker and 85.7 kt of off- w
Slide 8: Solid Waste Derived Fuels Project: Update
Build something great™ BORAL BERRIMA CEMENT > Solid Waste Derived Fuels Project: Update
Slide 9: Solid Waste Derived Fuels – Project Update
Solid Waste Derived Fuels – Project Update ˃ The new Solid Waste Derived Fuels (SWDF) feed system is now fully constructed and is being commissioned. ˃ Subject to final EPA and DPE sign off for trial protocols, the first fuel will be fed to the kiln around mid-August. ˃ Performance trials and plant
Slide 10: SWDF – Building our new energy future
SWDF – Building our new energy future https://vimeo.com/279194086/f53ab4b632
Slide 11: Year in Review: Environment
Build something great™ BORAL BERRIMA CEMENT > Year in Review: Environment
Slide 12: Environmental Management: Year in Review
Environmental Management: Year in Review ˃ All required environmental management information is published on Berrima Cement’s website - www.boral.com.au/berrimacement. ˃ Information published includes: ˃ Environmental monitoring and reporting requirements, including external audits. ˃ Environmental
Slide 13: Noise Monitoring – Licence Year 2017-2018
Noise Monitoring - Licence Year 1/5/2017 – 30/4/2018 ˃ Extensive (annual) noise monitoring undertaken within licence year period. ˃ Monitoring showed the site is compliant with noise limits stipulated in site’s licence. ˃ Monitoring and reporting undertaken by external contractors. ˃ Recommendations
Slide 14: Air Quality Management
Air Quality Management ˃ Stack Monitoring Continuous Monitoring of Solid Particulates graphed over time Last stack testing results undertaken for cadmium, mercury and hazardous substances
Slide 15: Air Quality Management
Air Quality Management ˃ Dust Deposition – graph of historical results and gauge location map
Slide 16: Air Quality Management
Air Quality Management ˃ Ambient Air Monitoring Program - HVAS
Slide 17: Water Quality Management
Water Quality Management ˃ Lake Quality Overflow ˃ One overflow event during last year’s reporting period (27 February 2018). ˃ SWDF construction was occurring at this time ˃ Results from water sampled from overflow point (EPA Point 9) were: ˃ Biochemical Oxygen Demand (mg/L): <2 (Guideline: 20) ˃ O
Slide 18: Recent Activities
Recent Activities ˃ Pest Control update ˃ Rabbit baits currently in use. ˃ Dust Management ˃ Our air quality emissions are within limits, however we are always looking for ways to improve our dust management on site. ˃ Continually review process and procedures including equipment used. ˃ Further nat
Slide 19: Reminder – Pollution Incident Response Register
Reminder – Pollution Incident Response Register ˃ Our obligations under the NSW Protection of the Environment Act 1997 require a procedure for notifying the community if a ‘pollution incident’ occurs. ˃ Examples include significant oil or hydrocarbon spills, release of high volumes of alkaline water
Slide 20: Year In Review: Community / General Business
Build something great™ BORAL BERRIMA CEMENT > Year In Review: Community / General Business
Slide 21: Community Liaison Group (CLG)
Community Liaison Group (CLG) ˃ At our last community meeting (Jul 2017), we announced we’d be changing our community engagement approach. ˃ Closer alignment to Cement Works planning consent ˃ Address long run of declining attendances at regular community meetings ˃ The model includes an annual ‘who
Slide 22: Community support and participation
Community support and participation ˃ Boral Cement Berrima continues to be an active corporate citizen of the Southern Highlands through its support of, and participation in, community initiatives. ˃ During the past year, some of these have included: ˃ Southern Highlands Science & Engineering Challe
Slide 23: General business and contacts
General business and contacts ˃ Items of general business ˃ Next meetings ˃ Community Liaison Group – re-formation by end of 2018 ˃ Next ‘Whole of Community’ meeting will be Jul-Aug 2019 unless needed earlier ˃ Boral Berrima Cement contacts: ˃ Berrima Cement Works Reception 4860 2222 / madeline.west
Slide 24: Thank you for your attendance
Build something great™ BORAL BERRIMA CEMENT > Thank you for your attendance