Lion Finance Group PLC · LSE:BGEO

Lion Finance — Georgia Global Utilities — Investor Presentation (October 2017)

26 slides from Lion Finance's investor presentation, October 2017

  1. Slide 1: Georgia Global Utilities Investor presentation

    Slide 1: Georgia Global Utilities Investor presentation

    Georgia Global Utilities Investor presentation October 2017

  2. Slide 2: Contents

    Slide 2: Contents

    Contents • General overview • Water utility • New energy projects • Appendix GGU October 2017 page 2

  3. Slide 3: GGU Group

    Slide 3: GGU Group

    GGU Group Water Energy Operating HPPs GWP - Tbilisi Water Zhinvali HPP (130.0MW) Rustavi Water Mtskheta Water Gardabani WWTP Tetrikhevi HPP Saguramo HPP Pshavela HPP2 (12.0MW) (4.4MW) (2.9MW) At a glance Committed project 520 m3 Mestiachala HPP Zoti HPP p.a.1 (50MW) (44.3MW) (Under construction) (Un

  4. Slide 4: GGU structure by shareholders and activities

    Slide 4: GGU structure by shareholders and activities

    GGU structure by shareholders and activities BGEO RP Group Global 100% 35% GGU Water Energy Utility Tbilisi Rustavi Mtskheta 149.3MW 150MW 150MW 50MW Gardabani 50MW 44.3MW Water Water Water Existing Pipeline Pipeline Pipeline WWTP UC Hydro UD Hydro Utility Utility Utility Hydro Hydro Wind Solar • Na

  5. Slide 5: Partnership in hydro & other renewables

    Slide 5: Partnership in hydro & other renewables

    Partnership in hydro & other renewables 1 BGEO Group 2 RP Global Georgia focused investment platform Austria-based renewables IPP 65% majority shareholder 35% shareholder Georgia’s leading investment platform. 30 years experience in developing, building, Owns & operates 149.3 MW of hydro power capac

  6. Slide 6: GGU strategy

    Slide 6: GGU strategy

    GGU strategy CURRENT STANDING MEDIUM TERM GOAL TARGETING 1 IPO in 2-3 years time WATER REVENUE 2016: GEL 117.1m DIVIDEND UTILITY EBITDA 2016: GEL 56.7m EBITDA 2019: GEL 70+ m PROVIDER 2 REVENUE 2016: GEL 15.0m EBITDA 2016: GEL 11.8m EBITDA 2019: GEL 38+ m VALUE CREATION ENERGY UPSIDE 149MW existing

  7. Slide 7: GGU management team

    Slide 7: GGU management team

    GGU management team Archil Gachechiladze Giorgi Vakhtangishvili Chief Executive Officer Chief Financial Officer - Joined GGU in November 2016 - Joined GGU in April 2015 - Previously served as Deputy CEO, Corporate & Investment Banking at - Previously held different managerial positions at BGEO Group

  8. Slide 8: Contents

    Slide 8: Contents

    Contents • General overview • Water utility • New energy projects • Appendix GGU October 2017 page 8

  9. Slide 9: GGU – a privately-owned natural monopoly

    Slide 9: GGU – a privately-owned natural monopoly

    GGU – a privately-owned natural monopoly GGU is the only profitable water-utilities player in Georgia with plenty of efficiency rooms GGU is the largest privately owned water utility company in Company has strong execution track record & financial Georgia strength • 2 core activities: • Management t

  10. Slide 10: GGU business lines

    Slide 10: GGU business lines

    GGU business lines Two revenue streams, each with solid cash generation capabilities Revenue Operating figures (2016A) Overview 1 Water – Owns and operates entire network for – Revenue – GEL 117.1m Supply and water supply and sanitation services - Sanitation pumping stations, reservoirs, Power, – Nu

  11. Slide 11: GGU water sales

    Slide 11: GGU water sales

    GGU water sales Overview Number of clients 2011-2016 – Water is sourced from Zhinvali reservoir (90%) and Mukhrani/Natakhtari (10%) aquifer to feed the cities of Tbilisi, Rustavi and Mtskheta 543,527 527,137 517,260 502,103 488,750 – Customer pool includes both legal entities and households: 456, 74

  12. Slide 12: GGU infrastructure network overview - Tbilisi

    Slide 12: GGU infrastructure network overview - Tbilisi

    GGU infrastructure network overview - Tbilisi GGU owns 100% of the infrastructure – Company operates c. 2,700km of water supply and c. 1,700km of wastewater pipeline network which consists of: trunk lines, tunnels of potable water and aqueducts, distribution networks to customers – Around 522m m3 of

  13. Slide 13: GGU P&L (2016)

    Slide 13: GGU P&L (2016)

    GGU P&L (2016) y-o-y % Numbers are given in GEL, thousand 2016A 2015A change - Total water sales increased by 4.4% as compared REVENUES to LY comparative results Revenue from water supply to legal enteties 78,139 74,587 4.8% Revenue from water supply to individuals 31,264 30,170 3.6% - Increase of e

  14. Slide 14: GGU P&L (1H17)

    Slide 14: GGU P&L (1H17)

    GGU P&L (1H17) y-o-y % Revenues Numbers are given in GEL, thousand 1H17A 1H16A change - Electric power sales declined due to lower REVENUES generation of Zhinvali HPP Revenue from water supply to legal entities 38,928 36,384 7.0% Revenue from water supply to individuals 16,053 15,132 6.1% - Revenue

  15. Slide 15: Contents

    Slide 15: Contents

    Contents • General overview • Water utility • New energy projects • Appendix GGU October 2017 page 15

  16. Slide 16: Projects going forward in hydro & other renewables

    Slide 16: Projects going forward in hydro & other renewables

    Projects going forward in hydro & other renewables 2017 50 MW HPP (Svaneti Hydro) 2018 Status – Under construction Project cost – USD 62.7m 44.3 MW HPP (Zoti Hydro) Long-term pipeline1 Completion – by the end of 2018. Status – Under development Project cost – USD 57.5m Hydro Completion – by the end

  17. Slide 17: Mestiachala / 50 MW

    Slide 17: Mestiachala / 50 MW

    Mestiachala / 50 MW Project main characteristics Project highlights Total project cost (US$ k) 62,720 • Location – near city Mestia, Svaneti region Total cost per MW (US$ k) 1,254 • Cascade of 2 power plants Nominal installed capacity (MW) 50.1 • Penstock routes – 10 km • Total – 2 powerhouses with

  18. Slide 18: Zoti / 44.3 MW

    Slide 18: Zoti / 44.3 MW

    Zoti / 44.3 MW Project main characteristics Project highlights Total project cost (US$ k) 57,485 • Location - village of Zoti, Guria region in Western Total cost per MW (US$ k) 1,297 Georgia Nominal installed capacity (MW) 44.3 • Cascade of 2 power plants • 2 tunnels – 1.2 km and 1.6 km Net annual g

  19. Slide 19: Wind projects

    Slide 19: Wind projects

    Wind projects Identifying wind project opportunities • Feasibility MoUs signed with government for all 7 projects in early 2017 • Land securing for Tkibuli, Kutaisi and Tbilisi projects to be finalized by December, 2017 • Based on preliminary findings 3 main locations are defined as stage 1 developm

  20. Slide 20: Solar projects

    Slide 20: Solar projects

    Solar projects Identifying solar project opportunities • Exclusivity Feasibility MoU with the Government was signed in early 2017 for 18 months Ksani Gldani Kaspi – 50 Saakadze MW Akhaltsikhe I Gardabani I Marneuli – 50 MW Akhaltsikhe II Gardabani II Algeti Further measurement stage Early feasibilit

  21. Slide 21: Contents

    Slide 21: Contents

    Contents • General overview • Water utility • New energy projects • Appendix GGU October 2017 page 21

  22. Slide 22: Utilities in Georgia – largely private, reforms in progress

    Slide 22: Utilities in Georgia – largely private, reforms in progress

    Utilities in Georgia – largely private, reforms in progress Utility sector in is largely privatized with high barriers to entry; reforms in progress for approximating the sector with the EU regulations – Utilities sector represents ~3% of total economic output in Georgia 1,800 1,589 mn, GEL 1,600 CA

  23. Slide 23: Water utilities – capitalizing on efficiency gains

    Slide 23: Water utilities – capitalizing on efficiency gains

    Water utilities – capitalizing on efficiency gains Underdeveloped industry offers ample potential for efficiency gains and long-term sustainable growth Water balance (m3), 2015 – Significant funding-gap in the past has led to largely depreciated water and sanitation infrastructure with an average te

  24. Slide 24: Water and Energy Tariff Setting Methodology

    Slide 24: Water and Energy Tariff Setting Methodology

    Water and Energy Tariff Setting Methodology Existing assets Net book value WACC Return on assets New CAPEX Depreciation Costs for water supply Total operating and Costs for maintenance expenses waste water Taxes Regulated revenue (annual determination) GGU October 2017 page 24

  25. Slide 25: Electricity market update

    Slide 25: Electricity market update

    Electricity market update Current installed capacity by types, MW Electricity supply and consumption Forecasted consumption Source: ESCO 23,000 MW HPP – More than 70 HPPs are under operation currently, with 3,164MW of MW Forecast total installed capacity. 7 conventional dam HPPs make up 68% of 1,400

  26. Slide 26: Disclaimer – forward looking statements

    Slide 26: Disclaimer – forward looking statements

    Disclaimer – forward looking statements This presentation contains forward-looking statements that are based on current beliefs or expectations, as well as assumptions about future events. These forward-looking statements can be identified by the fact that they do not relate only to historical or cu

Source: Internet Archive copy of bankofgeorgiagroup.com