Whitehaven Coal — H1 FY2010 Earnings Presentation

42 slides from Whitehaven Coal's earnings presentation, Feb 24, 2010

  1. Slide 1: ASX Company Announcement: Half Year Results Presentation

    24 February 2010 Australian Stock Exchange Company Announcements HALF YEAR TO 31 DECEMBER 2009 – RESULTS PRESENTATION Please find attached WHC’s Half Year Results Presentation which will be delivered by the Managing Director to analysts and the media later this morning. Yours Faithfully Timothy Burt

  2. Slide 2: Delivering Growth: First Half FY 2010 Results

    Whitehaven Coal Limited Delivering Growth First Half FY 2010 Results Sydney, Australia 24 February 2010

  3. Slide 3: Disclaimer

    Disclaimer Statements contained in this material, particularly those regarding the possible or assumed future performance, costs, dividends, returns, production levels or rates, prices, reserves, potential growth of Whitehaven Coal Limited, industry growth or other trend projections and any estimate

  4. Slide 4: Qualifications and Statement

    Qualifications and Statement Information in this report that relates to Coal Resources and Reserves is based on and accurately reflects reports prepared by the Competent Person named beside the respective information. All these persons are consultants for Whitehaven Coal Limited. Mr Colin Coxhead is

  5. Slide 5: Contents

    Contents ► Highlights ► Operating and financial results ► Status of growth plans ► Outlook 3 Half Year Results - February 2010

  6. Slide 6: First half financial highlights - FY 2010

    First half financial highlights - FY 2010 ► Net profit after tax (NPAT) of $83.5 million1 ► Underlying NPAT (excluding Significant Items) of $27.1 million, up 35% ► Interim fully franked dividend of 2.8 cents per share2 ► Average cost of sales per tonne down 10% from last year ► EBITDA of $53.9 mill

  7. Slide 7: First half operating highlights - FY 2010

    First half operating highlights - FY 2010 ► Coal sales up 32% (equity basis) ► Saleable coal production up 50% (equity basis) ► All operations performed well in terms of safety, environmental management, production and cost control ► Expansion of saleable open-cut coal production to 5.5 Mtpa, by Q3

  8. Slide 8: First half business development highlights - FY 2010

    First half business development highlights - FY 2010 ► Coal Resources (JORC) increased by 56% to 1,190.4 Mt ► Marketable Coal Reserves (JORC) increased by 16% to 322.7 Mt ► Purchased the Vickery coal assets from Coal & Allied for $31.5 million plus 1,150 ha of land ► Accelerated exploration program

  9. Slide 9: Contents

    Contents ► Highlights ► Operating and financial results ► Status of growth plans ► Outlook 7 Half Year Results - February 2010

  10. Slide 10: First half coal sales – FY 2010

    First half coal sales – FY 2010 Equity Basis – 000t H1 - FY 2009 H1 - FY 2010 Change Gunnedah Operations 1,160 1,556 +34% Werris Creek 425 541 +27% Whitehaven Total 1,585 2,097 +32% 100% Basis – 000t H1 - FY 2009 H1 - FY 2010 Change Gunnedah Operations 1,400 1,786 +28% Werris Creek 425 541 +27% Whit

  11. Slide 11: First half saleable coal production – FY 2010

    First half saleable coal production – FY 2010 Equity Basis – 000t H1 - FY 2009 H1 - FY 2010 Change Gunnedah Operations 685 1,155 +69% Werris Creek 466 570 +22% Whitehaven Total 1,151 1,725 +50% 100% Basis – 000t H1 - FY 2009 H1 - FY 2010 Change Gunnedah Operations 949 1,394 +47% Werris Creek 466 570

  12. Slide 12: First half profitability – FY 2010

    First half profitability – FY 2010 Reported Financial Performance - A$ millions H1 - FY 2009 H1 - FY 2010 Revenue 275.7 198.5 NPAT before Significant Items 20.0 27.1 NPAT 201.5 83.5 Earnings per share (cents per share - diluted) 5.0 5.8 Interim dividend (cents per share - fully franked) 2.5 2.8 Unde

  13. Slide 13: First half cost of sales down 10% from last year

    First half cost of sales down 10% from last year A$/t FOB H1 - FY 2009 H1 - FY 2010 Coal Sales - 000t (equity basis, excl. purchased coal) 1,012 1,649 Average revenue - (excl. purchased coal & net of NSW royalties) 154.94 95.15 Average cost of sales 65.83 59.25 EBITDA 89.11 35.90 EBITDA Margin - % 5

  14. Slide 14: First half cash flow – FY 2010

    First half cash flow – FY 2010 A$ millions H1 - FY 2009 H1 - FY 2010 Cash generated from operations 31.4 36.1 Interest and tax payments (8.7) (89.0) Net cash provided by/(used) in operating activities 22.7 (52.9) Proceeds from sale of assets 41.7 86.1 Capital investment (excluding leasing) (76.2) (1

  15. Slide 15: 31 December financial position

    31 December financial position A$ millions Dec 31 - 2008 Dec 31 - 2009 Cash 76.6 232.6 Current receivables 172.4 251.7 Other current assets 53.1 90.2 Current assets 302.1 574.5 Non-current receivables 157.0 72.2 Other non-current assets 462.7 646.1 Total assets 921.8 1,292.8 Current payables 40.2 71

  16. Slide 16: First half capex – FY 2010

    First half capex – FY 2010 Capital Investment - $ million H1 - FY 2009 H1 - FY 2010 Tarrawonga 1 1.3 3.3 Werris Creek 26.1 25.0 Rocglen 24.5 1.7 Sunnyside 16.8 1.9 Gunnedah CHPP 1.8 0.1 Total Open-cuts 1 70.5 32.0 Narrabri 1 91.7 57.7 New coal train - 19.2 Exploration - 2.2 Land/other 4.3 3.2 Total

  17. Slide 17: Contents

    Contents ► Highlights ► Operating and financial results ► Status of growth plans ► Outlook 15 Half Year Results - February 2010

  18. Slide 18: Coal Resources up 56%, Marketable Reserves up 16%

    Coal Resources up 56%, Marketable Reserves up 16% COAL RESOURCES – FEBRUARY 2010 (100% Basis) Measured Indicated Inferred Total Mining District Resource Resource Resource Resources GUNNEDAH OPERATIONS Opencut 48.24 97.26 37.4 182.9 GUNNEDAH OPERATIONS Underground 8.44 40.29 62.1 110.8 WERRIS CREEK O

  19. Slide 19: Bluevale (formerly Vickery) added to resources

    Bluevale (formerly Vickery) added to resources ► Whitehaven recognised the value of Gunnedah Basin coal early and has built up a large resource base over 11 years ► Narrabri was the last large Exploration Licence (EL) issued under the old NSW system, i.e. without competitive tender ► Transactions si

  20. Slide 20: Accelerated exploration program - $5m budget in 2010

    Accelerated exploration program - $5m budget in 2010 ► Whitehaven has a very large tenement holding between Gunnedah and Boggabri (including Bluevale) which has not been explored fully ► Substantial potential exists to increase coal resources and reserves ► Exploration efforts are currently focussed

  21. Slide 21: Bluevale (formerly Vickery) has a large coal inventory

    Bluevale (formerly Vickery) has a large coal inventory ► Exploration in the Bluevale area is focussed on: ► extending the known Bluevale open-cut area ► defining underground resources and reserves ► Coal seams being explored include the Shannon Harbour, Stratford, Bluevale, Cranleigh and Gundawarra

  22. Slide 22: Expansion of open-cuts to 5.5 Mtpa saleable underway

    Expansion of open-cuts to 5.5 Mtpa saleable underway ► Werris Creek Mine (WHC 100%)  Reserves to support 15 – 20 year LOM  Permitted to 2.0 Mtpa  PCI and thermal coals  Saleable coal yield 100%  Own crushing and rail load-out ► Tarrawonga Mine (WHC 70%)  Reserves to support 15 – 20 year LOM 

  23. Slide 23: Gunnedah CHPP and rail loader being upgraded

    Gunnedah CHPP and rail loader being upgraded ► Gunnedah CHPP (WHC 100%) ► Permitted to handle and rail 4.0 Mtpa saleable coal ► Being upgraded to handle planned 3.5 Mtpa saleable production from Tarrawonga, Rocglen & Sunnyside ► Remaining 2.0 Mtpa saleable open- cut coal will be crushed and loaded f

  24. Slide 24: Narrabri underground mine development - Stage 1

    Narrabri underground mine development - Stage 1 ► Coal resources of 854.6 Mt in single seam of 8-9 metres thickness ► Marketable reserves of ~199.9 Mt based on extracting the bottom 4.2 metre section of the seam ► Low ash, high energy, low sulphur PCI and thermal coals for the export market ► Saleab

  25. Slide 25: Narrabri longwall mine plan

    Narrabri longwall mine plan ► Seam thickness 8-9 metres ► 26 longwall panels ► Full panel length 4,000 metres ► 300 metre panel width ► 6 Mt panels at 4.2 metre mining height ► Potential for 12 Mt panels with top coal caving ► High productivity expected due to thickness and continuity of the coal se

  26. Slide 26: Narrabri Mine – construction almost complete

    Narrabri Mine – construction almost complete ► Kamilaroi Hwy Upgrade ► Earthworks & Rehab ► Access & Kurrajong Rds ► 66kv Transmission Line ► Rail Loop ► Ventilation Fans ► Industrial & Admin ► Mine Entries ► Sewerage Plant ► Boxcut ► Mining Equipment ► Crushing Plant ► Train Loadout ► Drift Constru

  27. Slide 27: Drift drivage delayed by difficult ground conditions

    Drift drivage delayed by difficult ground conditions ► Initial sandstone layer driven with road headers from the box cut ► Expected the hard dolerite layer to need drill & blast – this went to plan with good performance ► Underlying soft material expected to be good for road headers, but was too sof

  28. Slide 28: Narrabri Stage 2 progressing well

    Narrabri Stage 2 progressing well ► Stage 2 proposal lodged with the NSW Government for approval; progressing through the system as expected ► Longwall ordered in September 2009, for delivery in late 2010 ► Ventilation shaft, CHPP and other key Stage 2 facilities designed, tendered and ready to cons

  29. Slide 29: Preliminary evaluation of top coal caving for Narrabri

    Preliminary evaluation of top coal caving for Narrabri ► First 2 longwall panels will mine 4.2 metre bottom section & will provide experience of caving & geo-tech characteristics ► Potential thereafter for top coal caving (TCC) which could: ► Recover most of the 8-9 metre coal seam; increase resourc

  30. Slide 30: Narrabri can produce PCI coal, up to 40% of ROM

    Narrabri can produce PCI coal, up to 40% of ROM ► Coal quality and washability analyses of large diameter bore-cores from Narrabri indicate potential to produce substantial quantities of PCI coal ► By adding a dense-medium cyclone (DMC) to the planned Stage 2 CHPP, indications are that ~40% of ~7.5%

  31. Slide 31: Rail infrastructure to meet Whitehaven’s growth

    Rail infrastructure to meet Whitehaven’s growth ► Whitehaven (60%) and Idemitsu (40%) sponsored RIC and ARTC investments which have increased rail track capacity north of Muswellbrook, to meet the needs of Whitehaven & Idemitsu ► In return, Whitehaven and Idemitsu have rights to track capacity north

  32. Slide 32: Port infrastructure to meet Whitehaven growth

    Port infrastructure to meet Whitehaven growth ► Newcastle Coal Infrastructure Group (“NCIG”) ► Whitehaven owns 11% of NCIG....Stage 1 is due to be commissioned in March ► Stage 1 capacity of 30 Mtpa will be available to NCIG members pro-rata to shareholding ► Stage 2 capacity of a further 36 Mtpa ex

  33. Slide 33: NCIG first train arrival, February 2010

    NCIG first train arrival, February 2010 31 Half Year Results - February 2010

  34. Slide 34: NCIG first coal receival, February 2010

    NCIG first coal receival, February 2010 32 Half Year Results - February 2010

  35. Slide 35: Contents

    Contents ► Highlights ► Operating and financial results ► Status of growth plans ► Outlook 33 Half Year Results - February 2010

  36. Slide 36: Low-risk open cut production base with substantial growth from Narrabri

    Low-risk open cut production base with substantial growth from Narrabri ► Four existing open-cut mines can produce up to ~5.5 Mtpa. More WHC - SALEABLE PRODUCTION CAPACITY VS PORT CAPACITY open-cut capacity in future from existing resources + Bluevale 12,000 ► Total saleable production capacity for

  37. Slide 37: Managing sales and production growth

    Managing sales and production growth ► Advantages of high quality coal & flexibility in production from existing open-cut mines ► Our forward coal sales contracts support WHC’s growth profile ► Our matrix of coal sales contracts & commitments minimises production and infrastructure risks ► A$ forwar

  38. Slide 38: Fixed price coal contracts and fixed FX status

    Fixed price coal contracts and fixed FX status ► “Legacy” thermal coal contracts of 5.2 Mt will remain over the FY 2011 and FY 2012 years with an average fixed price of US$69.14/t ► Whitehaven currently has a total FX fixed position of US$408.7m at an average exchange rate of 0.7784 US$:A$ ► 100% of

  39. Slide 39: Coal market outlook

    Coal market outlook ► Coal demand growth remains strong ► Supply still constrained by infrastructure and ever-increasing “red tape” & “green tape” ► Contract coal prices in 2009 – US$ FOB ► Hard coking coal ~$128/t ► Newcastle semi-soft/PCI ~$80/t ► Newcastle thermal ~$70/t ► Spot coal prices – US$

  40. Slide 40: Growth plans are well funded

    Growth plans are well funded Capacity for funding new opportunities Major Cash Needs A$ million ► Major capital needs are more Narrabri Stage 1 20 than covered by cash on hand Narrabri Stage 2 210 and proceeds from the sale of Narrabri JV interests Open-cut expansion 50 Coal train 20 ► In addition,

  41. Slide 41: Looking further ahead

    Looking further ahead ► Strong fundamental growth in demand for coal remains (both metallurgical and thermal) ► Whitehaven is well positioned ► Large resources and reserves of high quality coal ► Efficient, flexible open-cut mines, competitive costs ► Narrabri to provide substantial growth ► Increas

  42. Slide 42: Delivering Growth: First Half FY 2010 Results

    Whitehaven Coal Limited Delivering Growth First Half FY 2010 Results Sydney, Australia 24 February 2010