  1. Slide 1: AGL Camden Gas Project Update

    AGL Camden Gas Project Update November 2019

  2. Slide 2: About the Camden Gas Project

    About the Camden Gas Project

  3. Slide 3: Fast facts

    Fast facts Camden Gas Project fields: • Began producing in 2001 • 60km southwest of Sydney, in the Camden, Wollondilly and Campbelltown LGAs • Produces approximately 5% of NSW’s gas supply (that’s about how much gas 265,000 homes use in a year) • 100km of low-pressure gas gathering lines 144 wells h

  4. Slide 4: Timeline

    Timeline 2002 2001 The addition of three production wells under PPL 2, bringing the Sydney Gas applies for PPL1. total of drilled production wells to 25. 2004 Operation of the Rosalind Park 2009 Gas Plant commenced. The The Camden Gas Project project expanded to include becomes wholly owned by AGL.

  5. Slide 5: Decommissioning & Rehabilitation – Whole Project Timeline

    Decommissioning & Rehabilitation – Whole Project Timeline Camden Rehabilitation Project - Whole Project Projected Preliminary Timeline Calendar Year End 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 Indicative Number of 124 114 104 96 90 85 80 60 40 20 0 Remaining Wells Phase-1 Ph

  6. Slide 6: Decommissioning and Rehabilitation

    Decommissioning and Rehabilitation

  7. Slide 7: Background

    Background • Decommissioning and Rehabilitation works towards ceasing production in 2023. • No new wells. • High level of regulatory oversight by the Department of Planning and Environment (DPE) and the NSW Environmental Protection Agency (EPA), following standards set in the NSW Government’s Code o

  8. Slide 8: The decommissioning process

    The decommissioning process • Residents are notified of upcoming works. • The equipment at the top of the well is safely removed. • A Workover Rig and other machinery comes to the well site. • Purpose-specific cement is placed inside the well from bottom to top in stages. • This cement seals the wel

  9. Slide 9: The rehabilitation process

    The rehabilitation process • Initial rehabilitation returns the surface of the site to the original contour of the land, usually seed is sown, or as agreed with the landowner. • Rehabilitation then continues over 12-24 months until both the regulator and landowner are satisfied. 9

  10. Slide 10: Decommissioning & Rehabilitation

    Decommissioning & Rehabilitation Since June 2019, AGL completed decommissioning activities at Menangle Park 05 (MP05), Elizabeth Macarthur 34 (EM34) and 22 (EM22), Sugar Loaf 09 (SL09) wells and is currently decommissioning Elizabeth Macarthur 40 (EM40). Surface rehabilitation of sites is continuing

  11. Slide 11: 12-month outlook

    12-month outlook During the next 12 months, we will prioritise workover well maintenance to improve production from Camden Gas Operations for AGL’s Customers. • Workover well maintenance o A number of wells will be visited by AGL Rig-1 to perform maintenance work to improve gas production. o Since J

  12. Slide 12: Landowner communication on workover and decommissioning access

    AGL continues to regularly communicate with landowners regarding access to well sites for planned workover maintenance and decommissioning activities on the land. Consultation occurs regarding surface rehabilitation of former well sites once decommissioning of the well is complete. AGL Camden Gas Pr

  13. Slide 13: Community

    Community

  14. Slide 14: AGL's Commitments to the Macarthur Region

    AGL’s Commitments to the Macarthur Region • The Camden Gas Project employs approximately 20 locals. • AGL aims to deliver community wide benefits, encourage innovation in and support for issues of community significance, and build and maintain strong relationships throughout the community. AGL and M

  15. Slide 15: How the community can contact AGL

    How the community can contact AGL Mail PO Box 67, Menangle NSW 2568 Web agl.com.au/Camden Phone (24-hour enquiries and complaints) 1800 039 600 Email aglcommunity@agl.com.au CCC CCC Independent Chair • provides a forum of open discussion between AGL and the community • Margaret MacDonald-Hill • aime

  16. Slide 16: Contact

    Contact Ernesto Calderon Community Relations Manager 1800 039 600 ECalderon@agl.com.au