Slide 1: Community Consultation Meeting
Community Consultation Meeting Oakdale West Estate February 2021 1
Slide 2: Overview
Overview Welcome and Introductions Consultation Requirements Project Update – OWE Project Update – WNSLR Project Update – Project Waratah Environmental Performance Safety Update Consultation and Community Interactions Stakeholder Feedback & Questions 2
Slide 3: Welcome and Introductions
Welcome and Introductions Project Team: Organisation Goodman AT&L SLR Consulting Ersed Role Proponent Project Manager & Contract Stakeholder Engagement Environmental Superintendent Representative Key Contacts Stephanie Partridge Alex Lohrisch Dan Thompson Carl Vincent Kym Dracopoulos Dane Segail Kat
Slide 4: Consultation Requirements - CEMP
Consultation Requirements - CEMP Condition D120 of SSD7348 requires • Project will be completed by Prime Goodman to consult with TfNSW, Constructions. Council and Water NSW prior to • Project is forecasted to commence in finalising the CEMP (Stage 1B & 1C). March ‘21 & finish in September ‘21. • Pri
Slide 5: Consultation Requirements – Staging Plan
Consultation Requirements – Staging Plan Condition B15 of SSD7348 requires Goodman to consult with relevant stakeholders on the staging plan for estate works and development. Diagram would fit in the space allocated here 5
Slide 6: Brickworks
= BRICKWORKS \ \ . “i N \ global environmental and advisory solutions
Slide 7: Progress To Date & Upcoming Works - OWE
Progress To Date & Upcoming Works - OWE • The internal road works are nearing completion over the next couple of months. • The final asphalt surfacing works are on schedule to commence mid February, • Utility infrastructure is in its final stages delivering essential services to the site. • There wi
Slide 8: Progress To Date – Compass Drive
Progress To Date – Compass Drive • Compass Drive and the bridge into the site has now been completed. • From Friday 12 February all Oakdale West Estate construction traffic will be via Compass Drive. • The road south of Lockwood Road will not be open for public access until dedication and while cons
Slide 9: Progress To Date & Upcoming Works – Lot 2B
Progress To Date & Upcoming Works – Lot 2B Progress to Date • Cladding Installation • Internal slabs installation • Roofing installation • Structural steel installation • Services installation • External slab installation Upcoming Works • Cladding Installation • Internal slabs installation • Roofing
Slide 10: Progress To Date & Upcoming Works – Lot 1A
Progress To Date & Upcoming Works – Lot 1A Progress to Date • Stormwater Installation • Bulk earthworks • Site establishment • Erosion & Sediment Control Installation Upcoming Works • Piling works • External Slab Preparation • Fire Tunnel Earthworks • Site Establishment 10
Slide 11: ER Inspections and Audits: SSD7348
ER INSPECTIONS AND AUDITS: SSD7348 ER INSPECTIONS 2019 TOTAL 3 2020 QTR1 (JAN-MARCH) 16 2020 QTR 2(APRIL-JUNE) 10 2020 QTR 3 (JULY-SEPT) 9 2020 QTR 4 (OCT-DEC) 7 2021 – QTR 5 PART (JAN) 3 TOTAL TO DATE 48 Copyright © ErSed 2011
Slide 12: ER Inspections and Audits: SSD7348
ER INSPECTIONS AND AUDITS: SSD7348 ER AUDITS THIS PERIOD DEC 20 • OWE (INFRASTUCTURE) • FIP • CAQMP • LOT 2B • CEMP – INDUCTIONS AND TRAINING • CTMP • WMP Copyright © ErSed 2011
Slide 13: Environmental Performance: SSD7348
ENVIRONMENTAL PERFORMANCE: SSD7348 NON COMPLIANCES, NON COMPLIANCE NIL QUARTER 4 - NIL Copyright © ErSed 2011
Slide 14: EC Inspections and Audits- SSD10397
EC INSPECTIONS AND AUDITS- SSD10397 INSPECTIONS AUDITS THIS PERIOD JULY 20 3 AUGUST 20 0 SEPTEMBER 20 1 OCTOBER 20 1 NOVEMBER 20 1 DECEMBER 20 1 JANUARY 21 0 FEBRUARY 21 1 TOTAL 8 Copyright © ErSed 2011
Slide 15: Environmental Performance- SSD10397
ENVIRONMENTAL PERFORMANCE- SSD10397 INCIDENTS AND COMPLAINTS AS DETAILED IN THE MONTLY REPORTS INCIDENTS 30 OCT 20 AN INCIDENT OCCURRED ON SITE ON 30/10/20. THIS INCIDENT DID NOT RESULT IN MATERIAL ENVIRONMENTAL HARM. AN INITIAL INCIDENT NOTIFICATION WAS MADE TO THE DPIE 2 NOV 20 IN ACCORDANCE WITH
Slide 16: Safety
Safety Minor incidents only 16
Slide 17: Consultation and Community Interactions
Consultation and Community Interactions • Correspondence with Neighbours regarding the removal of noise wall fencing and associated works and temporary storage. • Correspondence with Resident – Aldington Road re road conditions, water pressure and truck speeds. • Correspondence with Resident – Aldin
Slide 18: Communications and Consultation Channels
Communications and Consultation Channels Sources of information and complaints/enquiries via: • Website: oakdaleopportunities.com • Email: community.oakdalewest@goodman.com • Phone: 1300 002 887 • Post: Level 17, 60 Castlereagh Street, Sydney, NSW 2000 • Community Meetings: Subject to scheduling • E
Slide 19: Stakeholder Feedback & Questions
Stakeholder Feedback & Questions 19