  1. Slide 1: Public Water System Expansion

    Public Water System Expansion Litchfield Public Meeting Campbell High School October 25, 2016

  2. Slide 2: Project Overview

    Project Overview  On October 14, 2016 Pennichuck entered into a contract with Saint-Gobain Performance Plastics to begin the expansion of the current public water system in Litchfield  This is a two-phased project  Phase One has already begun  Phase Two will be completed in the Spring and early

  3. Slide 3: Phase One

    Phase One  Phase One objectives  Begin the installation of Water Mains in three simultaneous projects, starting at connection points to our existing water system in the town  Seeking to connect up to 173 properties in Phase One  The number of properties connected in Phase One will depend on weat

  4. Slide 4: Map of areas where the expansion of public water is being installed – both phases

    Map of areas where the expansion of public water is being installed – both phases 4

  5. Slide 5: Phase Two

    Phase Two  Phase Two objectives  Complete the installation of Water Mains in the three simultaneous projects, starting at the termination points from Phase One  Connection of all of the remaining  Construction on the Phase Two Water Mains to begin on or about April 1, 2017, weather permitting 

  6. Slide 6: Map of areas where the expansion of public water is being installed – both phases

    Map of areas where the expansion of public water is being installed – both phases 6

  7. Slide 7: Key Personnel

    Key Personnel  The Pennichuck team consists of the following individuals:  Chief Engineer – John Boisvert  Construction Manager – Mark Filion  Pennichuck Field Liaison – Victoria Bullard  Construction Inspectors  Pennichuck Employees  Pennichuck Inspector Subcontractors  Construction Company

  8. Slide 8: We will need to gain access to your home and property once again

    We will need to gain access to your home and property once again  In order to install the water service line to your home  A main to stop service line will be installed from the water mains in the streets to a shut-off valve (the “stop”) installed at your property line  A new service line will be

  9. Slide 9: How will you know that the person needing to access your property works for Pennichuck?

    How will you know that the person needing to access your property works for Pennichuck?  We will not seek to gain access to your home without a prearranged appointment  Please Note: There will be crews from Pennichuck or our subcontractors working in the area, but not directly on your property  A

  10. Slide 10: How will you know that the person needing to access your property works for Pennichuck?

    How will you know that the person needing to access your property works for Pennichuck?  If you would like to call the Company to confirm the identity of the individual, they will give you a card with the “800” number and their name on it, so you can call our Customer Service department to confirm

  11. Slide 11: What does it mean to be a customer of a public water system?

    What does it mean to be a customer of a public water system?  You will have access to water at your property which:  Is subject to compliancy with all of the State and Federal standards under the Safe Drinking Water Act  Is monitored and treated in compliance with these standards levels and testi

  12. Slide 12: What’s Next?

    What’s Next?  After the NHDES gives an update on their role in this process, including the following:  Discussion of private well decommissioning or continued use options  Point of Use Treatment Systems  Eligibility for these systems  Implementation of their installation  In the hallway, we ha

  13. Slide 13: Service Application Agreement

    Service Application Agreement 13

  14. Slide 14: New Customer Introduction Materials

    New Customer Introduction Materials 14

  15. Slide 15: Questions?

    Questions? 15

  16. Slide 16: Well Choices, POUs, and Next Steps

    Well Choices, POUs, and Next Steps Clark Freise Assistant Commissioner 16

  17. Slide 17: Existing Private Well Election

    25 Manchester Street PENNIGHUCK Sem ttas ——e Fax (603) 9132 Litchfield Public Water System Expansion Existing Private Well Election Saint-Gobain is funding the connection of your property to public water by Pennichuck because PFOA has been detected in the groundwater in your neighborhood. As part of

  18. Slide 18: Litchfield NH PFC Investigation

    LITCHFIELD NH PFC INVESTIGATION October 24, 2016 Eligible for Alternate Water (008 Arready Connected | EBB In Bid Connect This Year HB |r) Bid Connect Next Year Identified Pre Bid ADDL In Service Area HMI ADDL Outside Service Area GE Undeveloped *Requires Field Verification Transportation —— US/NH R

  19. Slide 19: Questions

    Questions Goal is to answer your questions personally. Pennichuck has individual folders by house. Any overarching questions? 19