Paladin Energy Ltd · ASX:PDN

Paladin Energy — Investor Presentation (May 2010)

32 slides from Paladin Energy's investor presentation, May 2010

  1. Slide 1: Paladin Energy Ltd – Investor Update May 2010

    Paladin Energy Ltd The New Energy In The Market Investor Update May 2010 V13.05.10

  2. Slide 2: Disclaimer

    Disclaimer This presentation includes certain statements that may be deemed “forward-looking statements”. All statements in this presentation, other than statements of historical facts, that address future production, reserve or resource potential, exploration drilling, exploitation activities and e

  3. Slide 3: Presentation Outline

    Presentation Outline • Paladin Status • U i Uranium S Supply l and dDDemand d • Projects Update • Future Outlook 3

  4. Slide 4: Paladin Status

    Paladin Status • Listed on Australian (ASX), Toronto (TSX) and Namibian ((NSX)) Stock Exchanges g – trades on Munich, Berlin Stuttgart and Frankfurt Exchanges – included in the MSCI Global Standard Indices, - ASX top 100 and Dow Jones African Titans 50 Index • Market Cap: A$2.7bn • Issued Capital: 7

  5. Slide 5: Value Proposition

    Value Proposition Paladin offers an extremely attractive investment offering at a time when the uranium market outlook remains uniquely positive. Uranium Producer Paladin is an (emerging Tier I global) uranium producer Fully Independent Paladin is the only non-aligned pure uranium producer Increasin

  6. Slide 6: March Quarter 2010 Highlights

    March Quarter 2010 Highlights • Record quarterly production of 1,157,375lb U3O8 • Langer Heinrich delivers full quarter at Stage 2 nameplate capacity. – production 928,370lb vs 841,995lb for previous quarter – Stage 3 construction remains on track for year-end commissioning • Kayelekera production s

  7. Slide 7: Paladin – A Mining House in the Making

    Paladin – A Mining House in the Making DEC 07 DEC 08 DEC 09 Cash on hand US$160M US$280M US$433M (400.6)* Shares on issue 601M 613M 716M Mkt Capital US$3.9bn US$1.2bn US$2.7bn LHM Stage 1 50% design 100% design 100% design Stage 2 Feasibility Construction 100% design Stage 3 - Feasibility Constructi

  8. Slide 8: Paladin proceeding with multi-staged parallel activities

    Paladin proceeding with multi-staged multi staged parallel activities Developing a complete company with 100% focus on achieving near term production targets. • Sustained production - LHM Stage 2 • Ramping up production - KM (73% of capacity) • E Expansion i (immediate) (i di t ) - LHM Stage St 3 (c

  9. Slide 9: Two Operating Uranium Mines in Two Years

    Two Operating Uranium Mines in Two Years WORLD FIRSTS ON BOTH OPERATIONS • New process technologies utilised • Langer Heinrich Mine – Alkaline Leach • Kayelekera Mine – Resin-in-Pulp • Prepared to take the up-front technical risk although this has presented ramp-up challenges • Gi Gives PDN a strong

  10. Slide 10: Paladin's Suite of Uranium Properties

    Paladin’s Suite of Uranium Properties staged for sequential development

  11. Slide 11: Resources and Reserves (April 2010)

    Paladin Energy Resources and Reserves (April 2010) Project Total Resources Total Reserves Attributable to Paladin 100% project basis Cut-off C t off Cut-off C t off ppm ppm t U3O8 Mlb U3O8 % U3O8 U3O8 t U3O8 Mlb U3O8 % U3O8 U3O8 Langer Heinrich (100%) 74,415 164.0 0.06 250 29,874 65.8 0.06 250 Kayel

  12. Slide 12: Presentation Outline

    Presentation Outline • Paladin Status • U i Uranium S Supply l and dDDemand d • Projects Update • Future Outlook 12

  13. Slide 13: Building a New Mining Supply Industry

    Building a New Mining Supply Industry 2007 to 2030 and beyond 2007 2020 2030 300 20M 290 (360) --------------------------------------------- 30M 220 (250) ------------------------------------------ 200 200M 72M 180M 100 108 108M 40M 90M 25-30 25 30 Huge discovery/development effort required (ADDITIO

  14. Slide 14: Global Uranium Production 2000 - 2008

    Global Uranium Production 2000 - 2008 Demand – remains robust Supply – static and not responding to both price and demand 130 487 120 360 50 112 315 110 50 100 90 nds U3O8 80 70 million poun 125 60 115 120 104.7 108.9 107.1 50 102.3 91.5 94.5 93.7 92.6 40 30 20 10 0 20 20 20 20 20 20 20 20 20 20 00

  15. Slide 15: World Nuclear Capacity - Growth is Assured

    World Nuclear Capacity - Growth is Assured number of reactors p proposed p to be operating p g by y 2030 Status April p 2010 Total 958 vs [853] – 12% increase in 12 months Current Nuclear Under Construction Planned Capacity Reactors / (Capacity) 438 (372.5GWe) 52 (44.3GWe) [43] 143 (150GWe) [108] 17

  16. Slide 16: Uranium Companies – current global status

    Uranium Companies current global status Companies Operations Producers - 18 countries Tier I • Cameco, AREVA, Rio Tinto, BHP-B, • ~85% of 2007 mine Companies K Kazatomprom, Atomredmetzoloto A d l production d i operating i iin 9 (ARMZ), Navoi countries Paladin Tier II • Uranium One, One Denison Deni

  17. Slide 17: Presentation Outline

    Presentation Outline • Paladin Status • Uranium Supply and Demand • Projects Update • Future Outlook 17

  18. Slide 18: Langer Heinrich Project Location

    Langer Heinrich Project Location

  19. Slide 19: Langer Heinrich Project – staged growth

    Langer Heinrich Project staged growth • Stage 1 – Alkaline leach, CAPEX US$100M (Jan 2007) – design g 2.6Mlb pa p • Stage 2 – Full quarter of nameplate production achieved – design g 3.7Mlb p pa,, CAPEX US$59M $ • Stage 3 - Expansion - increase to 5.2Mlb pa, – EIS approval pp received from Governmen

  20. Slide 20: Langer Heinrich Project – large resource/reserve upgrade

    Langer Heinrich Project large resource/reserve upgrade MINERAL RESOURCES 250ppm Cut-off Mt Grade % U3O8 t U3O8 Mlb U3O8 Measured Resources 32 8 32.8 0 06 0.06 19 582 19,582 43 171 43.171 Indicated Resources 23.6 0.06 13,276 29.269 Measured + Indicated 56.4 0.06 32,858 72.440 Inferred Resources 70.7

  21. Slide 21: Langer Heinrich Production quarter by quarter

    Langer Heinrich Production quarter by quarter 1,000 FY10 928 900 Stage 2 Design 841 800 686 693 700 674 650 655 b U 3O 8) Stage 1 Design 600 uction (000lb 500 Stage 2 400 nameplate Produ achieved 300 mid quarter 200 100 0 * Q1 - Sept 08 Q2 - Dec 08 Q3 - Mar 09 Q4 - Jun 09 Q1 - Sept 09 Q2 - Dec 09 Q3

  22. Slide 22: Kayelekera Project Location

    Kayelekera Project Location M26 Karonga-Chitipa Road Zambia Lake Malawi 5 km 5 mi

  23. Slide 23: Kayelekera Geology and Resources

    Kayelekera Geology and Resources Measured Indicated Inferred Total Grade Grade Grade Grade Mt ppm Metal t Mt ppm Metal t Mt ppm Metal t Mt ppm Metal t Resources 35 3.5 1 241 1,241 4 347 4,347 17 2 17.2 769 13 242 13,242 55 5.5 625 3 433 3,433 26 2 26.2 802 21 032 21,032 23

  24. Slide 24: Kayelekera Mine – current status (May 2010)

    Kayelekera Mine current status (May 2010) • Resin handling issues at RIP now resolved- circuit no longer a b ttl bottleneck k • Resin movement time from RIP to Elution significantly reduced from 6-8 hours to 2-3 hours by installation of new screen cloth • Traditional design elements proven to delive

  25. Slide 25: Kayelekera Mine – current status May 2010 (cont)

    Kayelekera Mine current status May 2010 (cont) Short Term Objectives • Achieve nameplate capacity during the June 2010 qtr • Improve mechanical availability Kayelekera Production 200000 150000 Lb U3O8 100000 50000 0 25

  26. Slide 26: Mount Isa Uranium Project – current status

    Mount Isa Uranium Project current status • Uranium resource now 111Mlb • Focussed metallurgical scoping test work underway • Environmental baseline work ongoing • Feasibility y study y to start mid 2010 • Ongoing lobbying of QLD Government re uranium policy • 09/10 budget A$10.5M SKAL • Significant

  27. Slide 27: Presentation Outline

    Presentation Outline • Paladin Status • U i Uranium S Supply l and dDDemand d • Projects Update • Future Outlook 27

  28. Slide 28: 4 Year Production Outlook

    4 Year Production Outlook 15 13.8 14 Actual Forecast 12.8 13 12 Stage 3 Langer Heinrich 11 Production 10.0 10 8.5 9.0 9 Mlb 8 7.0+ Stage 4 U3O8 7 6 5.0 5 I 4 2.70 4.4 3 1.71 2 1 0 07/08 08/09 09/10 10/11 11/12 12/13 13/14 14/15 15/16 + Stage 3 ramp up contribution Langer Heinrich Actual Langer Heinr

  29. Slide 29: Project Pipeline

    Project Pipeline assets acquired & projects developed Stage 3 Expansion Langer Heinrich Mine LHM LHM Stage 4 Expansion Kayelekera Mine Inventory U3O8 379 1Mlb 379.1Mlb New production with staged g organic g growth 2007 to 2013

  30. Slide 30: Paladin Outlook – strong growth

    Paladin Outlook – strong growth • Langer Heinrich (Namibia) – optimise Stage 2 production – Complete Stage 3 construction – Stage 4 feasibility to commence 2nd half CY10 – resource upgrade drilling underway y • Kayelekera (Malawi) – nameplate production in current quarter – drilling d illi off hot h

  31. Slide 31: Key Takeaways

    Key Takeaways • Multi-mine/multi-country operating status • P i it focus Priority f on meeting ti production d ti objectives bj ti • Maintaining strong production growth profile • Langer Heinrich Stage 3 e expansion pansion increasing prod production ction to 5 5.2Mlb 2Mlb pa – commissioning start u

  32. Slide 32: Paladin Energy Ltd Contact Details

    PALADIN ENERGY LTD Contact Details Head Office Level 4, 502 Hay Street Subiaco Western Australia 6008 PO Box 201, Subiaco Western Australia 6904 Telephone: +61 (0) 8 9381 4366 Facsimile: +61 (0) 8 9381 4978 Email: paladin@paladinenergy.com.au Website: www.paladinenergy.com.au 32