Hudbay Minerals Inc · TSX:HBM

Hudbay Minerals — Q3 2013 Earnings Presentation

14 slides from Hudbay Minerals's earnings presentation, Nov 11, 2013

  1. Slide 1: Q3 2013 Presentation

    Q3 2013 Presentation November 11, 2013 HBM

  2. Slide 2: Forward-looking Information

    Forward-looking Information This presentation contains “forward-looking statements” and “forward-looking information” (collectively, “forward-looking information”) within the meaning of applicable Canadian and United States securities legislation. All information contained in this presentation, othe

  3. Slide 3: Note to U.S. Investors

    Note to U.S. Investors Information concerning Hudbay’s mineral properties has been prepared in accordance with the requirements of Canadian securities laws, which differ in material respects from the requirements of the Securities and Exchange Commission (“SEC”) Industry Guide 7. Under SEC Industry

  4. Slide 4: Growth Project Highlights

    Growth Project Highlights Lalor > Sinking of main production shaft substantially complete > Constructed station development at 955 metre level and reached shaft bottom access on 985 metre level Reed > Received Environment Act Licence > Commenced initial production > Initial ore batch milled in Septe

  5. Slide 5: Financial Results

    Financial Results Three Months Ended Sept. 30 Nine Months Ended Sept. 30 ($000s except per share amounts) 2013 2012 2013 2012 Revenue 130,179 144,659 380,720 521,555 Profit (loss) before tax 9,650 6,254 (22,310) 23,873 Profit (loss) for the period 2,985 (5,354) (47,794) (31,606) Operating cash flow1

  6. Slide 6: Production Profile

    Production Profile Three Months Ended Nine Months Ended Guidance Manitoba contained metal in concentrate Sept. 30, 2013 Sept. 30, 2013 2013 Copper tonnes 7,972 22,596 33–38,000 Zinc tonnes 24,816 66,617 85–100,000 Precious Metals1 troy oz. 26,631 70,784 85–105,000 Unit Operating Costs 777 $/tonne 35

  7. Slide 7: Lalor

    Lalor MANITOBA > $371 million of overall $441 million1 capital Lalor costs invested to Oct. 31, 2013; entered into additional $40 million in commitments Winnipeg > Increase in Snow Lake concentrator production capacity expected to be completed by mid- 2014, in conjunction with commissioning of produ

  8. Slide 8: Lalor

    Lalor Production shaft commissioning expected in the second half of 2014 Surface 0m Production shaft Vent raise 500m 750m 2014 Exploration platform 1000m 1500m Base Metal Resource Gold & Copper-Gold Resource Looking 0m 250m High Grade Intercepts N70oW Completed infrastructure and development Q3 2013

  9. Slide 9: Reed

    Reed MANITOBA > $59 million invested and entered into Reed additional $7 million in commitments to Oct. 31, 2013 Winnipeg > Received Environment Act Licence and began initial production > Project remains on track to reach full production of approximately 1,300 tonnes per day in H1 2014 > Over 570 da

  10. Slide 10: Constancia Project

    Constancia Project PERU > US$872 million incurred and entered into additional US$336 million in Lima commitments to Oct. 31, Constancia 2013 > Results from completion of revised definitive capital cost estimate indicate total costs Tailings thickener (left) installed ball mills (right) Constancia pl

  11. Slide 11: Constancia Construction Progress

    Constancia Construction Progress Waste rock facility containment pond and grout curtain preparation Constancia bog dam East tailings dam of tailings management facility Setting the ball mill shells Q3 2013 l 11

  12. Slide 12: Constancia Construction Progress

    Constancia Construction Progress Primary crusher and retaining wall Mine fleet assembly Hitachi shovels on site Main Constancia sediment pond Q3 2013 l 12

  13. Slide 13: Balance Sheet

    Balance Sheet Pro-forma as at September 30, 2013 (in millions)1 Sources Uses (through 2014) Cash and cash equivalents $792.5 Lalor $73 Remaining stream agreement payments $260 Reed $16 Canadian income taxes and Peruvian value-added taxes2 $100 Constancia $900 Credit facility and committed Caterpilla

  14. Slide 14: Q3 2013 Presentation

    Q3 2013 Presentation November 11, 2013 HBM

Hudbay Minerals — Q3 2013 Earnings Presentation on 6ix