Yancoal Australia Ltd. · ASX:YAL
Yancoal Australia — Corporate Update (August 2020)
21 slides from Yancoal Australia's corporate update, August 2020
Slide 1: Stratford Coal CCC Meeting Presentation – Company Report & Overview of Activities
Stratford Coal CCC Meeting Presentation – Company Report & Overview of Activities August 2020 Michael Plain Environment & Community Superintendent
Slide 2: Table of Contents
Table of Contents 1. Agenda Item 7a (Progress at the Mine) 2. Agenda Item 7b (Environmental Reporting) 3. Agenda Item 7c (Environmental Management Plans and Monitoring) 4. Agenda Item 7d (Community Complaints) 5. Agenda Item 7e (Community Programs) 2
Slide 3: Covid-19 Response
Covid-19 Response The impacts of the Covid-19 pandemic has been risk assessed with significant measures undertaken on-site to protect and safeguard the health of our team members and community from infection and to protect our ability to operate our core business. Measures on site include but are no
Slide 4: 1. Progress at the Mine
1. Progress at the Mine Mining 2nd Quarter 2020 Waste BCM 1,899,435 BCM Stratford ROM Coal 190,714 tonnes Total CHPP product 92,016 tonnes Mining in Avon North continued during the quarter. Day and evening shift. Mining in the Roseville West Pit continued during the quarter. Dayshift only.
Slide 5: 2. Environmental Reporting & Regulators
2. Environmental Reporting & Regulators Management Area Project Status Reporting • Stratford Mining Complex • The Stratford Mining Complex 2019 Annual Review has been prepared and Annual Review 2019 submitted to DPIE and other relevant agencies. Copies will be made available to the CCC and on the we
Slide 6: Tenements
Tenements Exploration Licence Application (ELA) No.5910 • Stratford Coal has lodged the ELA over its existing Mining Lease ML 1447 (Roseville West Extension) • ML 1447 was only granted for ancillary mining activities and not mining production activities. • An ELA is the first step in the application
Slide 7: 3. Environmental Management Plans & Monitoring
3. Environmental Management Plans & Monitoring a) Air Quality Management b) Blast Management c) Noise Management d) Water Management e) Rehabilitation Management f) Biodiversity Management 7
Slide 8: 3a. Air Quality Management
3a. Air Quality Management Management Area Project Status Air quality monitoring • Real-time air quality • The real-time air quality TEOM monitors in Stratford and Craven villages monitoring continue to operate. • General ambient PM10 dust levels have been low throughout winter. 8 3 August 2020 8
Slide 9: 3a. Air Quality Management
3a. Air Quality Management Stratford Dust Deposition - Annual Rolling Average Stratford HVAS Monitoring - Particulate Matter (PM10) 12 Months to July 2020 12 Months to July 2020 5.0 200 4.0 150 PM10 (µg/m³) Dust (g/m2/month) 3.0 100 2.0 50 1.0 0 0.0 1-Jul-19 1-Sep-19 1-Nov-19 1-Jan-20 1-Mar-20 1-May
Slide 10: 3b. Blast Management
3b. Blast Management Management Area Project Status Blasting • Blast Monitoring • Blasting activities continued in both the Avon North, BRN and Roseville West open cuts with blasting commencing in Stratford East open cut from April 2020. • Blast Results • For the annual reporting period 1.23% of bla
Slide 11: 3b. Blast Management
3b. Blast Management Clarke (B5) Overpressur Overpressur (Mine-owned) e Isaac (B1) Ex-Judge (B2) Atkins (B6) Greenwood e Site Monitore Fume Location Date Time 7433 "Cumulative 7432 7441 7434 7422 Exceedance d Blasts1 Rating (previously 1 Exceedance" 1 7377) 24hr mm/s dBL mm/s dBL mm/s dBL mm/s dBL m
Slide 12: 3c. Noise Management
3c. Noise Management Management Area Project Status Monitoring • Monthly Noise Survey • Monthly attended noise monitoring was undertaken during Q2 2020. • No non-compliant results were recorded during the surveys. One elevated noise measurement was recorded at the Lowrey monitoring location. Follow-
Slide 13: 3d. Water Management
3d. Water Management Management Area Project Status Site Water • Annual water balance • The 2019 annual site water balance review has been completed. A summary is included Management review. in the Annual Review 2019. Water management • Avon North Pit Flood • The Avon North Pit Flood Bund constructi
Slide 14: 3d. Water Management
3d. Water Management Stratford Monthly Rainfall pH - Avon River & Avondale Creek 400 12 Months to July 2020 9 Rainfall (mm) 8 200 7 pH 0 6 2020 JAN FEB MAR 2019 APR MAY JUN JUL 5 2018 AUG SEP 04-Jul-19 02-Oct-19 31-Dec-19 30-Mar-20 28-Jun-20 26-Sep-20 OCT NOV Average 1908-2007 Month DEC W1 W2 W3A W4
Slide 15: 3e. Rehabilitation Management
3e. Rehabilitation Management Management Area Project Status Rehabilitated Waste • Avon North waste • Bulk shaping of the Avon North waste emplacement completed focusing on Emplacements emplacement areas with offsite visual impact (North Aspect). Native Tree Seed and Native Grass Seed spread on appr
Slide 16: 3e. Biodiversity Management
3e. Biodiversity Management Management Area Project Status Biodiversity Offset • Revegetation Works • In Q1 2020 SCPL has planted approximately 56,000 trees over 76 hectares along the Glen Area Road area in the Biodiversity Offset. • Tubestock planting in the biodiversity offset area commenced in Ma
Slide 17: 3f. Biodiversity Management
3f. Biodiversity Management Management Area Project Status Nest Box Program • Nest Box Installation • 70 Nest boxes have been installed in the Stratford Biodiversity Area and Biodiversity Enhancement Area in April 2020. 54 of these boxes are to specifically target the Squirrel glider and 16 of these
Slide 18: 4. Community Complaints - Summary
4. Community Complaints - Summary Stratford Complaint Summary Period: 01/05/2020 - 31/07/2020 Period: 3 Months Total No. of Complaints: 14 Total No. of Complainants: 3 Date/Time of Complainant Method of Nature of Complaint Location Complaint Complaint Investigation/Outcome 1/05/2020 12:03 Approx. 1.
Slide 19: 4. Community Complaints - Summary
4. Community Complaints - Summary Date/Time of Complainant Method of Nature of Complaint Location Complaint Complaint Investigation/Outcome 20/05/2020 8:00 Approx. 1.5km Direct text to Mine Noise Complaint “it now 11:34 I have 3 very tired and cranky children awake due to noise” "and start back up f
Slide 20: 4. Community Complaints - Summary
4. Community Complaints - Summary Date/Time of Complainant Method of Nature of Complaint Location Complaint Complaint Investigation/Outcome 9/06/2020 19:02 Approx. 3.2km Community Mine Noise Complaint: "Noise" • AB returned a call at 19:51. west of the Hotline • The complainant advise the noise 'sou
Slide 21: 5. Community Programs
5. Community Programs Management Area Project Status Support Programs Stratford Coal • The Stratford Coal Community Support Program will be running again in 2021. Advertising is Community Support expected to be released in October 2020, calling for applications from local community Program organisat