Agl Energy Limited · ASX:AGL

Agl Energy — Corporate Update (June 2018)

34 slides from Agl Energy's corporate update, Jun 7, 2018

  1. Slide 1: Silverton Wind Farm Community Consultative Committee

    Silverton Wind Farm Community Consultative Committee Meeting No.CCC-028 Thursday, 7 June 2018

  2. Slide 2: Agenda

    Agenda 1 2 3 4 5 6 Welcome Previous Project update Community Topics of interest Other minutes • Overview relations • Wilangee Road business • Wind Farm Works update • Solar PV Voltage Rise • Commissioning Silverton Wind Farm | 7 June 2018 2

  3. Slide 3: 1. Welcome

    1. Welcome

  4. Slide 4: 2. Previous minutes

    2. Previous minutes

  5. Slide 5: Action items

    2. Previous minutes Action items Item Action Status Who 5.19.01 AGL to arrange site tour for interested Silverton community members and the Broken Hill City Council. Open AGL – 1/18 3.23.16 AGL to contact Rod Grenfell in relation to erecting a fence along Daydream Mine Road near the Open AGL – 1/18

  6. Slide 6: 3. Project update

    • Overview • Wind Farm Works • Connection Works 3. Project update

  7. Slide 7: Silverton Wind Farm

    3. Project update Silverton Wind Farm Silverton Wind Farm • Located in the Barrier Ranges approximately 5km north of the Silverton township • Generation capacity of 200 MW • Wind turbines: 58 x GE 3.43-130 • Annual Energy Production (AEP) - ~780,000 MWh (capacity factor of 44.5%) - Powering more tha

  8. Slide 8: Scope of works

    3. Project update Silverton Wind Farm Scope of works • Silverton Wind Farm consists of two main scope of work: - Wind Farm Works (GE-CATCON) - Connection Works (TransGrid) • AGL has prepared an Overview Environmental Management Strategy (OEMS) in accordance with the project approval • Overview activ

  9. Slide 9: Silverton Wind Farm

    3. Project update Silverton Wind Farm Wind Farm Works • GE-CATCON (joint venture) has been engaged to deliver the wind farm works - Engineer, Procure, Construct (EPC) Contract • Scope of works, includes - 58 x GE 3.43-130 wind turbines - 33kV electrical reticulation (underground and overhead) and 33

  10. Slide 10: Connection Works

    3. Project update Silverton Wind Farm Connection Works • TransGrid has achieved Practical Completion on 20 February 2018 - Existing Broken Hill 220kV substation (connection point) - 220kV transmission line - Wind farm 220kV substation • Connection works were successfully energised on 23 Feb 2018. •

  11. Slide 11: Construction works

    3. Project update Wind Farm Works Construction works • Civil works progress: - Access road clearance: 65/65km (100%) - Access road capping: 64/65km (~98%) • Structural works progress: - WTG foundations excavated: 58/58 (100%) - WTG foundations poured: 58/58 (100%) • Electrical works progress: - 33kV

  12. Slide 12: Construction works – Progress photos

    3. Project update Wind Farm Works Construction works – Progress photos Silverton Wind Farm | 7 June 2018 12

  13. Slide 13: Wind Turbine Deliveries

    3. Project update Wind Farm Works Wind Turbine Deliveries • Components requiring police escort - Tower mid section A - Tower top section - Blades • Components requiring pilot escort - Tower mid section B - Tower mid section C - Tower door section - Nacelle and Hub • Deliver status - Tower Sections:

  14. Slide 14: Wind Turbine Erection

    3. Project update Wind Farm Works Wind Turbine Erection • GE-CATCON mobilised a second main crane during April 2018. • Two main cranes are currently being used for the erection of wind turbines. These cranes have been certified and registered with SafeWork NSW. - LR1650 (650 tonne crane) – Sarens -

  15. Slide 15: Wind Turbine Commissioning

    3. Project update Wind Farm Works Wind Turbine Commissioning • The wind farm is currently being commissioned in accordance with the AEMO commissioning plan which involves coordination with AEMO and TransGrid (NSP). - AEMO – Australian Energy Market Operator - NSP – Network Service Provider • Commiss

  16. Slide 16: Wind Turbine GE 3.43-130

    3. Project update Wind Farm Works Wind Turbine GE 3.43-130 • GE 3.43-130 Power Curve - Cut in wind speed – 3 m/s - Rated wind speed – 12 m/s - Cut out wind speed – 25 m/s Silverton Wind Farm | 7 June 2018 16

  17. Slide 17: First Generation

    3. Project update Wind Farm Works First Generation • First generation occurred from the Silverton Wind Farm (STWF) on Saturday, 12 May 2018 at 23:30 hrs • Generation from the Silverton Wind Farm (STWF) as at 11:00hrs Thursday, 7 June 2018 - 3,061.60 MWh - Already powering more than 500 average Austr

  18. Slide 18: Local Industry Participation

    3. Project update Wind Farm Works Local Industry Participation • Currently ~115 construction workers with approximately 24% from the local area. - Reduced workers as the civil works and electrical works have progressed to completion. - Increase in wind turbine specialist for commissioning which has

  19. Slide 19: Local suppliers

    3. Project update Wind Farm Works Local suppliers • Delivery of the Silverton Wind Farm to date has involved the following local suppliers / contractors - Attards Transport - Interhealth Broken Hill - Barrier Daily Truth - Judd Plumbing - Boss Construction - Lawrence Engineering - Broken Hill City C

  20. Slide 20: 4. Community relations update

    4. Community relations update

  21. Slide 21: Community Enhancement Program

    4. Community relations update Community enhancement program Community Enhancement Program AGL has started the Community Enhancement Program for the Silverton Wind Farm, in accordance with condition 18 (schedule 2) of the project approval and will implement the program in order to give effect to the

  22. Slide 22: Silverton Community Fund

    4. Community relations update Community enhancement program Silverton Community Fund • The Silverton Village Committee has applied for funding to support the upgrade of the Silverton Municipal Chambers to turn it into a ‘Community Hub’ • The Chambers would support community interaction and social in

  23. Slide 23: Silverton Solar Program

    4. Community relations update Community enhancement program Silverton Solar Program • AGL commenced installation of the first 5kW solar PV system on 7 May 2018 and has completed 3* to date. - *Two installations awaiting inverters • Further installation planning: - 13 installations planned for week c

  24. Slide 24: Water Tank Program

    4. Community relations update Community enhancement program Water Tank Program • AGL has progressed discussions with our preferred suppliers in relation to supply, install and connection of a domestic sized water tank (10,000L) - Water tank supply  Landmark - Installation and connection  Broken Hi

  25. Slide 25: Mobile Reception Program

    4. Community relations update Community enhancement program Mobile Reception Program • AGL is progressing an Enterprise Work Agreement (EWA) with Telstra in relation to the proposed 4GX solution developed with Telstra for the mobile reception program - Installation of a 20m monopole at Telstra’s Sil

  26. Slide 26: Mobile Reception Program

    4. Community relations update Community enhancement program Mobile Reception Program • The coverage predications below provide and indicative view of the coverage the proposed 4GX small cell would provide - Proposed 4GX solution would require a 4G 700 MHz compatible device to benefit from the improv

  27. Slide 27: Visual Impact Mitigation

    4. Community relations update Visual impact mitigation Visual Impact Mitigation AGL issued notification to the Silverton residents in accordance with condition 2 (schedule 3) of the project approval in relation to the visual impact mitigation measures outlined in condition 1 (schedule 3). • Owners w

  28. Slide 28: Community information

    4. Community relations update Community engagement Community information AGL contact details for community and project information are shown below: • P: 1800-039-600 • E: AGLcommunity@agl.com.au • W: agl.com.au/silverton Construction information GE-CATCON will provide contact details on the project

  29. Slide 29: 5. Topics of interest

    • Wilangee Road • Solar PV Voltage Rise 5. Topics of interest

  30. Slide 30: Wilangee Road

    5. Topics of interest Wilangee Road Wind Farm Emergency Access • The emergency access from the Silverton Wind Farm intersects with Wilangee Road on the western boundary of the wind farm. • Access for construction of this emergency access was internal to the wind farm. • RMS installed advisory signag

  31. Slide 31: Solar PV Voltage Rise

    5. Topics of interest Solar PV Voltage Rise Solar Silverton • Voltage rise calculations are required for all solar PV system >3kW for rural areas. • As per Service Installation Rules of NSW 8.6.1.3., details of the voltage rise calculations for each of the three components of the generating system t

  32. Slide 32: 6. Other business

    6. Other business

  33. Slide 33: Next meeting

    Silverton Wind Farm Community Consultative Committee (CCC) • Next meeting (TBC) - Thursday, 30 August 2018 - Time: 3-5pm - Silverton Municipal Chambers, Silverton Next meeting

  34. Slide 34: Contact

    Contact AGL Energy Silverton Wind Farm 1800-039-600 AGLcommunity@agl.com.au

AGL Energy — Corporate Update (June 2018) on 6ix