  1. Slide 1: AGL Camden Gas Project

    AGL Camden Gas Project Camden Community Consultative Committee Presented by Camden Gas Operations Team Date 22 March 2017

  2. Slide 2: Agenda

    Camden Consultative Committee Meeting | 22 March 2017 | 2 Agenda 1 2 3 4 5 6 Open and Correspondence Reports & AGL Update General Next Meeting Welcome Presentations Business Date Operations & Declarations of Environment Close Interest Land & Previous Approvals Minutes Community & Business Arising St

  3. Slide 3: AGL Energy Business Update

    Camden Consultative Committee Meeting | 22 March 2017 | 3 AGL Energy. Business Update. Western Australia Market Entry › Contestable gas market – AGL to act with a differentiated value proposition › Attractive in size and accessibility – 92% live in south-west corner › AGL on track to enter market in

  4. Slide 4: Camden Operations: Decommissioning & Rehabilitation Overview and Program

    Camden Consultative Committee Meeting | 22 March 2017 | 4 Camden Operations. Decommissioning & Rehabilitation Overview and Program. Production Well Status Total Total (as at 21 March 2017) (as at 13 December 2016) Drilled (total wells) 144 144 Producing and dewatering 92 92 wells Suspended or shut i

  5. Slide 5: Camden Operations: Field Operations

    Camden Consultative Committee Meeting | 22 March 2017 | 5 Camden Operations. Field Operations. Well workovers Well workover completed in Mt Taurus field (MT05) during February/ March Next workover planned for Menangle Park (MP22) in March/ April Workover Rig now permanently based in Camden Well site

  6. Slide 6: Camden Operations: Well Site Rehabilitation

    Camden Consultative Committee Meeting | 22 March 2017 | 6 Camden Operations. Field Operations. Well site rehabilitation Once all surface infrastructure is removed, well site decommissioning is completed in four steps: 1: Milling and cementing 2: Cutting casing 1.5m bgl 3: Surveying and capping 4: Su

  7. Slide 7: Campbelltown LGA

    Camden Consultative Committee Meeting | 22 March 2017 | 7 Campbelltown LGA. Wells to be rehabilitated: MP01, MP05, RP02, RP06, RP10, RP12, SL09 AGL Camden Gas Operations Team

  8. Slide 8: Camden LGA

    Camden Consultative Committee Meeting | 22 March 2017 | 8 Camden LGA. Wells to be rehabilitated: GL16 AGL Camden Gas Operations Team

  9. Slide 9: Wollondilly LGA

    Camden Consultative Committee Meeting | 22 March 2017 | 9 Wollondilly LGA. Wells to be rehabilitated: EM16, EM34, JS01, JS03, JS04, LP01, MT09, MT10, WG06 AGL Camden Gas Operations Team

  10. Slide 10: Field Operations / Rosalind Park Gas Plant

    Camden Consultative Committee Meeting | 22 March 2017 | 10 Camden Operations. Field Operations / Rosalind Park Gas Plant. Leak Detection Survey The annual Leak Detection and Repair Survey was completed by external specialist contractors in November 2016. The scope of the survey included all producin

  11. Slide 11: 2014-16 Independent Environmental Audit

    Camden Consultative Committee Meeting | 22 March 2017 | 11 Camden Operations. Field Operations / Rosalind Park Gas Plant. 2014-16 Independent Environmental Audit Treo Environment were engaged by AGL and approved by the DP&E to complete the 2014-16 IEA. The Audit assessed the environmental performanc

  12. Slide 12: 2014-2016 IEA Corrective Actions Register

    Camden Consultative Committee Meeting | 22 March 2017 | 12 Camden Operations. Field Operations / Rosalind Park Gas Plant. 2014- 2016 IEA Corrective Actions Register Development Consent and Action Finding Status/ Target Action Taken by AGL Condition Number Action Date DA 282-6-2003 Sch 4 Cond 58 Work

  13. Slide 13: Land & Approvals

    Camden Consultative Committee Meeting | 22 March 2017 | 13 Land & Approvals. Business as usual. Landholder engagement on production activities and decommissioning consultation for candidate wells. AGL Camden Gas Operations Team

  14. Slide 14: Community Engagement Policy

    Camden Consultative Committee Meeting | 22 March 2017 | 14 Community & Stakeholders. Community Engagement Policy Aspiration Leave a positive legacy: AGL will strive to make a net positive social, economic and environmental contribution to the communities in which we operate. Vision AGL will be a tru

  15. Slide 15: Community Complaints Framework

    Camden Consultative Committee Meeting | 22 March 2017 | 15 Community & Stakeholders. Community Complaints Framework Purpose This Policy sets out AGL’s commitment to the effective management of complaints made by members of the community about our assets, operations, existing or planned projects and

  16. Slide 16: Community and Stakeholder Engagement Plan

    Camden Consultative Committee Meeting | 22 March 2017 | 16 Community & Stakeholders. Community and Stakeholder Engagement Plan. Objectives: › Communicate and engage with community members › Inform the local community and stakeholders › Understand how AGL can positively contribute to the Macarthur co

  17. Slide 17: 2017 Local Community Investment Program

    Camden Consultative Committee Meeting | 22 March 2017 | 17 Community & Stakeholders. 2017 Local Community Investment Program 2017 Local Community Investment Program (LCIP) › With the refreshed approach to community engagement, we are also standardising the LCIP › Looking to formalise our current app

AGL Energy — Corporate Update (March 2017) on 6ix