Sbm Offshore Nv · EURONEXT:SBMO

Sbm Offshore Nv — FY2009 Earnings Presentation

27 slides from Sbm Offshore Nv's earnings presentation, Feb 26, 2010

  1. Slide 1: 2009 Results Analyst Presentation

    2009 RESULTS Analyst Presentation February 26, 2010 T. Mace, CEO and M. Miles, CFO

  2. Slide 2: Disclaimer

    DISCLAIMER Some of the statements contained in this presentation that are not historical facts are statements of future expectations and other forward- looking statements based on management’s current views and assumptions and involve known and unknown risks and uncertainties that could cause actual

  3. Slide 3: Content

    CONTENT 2009 Review 2009 Financials Outlook 3

  4. Slide 4: 2009 Review

    2009 Review 4

  5. Slide 5: Highlights 2009

    HIGHLIGHTS 2009 ƒ Turnover US$ 2,957 million (US$ 3,060 million in 2008) ƒ Net profit of US$ 230 million (US$ 228 million in 2008) ƒ New orders totalled US$ 3,740 million (US$ 4,365 million in 2008) ƒ Record backlog US$ 10,032 million (2008: US$ 9,247 million) ƒ EPS of US$ 1.47 (US$ 1.54 in 2008) ƒ

  6. Slide 6: Major Projects Delivered

    MAJOR PROJECTS DELIVERED FPSO Frade started operation offshore Brazil FPSO Espirito Santo started operation offshore Brazil Thunder Hawk started operation in Gulf of Mexico BP Skarv turret partially delivered 6

  7. Slide 7: Contract Developments 2009

    CONTRACT DEVELOPMENTS 2009 Lease Fleet ƒ Fifteen year contract for an FPSO for the Aseng field ƒ Eighteen year contract for the FPSO Espadarte for Baleia Azul field ƒ Twelve month extension for FSO Unity operations ƒ Sale of the Turkmenistan MOPU and FSO facilities ƒ End of lease contract for FPSO F

  8. Slide 8: SBM's Lease Fleet

    SBM’s LEASE FLEET MOPU Deep Panuke MOPUstor FSO FPSO Yme Yetagun Falcon Semi-Sub Thunder Hawk FPSO Brasil FPSO FPSO Marlim Sul Kikeh FPSO Capixaba FPSO Aseng FPSO Espadarte FSO Nkossa II FPSO Espirito Santo FPSO FPSO FPSO FPSO LPG FPSO Mondo Saxi Batuque Xikomba Kuito Sanha Lease in operation (red)

  9. Slide 9: Remaining Duration of Lease Contracts

    REMAINING DURATION OF LEASE CONTRACTS Firm order backlog on long term contracts with robust and solid clients 9

  10. Slide 10: Performance Improvements

    PERFORMANCE IMPROVEMENTS ƒ Corporate Organisation - Operating units ƒ Project Execution - Proposals robustness - Project Controls strengthened ƒ Human Resources - Talent Management - Succession Planning ƒ Risk Management strengthened ƒ Internal Assurance expanded Introduction of new initiatives 10

  11. Slide 11: 2009 Financials

    2009 Financials 11

  12. Slide 12: Financial Overview 2009

    FINANCIAL OVERVIEW 2009 P&L Total Group In millions of US Dollars 31/12/09 31/12/08 Change Comment Turnover 2,957 3,060 (3%) 72% Turnkey, 28% Lease & Operate Gross Margin 452 399 13% 57% Turnkey, 43% Lease & Operate (%) (15.3%) (13.0%) EBITDA 613 530 Depreciation & amortisation increases 16% 25% (%

  13. Slide 13: Financial Overview 2009: Turnkey Systems

    FINANCIAL OVERVIEW 2009 Turnkey Systems In millions of US Dollars 31/12/09 31/12/08 Change Comment P-57, Okha, Skarv, Rigs, Turkmenistan Turnover 1,924 1,984 (3%) sale US$ 51.5 mln Gross Margin 187 71 Cost overruns on drilling rigs; Includes (%) (9.7%) (3.6%) X 2.6 Turkmenistan sale US$ 32 mln EBITD

  14. Slide 14: Financial Overview 2009: Turnkey Services

    FINANCIAL OVERVIEW 2009 Turnkey Services In millions of US Dollars 31/12/09 31/12/08 Change Comment Mooring components supply & overhaul; Turnover 262 308 (15%) Offshore installation Gross Margin 70 76 Normand Installer drydock; (%) (26.7%) (24.6%) (8%) Pyrodriver impairment EBITDA 67 68 (1%) As abo

  15. Slide 15: Financial Overview 2009: Lease and Operate

    FINANCIAL OVERVIEW 2009 Lease and Operate In millions of US Dollars 31/12/09 31/12/08 Change Comment Espirito Santo and Saxi FPSOs full Turnover 816 810 1% twelve months; 4 smaller units terminated in 2008, Turkmenistan, Falcon leases ended in 2009; Tanker fleet in 2008 Gross Margin 195 253 High bon

  16. Slide 16: Financial Overview 2009: Ratios Total Group

    FINANCIAL OVERVIEW 2009 Ratios Total Group In millions of US Dollars 31/12/09 31/12/08 Change Comment Yme MOPUstor, Encana MOPU, Thunder Capital Expenditure 656 1,000 (34%) Hawk semi, Cachalote New loans arranged for Encana MOPU, Long-Term Debt 1,611 1,694 (5%) Cachalote FPSO Net Liquidities 147 230

  17. Slide 17: Order Portfolio Backlog

    ORDER PORTFOLIO BACKLOG US$ billion Turnkey Turnkey Lease & Total Systems Services Operate 2010 1.4 0.2 0.8 2.4 2011 0.6 - 0.9 1.5 2012 - - 0.9 0.9 Beyond - - 5.2 5.2 2012 TOTAL 2.0 0.2 7.8 10.0 Record order backlog 17

  18. Slide 18: Cost Initiatives

    COST INITIATIVES ƒ Outsourcing more detailed engineering ƒ Establish new suppliers and construction subcontractors ƒ Further develop major project execution in Kuala Lumpur office ƒ Lease operations improved maintenance framework contracts ƒ Streamline internal procedures ƒ More fit for purpose inte

  19. Slide 19: Outlook

    Outlook 19

  20. Slide 20: Outlook General

    OUTLOOK GENERAL ƒ Deep water oil and gas field development increasing ƒ High bidding activity continues ƒ Oil companies need to maintain production levels ƒ Gradual release of new oil and gas field project developments during 2010 and beyond Expected improvement in market 20

  21. Slide 21: Major Projects in Execution 2010

    MAJOR PROJECTS IN EXECUTION 2010 ƒ Singapore Petrobras - P-57 Woodside - FPSO Okha BP - Skarv Turret Noble Energy - Benita ƒ U.A.E. Talisman - Yme EnCana - Deep Panuke QGP - Drilling Rig Odebrecht - Delba - Drilling Rig Drilling Rig ƒ In Transit ƒ TBA Petrobras - Cachalote Baleia Azul Focus on enhan

  22. Slide 22: Short Term Prospects

    SHORT TERM PROSPECTS DW CALM DW CALM TURRET FPU (Gas) Shtokman CLOV Egina Quad 204 Gazprom Semi – Tubular Bells Total Total BP Russia BP Gulf of Mexico Semi – Green Canyon Enterprise Gulf of Mexico BS-4 TLP - Malikai Shell Shell Brazil Malaysia FPSO – Iara/Guara Petrobras FSO Cepu Brazil ExxonMobil

  23. Slide 23: Strategic Objectives

    STRATEGIC OBJECTIVES ƒ Expand the lease & operate fleet ƒ Selective approach to turnkey sales ƒ Maintain market leadership position (converted FPSO’s, turrets, swivels, CALMs) ƒ Floating LNG remains prime focus within gas sector ƒ Develop technology for strategic growth areas: deep water, arctic, LN

  24. Slide 24: Technology Development

    TECHNOLOGY DEVELOPMENT Deepwater FourStarTM TLP MoorsparTM Riser Buoy Renewable Wave Energy Converter

  25. Slide 25: Technology Development

    TECHNOLOGY DEVELOPMENT LNG FPSO COOLTM LNG Floating Hose LNG Floating Production, Storage and Offloading (FPSO) 25

  26. Slide 26: Financial Outlook 2010

    FINANCIAL OUTLOOK 2010 ƒ Turnover in the same range as 2009; ƒ EBIT in Turnkey Systems solidly within the 5% - 10% range ƒ EBIT in Turnkey Services at lower end of 15% – 20% range; ƒ EBIT in Lease and Operate below 2009 level ƒ Net interest charge will increase by up to 20% ƒ Capital expenditure to

  27. Slide 27: Q&A

    Q&A T. Mace, CEO and M. Miles, CFO