KGHM Polska Miedz S.a. · GPW:KGH
KGHM Polska Miedz — FY2017 Earnings Presentation
41 slides from KGHM Polska Miedz's earnings presentation, Mar 16, 2018
Slide 1: Results of the Group for the 4th quarter and full-year 2017
Layers of possibilities Results of the Group for the 4th quarter and full-year 2017 16 March 2018
Slide 2: Cautionary Statement
Cautionary Statement This presentation was prepared by KGHM Polska Miedź S.A. (KGHM). The presentation is strictly of an informational nature and should not be construed as containing investment advice. The users of this presentation are solely responsible for their own analysis and assessment of th
Slide 3: Agenda
Agenda 1 Introduction 2 Economic results of the KGHM Polska Miedź S.A. Group 3 Summation Supporting slides Impairments recognised on the assets of KGHM 4 Key international projects Key domestic projects Economic results of KGHM Polska Miedź S.A. 5 Q&A 3
Slide 4: Introduction
Introduction EE *—
Slide 5: Summary of the year 2017 in the Group
Summary of the year 2017 in the KGHM Polska Miedź S.A. Group Production, sales and finance Payable copper production (kt)1,3 -3% -8% Production: A decrease in payable copper production by 677 656 170 156 3% in 2017, alongside 8% lower production in Q4 yoy, mainly due to the breakdown-related shutdow
Slide 6: Perspectives for global industry remain positive, which supports prices of industrial metals
Perspectives for global industry remain positive, which supports prices of industrial metals; the USD continues to weaken Significant increase in copper and molybdenum prices alongside lower silver price and Perspectives for the industrial sector measured by appreciation of the USD/PLN exchange rate
Slide 7: Metals production by the Group
KGHM Polska Miedź S.A. KGHM INTERNATIONAL Sierra Gorda (55%) Metals production by the Group Payable copper production (kt) 170 -8% 156 Payable copper production 14 21 13 (kt) 20 Production of payable copper in KGHM Polska Miedz S.A. in the fourth quarter of 135 122** -3% 2017 was 10% lower than that
Slide 8: C1 unit cost in the Group
C1* unit cost in the Group C1 – KGHM Polska Miedź S.A. C1 – Group (USD/lb) (USD/lb) 1.84 +37% +6% +4% 1.42 In the fourth quarter of 2017, C1 cost in 1.34 0.59 +13% KGHM Polska Miedź S.A. was negatively 1.59 0.44 0.41 including the minerals 1.41 1.46 impacted mainly by the higher minerals extraction
Slide 9: Economic results of the KGHM Polska Miedź S.A. Group
Economic results of the KGHM Polska Miedź S.A. Group
Slide 10: Sales revenue of the Group in the fourth quarter of 2017
Segment Segment Other KGHM Polska Miedź S.A. KGHM INTERNATIONAL Sales revenue of the Group in the fourth quarter of 2017 Sales revenue (mn PLN) Sales revenue -2% (mn PLN) +6% +848 -560 20 358 +91 -600 19 156 +77 6 015 5 871 1 732 1 509 2 602 2 535 15 112 16 024 Sales revenue Change in sales Change i
Slide 11: Operating results of the Group
Other segments Segment Segment Segment and consolidation KGHM Polska Miedź S.A. KGHM INTERNATIONAL Sierra Gorda adjustments Operating results of the Group EBITDA of the segments (mn PLN) EBITDA of the segments -3% (mn PLN) +23% -145 -18 5 753 1 515 +34 +43 -119 +166 1 476 277 4 666 609 312 707 189 6
Slide 12: Financial results of the Group
Financial results of the Group Profit for the period (mn PLN) Net profit/loss (mn PLN) 1 525 -142 +66 -134 -227 2016 2017 +4 908 -4 449 +339 -5 078 Net loss 4Q'16 Change in EBIT Impairment losses* Exchange rate Change in CIT Other Net loss 4Q'17 differences 710 605 344 4Q'16 1Q'17 2Q'17 3Q'17 4Q'17
Slide 13: Net cash generated by operating activities lower due to increase in working capital
Net cash generated by operating activities lower due to PLN 1.0 billion increase in working capital – mainly inventories Consolidated cash flow (mn PLN) -2 796 +4 050 -461 -157 +370 -200 860 -84 -996 586 Cash and cash Change in working Other net cash Acquisition of Acquisition of Proceeds from / Int
Slide 14: Net debt of the Group as at end-December 2017
Net debt of the KGHM Polska Miedź S.A. Group – as at end-December 2017 Net Debt / adjusted EBITDA Borrowing costs (mn PLN) In accordance with the financial strategy adopted by KGHM Polska Miedź S.A., the basic currency in which debt is incurred is 214 Costs of fees and the USD (natural hedging). 1.6
Slide 15: Summation
Summation
Slide 16: Production of Cu and Mo below target
Production of Cu and Mo below target in KGHM Polska Miedź and Sierra Gorda due to breakdown-related shutdown at the Głogów Smelter and Refinery and a change in sequencing of mining at the Chilean mine 2017E Execution of production plans versus initial targets Budget Nov 2017 CopperCopper in concentr
Slide 17: Lower production led to lower sales and higher C1 cost
Lower production by KGHM Polska Miedź led to lower sales and higher C1 cost, while higher metals prices allowed for a decrease in equity investments in overseas investments 2017E Execution of production plans versus initial targets Budget Nov 2017 Payable Miedź copper płatna (kt) (tys. t) 506 536 51
Slide 18: Key challenges for the KGHM Group in 2018
Key challenges for the KGHM Group in 2018 Improve electrolytic copper production from own concentrate in Poland Further increase in furnace productivity at Głogów I Copper Smelter/Refinery in order to achieve target production capacities Commissioning of copper concentrate roasting installation by y
Slide 19: Supporting slides
Supporting slides
Slide 20: Impairments recognised on the assets of KGHM
Impairments recognised on the assets of KGHM
Slide 21: Indications to conduct testing for the impairment of international mining assets
Indications to conduct testing for the impairment of international mining assets As a result of the review of technical and economic assumptions regarding the Group’s key international mining assets there were changes to the parameters for these assets in terms of: mine life, metals production volum
Slide 22: Results of the tests with respect to key international mining assets (standalone)
Results of the tests with respect to key international mining assets in the standalone financial statements of KGHM Polska Miedź S.A. Shares in Future 1 and loans granted to the KGHM International Group Pre-tax impairment loss: PLN 936 million (USD 269 million) The impairment in the amount of PLN 33
Slide 23: Results of the tests with respect to key international mining assets (consolidated)
Results of the tests with respect to key international mining assets in the consolidated financial statements of the KGHM Polska Miedź S.A. Group Mining assets of KGHM International Net impairment loss: PLN 645.1 million (USD 185.3 million) Reversal of net impairment loss : PLN 341.2 million (USD 98
Slide 24: Macroeconomic environment
Macroeconomic environment
Slide 25: Metals prices amongst best-performing commodities; copper price strongly up
Metals prices amongst best-performing commodities in terms of rate of return; copper price strongly up In 2017 metals were amongst the top-performing In the second half of 2017 the price of copper, both commodities in terms of rate of return in USD as well as PLN, grew decisively Energy Metals Other
Slide 26: Key international projects
Key international projects
Slide 27: International production assets of KGHM
International production assets of KGHM Polska Miedź S.A. In 2017 the production assets of KGHM International (excluding SG) produced a total of 81 thousand tonnes of copper, 1.1 tonnes of nickel, 1.6 tonnes of silver and 74 thousand ounces of gold, palladium and platinum. In terms of actions taken
Slide 28: Sierra Gorda
Sierra Gorda Sierra Gorda Significant events and current status Mined metals Production of copper in concentrate in the fourth quarter of 2017 Cu amounted to 24.3 thousand tonnes, while production of Mo Au molybdenum in concentrate amounted to 6.0 million pounds (on a 100% basis). 55% KGHM Ownership
Slide 29: International development assets of KGHM
International development assets of KGHM Polska Miedź S.A. Sierra Gorda Oxide The project is currently in the concept phase, involving the selection of the best economic variant of advancing the project while restricting required capital expenditures. Victoria In 2017 work was performed on technical
Slide 30: Key domestic projects
: ~ é domestic pr oject / i Se
Slide 31: Ore access program in KGHM's concessioned areas in Poland
Ore access program in KGHM’s concessioned areas in Poland Deep Głogów (GGP) area Work performed in 2017 Scope of development-preparatory tunnelling Share of production from Deep Głogów Status of the Ore Access Program completed (in metres) in total production in Poland Work continued on sinking the
Slide 32: Metallurgical Development in KGHM
Metallurgical Development in KGHM Construction of a Flash Furnace and associated infrastructure at Głogów I Work performed in 2017 Pyrometallurgy Modernisation Metallurgy Development Program Program Guarantee tests were conducted as well as work related to the installation start-up phase of the mode
Slide 33: Economic results of KGHM Polska Miedź S.A.
Economic results of KGHM Polska Miedź S.A.
Slide 34: Stable level of mine production
Stable level of mine production Ore extraction Production of Cu Electrolytic copper Metallic silver (mn t dry weight) in concentrate production production -2% (kt) From (kt) (t) -1% purchased -3% +2% 32.0 31.2 536 522 metal- From 3rd- 1 191 1 218 From 3rd- 424 419 bearing 15 party Silver grade 47 pa
Slide 35: Revenues from sales in 2017
Revenues from sales in 2017 Sales of copper and copper Silver sales (t) Sales revenue products (kt) -7% (mn PLN) -10% Cu in concentrate 560 1 280 506 1 185 35 91 +10% 16 024 Other 15 112 1 370 1 250 of which Silver 2 441 wire rod 2 798 265 260 Copper and copper products 2016 of which 2017 2016 2017
Slide 36: Expenses by nature
Expenses by nature, excluding purchased metal-bearing materials and Expenses by nature the minerals extraction tax, were higher by PLN 439 million (6%) due to higher labour costs (+PLN 187 million), external services (+PLN 139 million) and depreciation/amortisation (+PLN 80 million), mainly due Expe
Slide 37: Financial results of KGHM Polska Miedź S.A. in 2017
Financial results of KGHM Polska Miedź S.A. in 2017 Adjusted EBITDA Profit/(loss) for the (mn PLN) period (mn PLN) 4 160 3 551 1 323 The increase in adjusted EBITDA by PLN 609 million (+17%) was mainly due to more favourable metals prices, 2016 2017 alongside lower copper and silver sales volumes, a
Slide 38: Statement of Profit or Loss of the Group
Statement of Profit or Loss of the Group Difference vs Main consolidation (mn PLN) adjustments for 2017 2016 Change (%) 2017 KGHM SA selected items in the Sales revenue 20 358 19 156 +6 +4 334 Statement of Profit or Loss Cost of sales 15 204 15 242 -0.2 +3 182 Gross profit 5 154 3 914 +32 +1 152 Sel
Slide 39: Accrued result on derivatives: metals and currency hedging position
The accrued result on derivatives achieved by KGHM Polska Miedź S.A. as at 31 December 2017 amounted to –PLN 227 million Market risk management – hedging position (as at 31 December 2017) Position in derivatives on the metals and currencies markets Copper USD/PLN in tonnes in million USD 12 000 21 0
Slide 40: Accrued result on derivatives: interest rate position
The accrued result on derivatives achieved by KGHM Polska Miedź S.A. as at 31 December 2017 amounted to –PLN 227 million Market risk management – hedging position (as at 31 December 2017) Position in derivatives on interest rates Interest rate (LIBOR 3M USD) Result on derivatives in million USD In 2
Slide 41: Thank you!
Get our mobile KGHM IR app! Thank you! Investor Relations kghm.com/en/investors ir@kghm.com +48 76 74 78 280 41