Stelco — Corporate Update (July 2025)
14 slides from Stelco's corporate update, Jul 16, 2025
Slide 1: Hamilton Works Community Liaison Committee Meeting
Hamilton Works Community Liaison Committee Meeting July 16, 2025
Slide 2: Agenda
Agenda 1. Welcome 2. Review and Approval of Agenda 3. Review and Approval of Minutes of 30 April 2025 Meeting 4. Coke Battery Performance 5. Additional Updates 6. Community Feedback 7. 2025 CLC Meeting Dates 8. Adjournment 2
Slide 3: Agenda
Agenda 1. Welcome 2. Review and Approval of Agenda 3. Review and Approval of Minutes of 30 April 2025 Meeting 4. Coke Battery Performance 5. Additional Updates 6. Community Feedback 7. 2025 CLC Meeting Dates 8. Adjournment 3
Slide 4: Coke Battery Performance – Method 303: Daily Review (Q2 2025)
Coke Battery Performance – Method 303 Performance Review – Daily (Q2 2025) Doors Lids Off-takes Date (% Leaks) (% Leaks) (% Leaks) 2015 Thresholds 54% 2% NA (July 2 start) 2016 Thresholds 32% 2% NA 2017-2019 Thresholds 10% 2% 5% 2020 - 2025 Thresholds 5% 1% 4% Apr - June 2025 Range 0 – 7.33% 0 – 0.7
Slide 5: Coke Battery Performance – Method 303: Rolling Average (Q2 2025)
Coke Battery Performance – Method 303 Performance Review – 30-Day Rolling Avg. (Q2 2025) Doors Lids Off-takes Charging (sec) Date (% Leaks) (% Leaks) (% Leaks) (log avg) 2015 Limits (July 2 start) 38% 0.8% 25% 12 sec 2016 Limits 22.5% 0.8% 15% 12 s 2017-2019 Limits 7% 0.8% 4.2% 12 s 2020 - 2025 Limi
Slide 6: Coke Battery Performance – Method 303: Daily Observations (Q2 2025)
Coke Battery Performance – Method 303 Performance Review – Daily Observations (Q2 2025) Pushing Emission Date (opacity %) 2015 Threshold (July 2 start) ≥ 50% 2016 – 2018 ≥ 50% 2019 ≥ 40% 2020 – 2025 ≥ 30% Apr - June 2025 0 – 24.2% Range (3.33%) (Average) April - June Operational Adjustments • In com
Slide 7: Coke Battery Performance: Additional Items and Community Feedback
Coke Battery Performance Additional Items Community Feedback • No complaints attributable to Stelco’s operations were received • MECP invited to provide verbal comments 7
Slide 8: Agenda
Agenda 1. Welcome 2. Review and Approval of Agenda 3. Review and Approval of Minutes of 30 April 2025 Meeting 4. Coke Battery Performance 5. Additional Updates 6. Community Feedback 7. 2025 CLC Meeting Dates 8. Adjournment 8
Slide 9: Additional Updates: Water Discharge Permit Amendment Updates
Additional Updates Water Discharge Permit Amendment Updates • Gate & Scale Relocation Stormwater • ECA amendment application submitted April 21 for MECP review • Gate & Scale Relocation Construction • Registered for an EASR in the event dewatering is required during construction 9
Slide 10: Agenda
Agenda 1. Welcome 2. Review and Approval of Agenda 3. Review and Approval of Minutes of 30 April 2025 Meeting 4. Coke Battery Performance 5. Water Discharge Permit Amendment Updates 6. Community Feedback 7. 2025 CLC Meeting Dates 8. Adjournment 10
Slide 11: Community Feedback
Community Feedback Additional Questions? • Please contact us with concerns or questions about our operations - environment@stelco.com 11
Slide 12: CLC Meeting Dates
CLC Meeting Dates • Next meeting dates for 2025: Jan 15 April 30 July 16 October 29 12
Slide 13: Agenda
Agenda 1. Welcome 2. Review and Approval of Agenda 3. Review and Approval of Minutes of 30 April 2025 Meeting 4. Coke Battery Performance 5. Water Discharge Permit Amendment Updates 6. Community Feedback 7. 2025 CLC Meeting Dates 8. Adjournment 13
Slide 14: Thank You.
| STELCO | 9 The Steel Company of Canada Thank You. stelco.com