  1. Slide 1: Building a Global Uranium Company

    Building a Global Uranium Company Investor Presentation Bell Potter Emerging Leaders Conference (12-13 September 2023) John Borshoff - MD/CEO 13 September 2023 DYL: ASX / NSX (Namibia) DYLLF: OCTQX www.deepyellow.com.au

  2. Slide 2: Disclaimer

    Disclaimer Past performance and readers should not place undue reliance on such forward-looking information. The Company disclaim any intent or obligations to finalise, check, update or revise any forward-looking statements whether as a result of new This presentation has been prepared by Deep Yello

  3. Slide 3: Deep Yellow - Building on Five Guiding Principles

    Deep Yellow - Building on Five Guiding Principles ● Decarbonisation ● Uranium Supply Shortage ● Nuclear Demand Outstripping Supply ● Capturing Growth ● ESG Focus 3

  4. Slide 4: Best Positioned Uranium Mid-Cap Globally

    Best Positioned Uranium Mid-Cap Globally Deep Yellow has the global diversity seen as a necessity by off-takers – located in two Tier-1 mining jurisdictions Significant production capability - once in production, Deep Yellow will be the largest pure-play uranium producer on the ASX - production capa

  5. Slide 5: Globally Diversified with Two Flagship Projects

    Globally Diversified with Two Flagship Projects • Project portfolio provides diversity by asset, stage of Advanced-stage development and geographic location Early-stage to continue organic pipeline • Largest uranium resource base of any Omahola Alligator River ASX-listed company Namibia Northern Ter

  6. Slide 6: Balanced & Optimised Team

    Balanced & Optimised Team Steady deliberate program upgrading board with appropriate Board experience and skill levels to ensure operational, financial and governance excellence Proven leadership understanding what needs to be developed for Leadership uranium supply in the post-Fukushima reconstruct

  7. Slide 7: Capital Structure - Performance FY23

    Capital Structure - Performance FY23 1.60 70 FY23 1.40 Market Cap Range $450M - $910M 60 1.20 50 1.00 A$/Share1 40 0.80 30 0.60 20 0.40 Merger Completion Tumas DFS Completion August 2022 Feb 2023 10 0.20 Share Price U3O8 Price 0 0 22-Aug-20 22-Feb-21 22-Aug-21 22-Feb-22 22-Aug-22 22-Feb-23 22-Aug-23

  8. Slide 8: Uranium is Critical for a Clean Energy Future

    01 Uranium is Critical for a Clean Energy Future www.deepyellow.com.au

  9. Slide 9: The Global Equation - Zero Emission needs to address many areas

    The Global Equation - Zero Emission needs to address many areas World Electricity Production by Source1 Other Coal Gas Oil Hydropower Nuclear Wind Solar Renewables 36% 23% 3% 15% 10% 6% 4% 3% 4% renewables on global scale Total Global Energy 175,000 TWh (2022) More electricity Equation – required 75

  10. Slide 10: Land Footprint & Productivity of Nuclear vs Solar & Wind

    Land Footprint & Productivity of Nuclear vs Solar & Wind Capacity Factors by Energy Source One x 1GW Nuclear Reactor equivalent To generate ● 3 Wind farms (each of 1GW) same Nuclear 93% ● 4 Solar farms (each of 1GW) electrical power as a Impact on land use & productivity – Land use for 1GW 1GW nucle

  11. Slide 11: Nuclear Essential - net zero nuclear initiative to triple nuclear by 2050

    Nuclear Essential -net zero nuclear initiative to triple nuclear by 2050 Nuclear becoming the clear winner and the uranium supply industry is well-placed for significant growth and value uplift in global energy transition Most major economies in full alignment demanding more nuclear. This hasn’t hap

  12. Slide 12: Strong World Nuclear Power Reactor Growth

    Strong World Nuclear Power Reactor Growth Status July 20231 Nuclear Reactors Globally US (94); France (56); China (55) Proposed Reactors 321 436 Russia (37); Japan (33); Korea (25); Other (136) Reactors Planned Reactors Under 111 Construction China (45); Russia (25); 59 India (12); Canada (11); Chin

  13. Slide 13: Demand - Governments Pivot Towards Nuclear

    Demand - Governments Pivot Towards Nuclear Increasing global ● Sweden changes policy from “100% renewable electricity concern for Energy production” to “100% Fossil Free” Security, ● Belgium reverses decision to shut down reactors in 2025, now Inability for extends to 2036 renewables to deliver, ● B

  14. Slide 14: WNA Sept'23 Market Study - exposes huge challenges to meet new demand

    WNA Sept’23 Market Study - exposes huge challenges to meet new demand ● Large, long-life operations have ceased production Degradation of ● No new production without significant uranium price uranium supply incentivisation (US$65/lb-$75/lb+) industry over time ● Global mining houses (Rio Tinto) have

  15. Slide 15: Nuclear Fuel Cycle Under Pressure

    Nuclear Fuel Cycle Under Pressure Fabrication o Increasing demand for conversion and enrichment o SWU trading at a services causing 10 year high – US$134/SWU extraordinary price increases o Inevitable pricing pressure will +300% move to uranium price as high increase Enrichment Reactor demand works

  16. Slide 16: Project Pipeline Positioned for Growth and Value

    02 Project Pipeline Positioned for Growth and Value www.deepyellow.com.au

  17. Slide 17: Tumas Project, Namibia - Overview

    Tumas Project, Namibia - Overview ● Uranium and mining friendly jurisdiction Page 1 of 2 ● Ore Reserves of 67.3Mlb increased by 120% in CY2021 o 22.5-year LOM achieved ● DFS completed January 2023 ● EIA submitted April 2023 and grant of Mining Lease expected late Q3/CY2023 ● Further 10+ years to LOM

  18. Slide 18: Tumas Project Analysis (US$)

    Tumas Project Analysis (US$) Project Financials (Ungeared): Real Unit 65/lb 77/lb1 85/lb Commentary Project operating life Years 22 22 22 U3O8 Produced  Head grade is Mlb 64 64 64 340ppm U3O8 (av) Gross revenue: total $M 4,272 5,166 5,548 Operating margin (EBITDA) $M 1,790 2,654 3,024  Annual prod

  19. Slide 19: Mulga Rock Project – 100%

    Mulga Rock Project – 100% ● Located in the Tier-1 mining jurisdiction of Western Page 1 of 2 Australia ● Globally significant Mineral Resource of 71.2Mt @ 570ppm for 90.1Mlb U3O8, positioning Mulga Rock as one of the largest undeveloped uranium projects in Australia ● Only uranium project in WA to r

  20. Slide 20: Mulga Rock Project FY23 Activities

    Mulga Rock Project FY23 Activities ● Test work on 63 deep geo-metallurgical Page 1 of 2 samples - expected completion early 2024 Princess ● Resource/reserve upgrade and ore variability drilling : 656 holes/36,647m, completed August 2023 ● Updated MRE to Indicated status Q4/2023 Ambassador West Ambas

  21. Slide 21: Exceptional Exploration Upside

    Exceptional Exploration Upside ALLIGATOR RIVER PROJECT, NORTHERN TERRITORY - 100% OMAHOLA BASEMENT PROJECT, NAMIBIA - 100% Page 1 of 2 ● Located in the world class uranium province of Alligator ● Measured, Indicated and Inferred Resource base of 125Mlb River, which hosts some of the highest-grade ur

  22. Slide 22: Looking Ahead - a Differentiated Company

    03 Looking Ahead - a Differentiated Company www.deepyellow.com.au

  23. Slide 23: Two Substantial, Advanced Uranium Projects to Produce +7Mlb

    Two Substantial, Advanced Uranium Projects to Produce +7Mlb Page 1 of 2 Initial Investment Production Mulga Rock Project Tumas Project 1 2028 3.5 3.5 2026 2.0 3.0 3.6 3.6 3.6 1.5 Year 0 Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 0 Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Tumas − 22.25YR LOM Mul

  24. Slide 24: Opportunities Through Consolidation

    Opportunities Through Consolidation ● Nuclear demand expected to increase dramatically 2030-2060 ● Outside the 2 majors (Cameco, Kazatomprom) the supply industry fragmented and largely dysfunctional ● Supply sector needs massive re- shaping to meet identified growth challenges ● Deep Yellow well-pos

  25. Slide 25: Key Workstreams for next 12 Months

    Key Workstreams for next 12 Months Page 1 of 2 TUMAS PROJECT MULGA ROCK ALLIGATOR RIVER M&A • Q3 2023 - Further focused test • Q3 2023 – 656 air core drill • Q2 2023 - New resource • Ongoing - Continued focus work continuing to optimise program completed for estimate for Angularli Deposit on accreti

  26. Slide 26: Best Pure Play Uranium Investment

    Best Pure Play Uranium Investment Page 1 of 2 Deep Yellow is successfully establishing the right platform Uranium market backdrop creates exceptional opportunities in the post-Fukushima supply reconstruction era Growth initiatives are led by an experienced board, proven leadership and team, and are

  27. Slide 27: For further information

    For further information: T: +61 8 9286 6999 E: info@deepyellow.com.au W: www.deepyellow.com.au : @deepyellowltd : deep-yellow-limited

  28. Slide 28: Appendix Mineral Resources

    Cut-off Tonnes U 3 O8 U 3 O8 U 3 O8 Resource Categories (Mlb U3O8) Appendix Deposit Category (ppm U 3 O8 ) (M) (ppm) (t) (Mlb) Measured Indicated Inferred Mineral Resources BASEMENT MINERALISATION Omahola Project - JORC 2012 1 INCA Deposit ♦ Indicated 100 21.4 260 5,600 12.3 - 12.3 - Notes: INCA Dep

  29. Slide 29: Appendix Mineral Resources

    Appendix Deposit Category Cut-off Tonnes U 3 O8 U 3 O8 U 3 O8 Resource Categories (Mlb U3O8) Mineral Resources (ppm (M) (ppm) (t) (Mlb) Measured Indicated Inferred U 3 O8 ) Northern Territory Angularli Project - JORC 2012 1 Angularli Inferred 1,500 1.37 10,900 14,917 32.9 - - 32.9 Notes: Angularli P