Investigator Silver Limited · ASX:IVR
Investigator Silver — Investigator Resources — Noosa Mining Investor Conference 2024
22 slides from Investigator Silver's conference presentation, Jul 18, 2024
Slide 1: Thinking Silver? Think Investigator.
For personal use only Thinking Silver? Think Investigator. Advancing Australia’s highest grade Silver project. Noosa Mining Investor Conference Presentation 18 July 2024 ASX:IVR
Slide 2: Disclaimer
Disclaimer The information in this presentation is published to inform you about Investigator Resources Limited and its activities. Some statements in this presentation regarding estimates or future events are forward looking statements. They involve risk and uncertainties that could cause actual re
Slide 3: What do you really need to know about Silver?
What do you really need to know about Silver……? For personal use only Only that industrial demand is skyrocketing.…. Investigator Resources Limited - Noosa Mining Investor Conference – 18 July 2024 3
Slide 4: What else do you need to know about Silver?
What else do you need to know about Silver*……? Photovoltaic Photography Brazing / Alloys Both a precious and an industrial metal 3% For personal use only 8% 4% • Traditional store of wealth Etylene Oxide 5% Other Industrials • Most electrically conductive metal 14% • Circuit boards, semiconductors •
Slide 5: What is happening with silver supply & demand?
What is happening with silver supply & demand……? For personal use only Investigator Resources Limited - Noosa Mining Investor Conference – 18 July 2024 5
Slide 6: What is the Au:Ag ratio and why is that important?
What is the Au:Ag ratio and why is that important.…? For personal use only Investigator Resources Limited - Noosa Mining Investor Conference – 18 July 2024 6
Slide 7: What you really need to know about Investigator
What you really need to know about Investigator.…. $0.08 $35.00 For personal use only $0.07 $33.00 IVR (A$/sh) $0.07 $31.00 Silver (U$) $0.06 $29.00 $0.06 $27.00 Silver (US$/oz) IVR (A$/sh) $0.05 $25.00 $0.05 $23.00 $0.04 $21.00 $0.04 $19.00 $0.03 $17.00 Jul 2023 Sep 2023 Nov 2023 Jan 2024 Mar 2024
Slide 8: What do you need to know about Investigator?
What do you need to know about Investigator? South Australia focus - 8,150km2 • Paris Silver Project For personal use only • Australia’s highest grade primary Ag project • 57Moz Silver + 99kt Lead - JORC (2012) Resource #1 • PFS completed 2021 • Resource updated July 2023 • DFS in progress – Sept Qt
Slide 9: For personal use only
For personal use only Investigator Resources Limited - Noosa Mining Investor Conference – 18 July 2024 9
Slide 10: Paris Silver Project – 100% IVR
Paris Silver Project – 100% IVR Pre Tax NPV8: Pre-Feasibility Study#2 For personal use only A$202 Million Paris – the highest grade undeveloped primary silver IRR: project in Australia 47.9% • Simple open pit – 70% free dig Project Life • Dry stacked tailings 7 years • Hybrid diesel & solar power ge
Slide 11: Paris Silver Project – Definitive Feasibility Study
Paris Silver Project – Definitive Feasibility Study • Southern resource extension For personal use only • Metallurgical optimisation • Crush, grind and Lead recovery test work • Final Silver leach studies – incl tails & detox • Hydrological study – pit & process water • Environmental survey • Engage
Slide 12: Paris Silver Project – Process plant layout
Paris Silver Project – Process plant layout For personal use only Investigator Resources Limited - Noosa Mining Investor Conference – 18 July 2024 12
Slide 13: 2024 exploration program within 5km of Paris
2024 exploration program within 5km of Paris For personal use only • 2 Passive Seismic programs • 98 station ANT • 300 station Tromino • Gravity survey – 3,000 station • Soil sampling • 5,000m air core drilling @ Apollo • 8m @ 1,262g/t Ag from 149m #3 • Mineralogically identical to Paris #3 – As rel
Slide 14: 2024 exploration program results
2024 exploration program results…. For personal use only 2 Discoveries: Perseus: • 1m @ 71g/t Ag & 0.6% Pb from 38m #4 • Similar petrology to Paris Manto: • 3m @ 0.1% Cu & 0.1% Ni from 30m #4 And…… • Geophysical interps in progress • Follow up drilling H2 2024 #4 – As released to ASX on 30 May 2024
Slide 15: Investigator – SA Regional Opportunities
Investigator – SA Regional Opportunities For personal use only Uno Morgans tenements: 80km east of Paris…. • Similar structural/geologic setting to Paris • Silver, Gold & Base metal potential • 24 of 27 holes intersected mineralisation #5 • 12m @ 240g/t silver from 78m (12 Mile) • 123m @ 0.48% zinc
Slide 16: Diversification – Molyhil Tungsten/Molybdenum Project - NT
Diversification – Molyhil Tungsten/Molybdenum Project - NT • 3 stage Earn-In to Joint Venture with Thor Energy (ASX:THR) For personal use only • Stage 1 – completed – 25% interest earned (& 40% Bonya) • Stages 2 & 3 – total $7M over 6 years • JORC 2012 Mineral Resource Estimate # • 4.65Mt @ 0.26% WO
Slide 17: For personal use only
For personal use only Investigator Resources Limited - Noosa Mining Investor Conference – 18 July 2024 17
Slide 18: Investigator – The Value Proposition
Investigator – The Value Proposition……. • Silver exposure: • Paris is the highest-grade undeveloped Silver project in Australia For personal use only • Robust project PFS financials, opportunities to enhance - DFS in progress • Stable jurisdiction, clear pathway to approval, experienced team • Regio
Slide 19: Thank you
For personal use only Thank you • Andrew McIlwain, Managing Director • 47 King Street, Norwood SA 5067 Thinking Silver? Think Investigator.… • • +61 (0) 8 7325 2222 amcilwain@investres.com.au Investigator Resources Limited - Noosa Mining Investor Conference – 18 July 2024 19 • www.investres.com.au
Slide 20: Appendix – Paris Mineral Resource Estimate
Appendix 1 – Paris Mineral Resource Estimate #7 For personal use only Category Mt Ag ppm Pb % Ag Mozs Pb Kt Indicated 17 75 0.5 41 85 Inferred 7.2 67 0.42 16 14 Total 24 73 0.41 57 99 Table 1: 2023 Paris Silver Project Mineral Resource estimate (25g/t silver cut-off grade). (Note: Total values may d
Slide 21: Appendix – Molyhil Earn-In to JV Agreement
Appendix 2 – Molyhil Earn-In to JV Agreement #8 General Terms • 3 stage Earn-In to Joint Venture with Thor Mining (ASX:THR) For personal use only • Stage 1: • Payment to Thor of $100,000 on execution of Heads of Agreement documentation • Expenditure of $1M over 18 months (includes $100k HoA fee abov
Slide 22: Appendix – Molyhil Mineral Resource Estimate
Appendix 3 – Molyhil Mineral Resource Estimate #9 0.05% WO3 cut-off to 150mRL WO3 Mo Cu Category Tonnes Grade % Tonnes Grade % Tonnes Grade % Tonnes For personal use only Measured 1,160,000 0.34 3,900 0.11 1,300 0.06 700 Indicated 1,664,000 0.27 4,600 0.10 1,600 0.05 800 Inferred 1,823,000 0.20 3,60
Investigator Resources — Noosa Mining Investor Conference 2024 on 6ix