Agl Energy Limited · ASX:AGL

Agl Energy — Corporate Update (September 2019)

19 slides from Agl Energy's corporate update, Sep 6, 2019

  1. Slide 1: Newcastle Community Dialogue Group

    Newcastle Community Dialogue Group 06 September 2019 – Meeting 11

  2. Slide 2: Open and welcome, apologies, declarations, previous minutes and business arising

    Open and welcome, apologies, Newcastle Gas Storage Facility 1 declarations, previous minutes and business arising 3 Latest news Newcastle Power Station Project 2 4 General business Latest news and next steps Next meeting and close

  3. Slide 3: Apologies, declarations, previous minutes and business arising

    Apologies, declarations, previous minutes and business arising

  4. Slide 4: Newcastle Power Station Project: Latest news and Next steps

    Newcastle Power Station Project Latest news and Next steps

  5. Slide 5: Newcastle Power Station

    Newcastle Power Station ~250 MW Dual Fuel Peaker Low Unrestricted 132kV Fast Start Gas Diesel Capacity operation Factor 5

  6. Slide 6: Location

    aurecon Newcastle 250MW Gas Fired Power Station Preliminary Environmental Assessment FIGURE? Ste layout plan agl

  7. Slide 7: EIS process

    EIS process 2019 October November December Lodge EIS with the NSW Department of Planning for an ‘Adequacy Review’. Formal lodgement. EIS goes on exhibition. Submissions welcome. AGL prepares and lodges a ‘Submissions Report’ responding to submissions. 06 September 2019 7

  8. Slide 8: Environmental Impact Statement (EIS)

    Environmental Impact Statement (EIS) - An EIS details the anticipated potential environmental impacts of a development on the environment as well as proposing avoidance, mitigation and offset measures. Aboriginal Heritage Assessment Non-Aboriginal Heritage Assessment Air Quality and GHG Assessment P

  9. Slide 9: Possible venue for EIS public display

    Possible venue for EIS public display Hunter Region Botanic Gardens 2100 Pacific Hwy, Heatherbrae NSW 2324 06 September 2019 9

  10. Slide 10: Possible venues for EIS information sessions (Oct – Nov)

    Possible venues for EIS information sessions (Oct – Nov) Tomago Bowling and Sporting Club Tomago House Hunter Region Botanic Gardens 657 Tomago Rd, Tomago NSW 2322 421 Tomago Rd, Tomago NSW 2322 2100 Pacific Hwy, Heatherbrae NSW 2324 06 September 2019 10

  11. Slide 11: Construction timeline

    Q2 18 Q3 18 Q1 19 Q2 19 Q3 19 Q4 19 Q1 20 Q2 20 Q3 20 Q4 20 ..Q3 22 Community Engagement Site Selection Land Access Easements Final Investment Decision PEA EIS Government Assessment Construction PS concept design Online Invitation to Tender Tender Gas concept design Documentation & Negotiation Elec

  12. Slide 12: Newcastle Gas Storage Facility: Latest news

    Newcastle Gas Storage Facility Latest news

  13. Slide 13: Environmental management report and pollution incident response plan

    ➢ We have completed and submitted our annual environmental management report ➢ We have updated our pollution incident response plan 06 September 2019 13

  14. Slide 14: Maintenance, safety and audit updates

    ➢ Completion of Liquefaction System Annual Maintenance Shutdown ➢ Installation of additional isolation valves ➢ Commissioned standby firewater tank ➢ Have commenced site refresher visits with NSW Fire and Rescue ➢ Completion of NSW Department of Planning 3 yearly Hazard Audit ➢ Commenced preparation

  15. Slide 15: Community investment grants awarded

    Organisation Initiative Money granted Paid? Program complete? Hunter Breast Cancer Funding of 600 HBCF Comfort Care $6,782.00 Y Y Foundation Packs. Nelson Bay Croquet Purchase of boom sprayer for $1,255.00 Y N Club maintenance of the club's croquet courts. Tanilba Bay Senior Installation of air con

  16. Slide 16: Hunter Breast Cancer Foundation Tilligerry Arts Group

    Hunter Breast Cancer Foundation Tilligerry Arts Group 06 September 2019 16

  17. Slide 17: Local Community Investment Program advertising

    Local Community Investment Program expected to be advertised during November 2019 in the following publications: • Port Stephens Examiner • Maitland Mercury • Newcastle Herald • Facebook paid advertising for three LGAs. 06 September 2019 17

  18. Slide 18: Next meeting and close

    General Business Next meeting and close

  19. Slide 19: Contacts

    Lisa Andrews Ernesto Calderon Independent Chairperson Newcastle Gas Storage Facility and 0401 609 693 Newcastle Power Station Project Community Relations Manager lisaandrews.ic@gmail.com 0498 001 536 ecalderon@agl.com.au

AGL Energy — Corporate Update (September 2019) on 6ix