Iluka Resources Limited · ASX:ILU

Iluka Resources — Technical Presentation (January 2004)

8 slides from Iluka Resources's technical presentation, January 2004

  1. Slide 1: Procurement Strategy

    Procurement Strategy Rod Schier DFS Project Manager

  2. Slide 2: Procurement Strategy: Scope, Vendor Pre-qualification, Database

    Procurement Strategy n Scope u Commence Procurement activities - second quarter 2004 u Equipment $60 m u Bulk materials $80 m u Number of Packages 180 + n Vendor Pre-qualification Process u Technical u Quality Assurance u Commercial u Industrial Supplies Office Coordination n Vendor Database u Roche

  3. Slide 3: Procurement Strategy: Tender Process and Evaluation Criteria

    Procurement Strategy n Tender Process u Procurement Plan « Competitive tendering u Sealed tender protocol n Tender Evaluation Criteria u Technical conformance to specifications u Quality u Commercial « Price « Terms and conditions

  4. Slide 4: Implementation Strategy

    Implementation Strategy [ADNIBON OF OOWNER EDI UNSTED

  5. Slide 5: Construction Scope of Work

    Construction Scope of Work n On Site u Site Preparation u Temporary Facilities u Power generation u Utilities and Interconnections n Off Site u Accommodation of Construction Personnel u Fabrication of plant structures, plate work and piping u Fabrication of process equipment

  6. Slide 6: Construction Quantities

    Construction Quantities ---------------------------------------------------------------- Commodity Quantity ---------------------------------------------------------------- n Site preparation 300,000 m3 n Steel 4,000 t n Pipe 500 t n Concrete 6,000 m3 n Equip (Total) 480 ea n Tanks 20 ea

  7. Slide 7: Construction Strategy Key Project Objectives

    Construction Strategy Key Project Objectives n To ensure the health safety and welfare of the construction workforce n To protect the well-being of workforce personnel and assets n Be judged by Hamilton and Horsham communities as welcome guests u Attract highest calibre of construction workforce u H

  8. Slide 8: Construction Execution Strategy

    Construction Execution Strategy n On site works u Earthworks and civil contracts tendered local and regional u Fabrication contracts tendered local and regional u Utilise specialist Erection Contractors to execute the work « Direct work packages horizontal and vertical scope « Major contractors iden