Vault Minerals Limited · ASX:VAU

Vault Minerals — Red 5 — Investor Presentation (June 2016)

23 slides from Vault Minerals's investor presentation, Jun 14, 2016

  1. Slide 1: A growing, low-cost gold producer in the Philippines

    For personal use only A growing, low-cost gold producer in the Philippines Investor Presentation – June 2016 Mark Williams, Managing Director ASX Code: RED 1

  2. Slide 2: Presentation Overview: 5 Key Pillars

    Presentation Overview: 5 Key Pillars ASX-listed gold producer operating in the Philippines For personal use only 1. Low-cost production from open pit operations at Siana – Projected to achieve higher end of FY2015/16 guidance at 57-60,000oz – Operating cost profile expected to reduce with expected s

  3. Slide 3: Corporate Snapshot

    Corporate Snapshot Unhedged and debt-free ASX-listed gold producer operating in the Philippines For personal use only ASX Code RED Directors and Management Share price (as at 10 June 2016) A$0.088 Kevin Dundo – Chairman Issued shares 761.9M Mark Williams – Managing Director Market capitalisation (at

  4. Slide 4: Siana Gold Project – Location

    Siana Gold Project – Location Located in a highly prospective and well-established mining region For personal use only 4

  5. Slide 5: Open Pit Mining Schedule and Production Guidance

    Open Pit Mining Schedule and Production Guidance Open pit on track to achieve guidance with reducing cost profile For personal use only 1. 2015/16 financial year forecast production profile: Low cost open pit Open Pit Update and FY 2017 Guidance production Quarter Estimated Au oz recovered 2. Septem

  6. Slide 6: Siana – Underground Feasibility Study

    Siana – Underground Feasibility Study A blueprint to deliver future growth at Siana For personal use only 1.  Updated Feasibility Study completed in Low cost open pit June 2016 by underground mining production consultants Mining One Pty Ltd: 2. – Forecast production of ~60,000ozpa over Underground

  7. Slide 7: Siana – Underground Resources & Reserves

    Siana – Underground Resources & Reserves Underpins robust long-term underground mine development For personal use only 1. Siana Underground deposit: Low cost open pit production  Indicated and Inferred Mineral Resource of 3.8Mt @ 5.8g/t 2. Au for 704,000oz Underground development  Maiden Probable

  8. Slide 8: Siana – Underground Production Profile

    Siana – Underground Production Profile Robust economics with relatively modest capital cost estimate For personal use only 1. 600,000 7.00  Projected 12-month Low cost open pit timeline to access production 6.00 underground ore 500,000  Potential to fund Total Ore Production & Grade 2. 5.00 Underg

  9. Slide 9: Siana – Underground Mining Method

    Siana – Underground Mining Method A blueprint to deliver future growth at Siana For personal use only 1.  Mine plan based on use of Low cost open pit a conservative short up- production hole retreat mining method with cemented 2. Underground paste-fill for ore extraction development  Proven mining

  10. Slide 10: Siana – Long-Term Underground Mine Plan

    Siana – Long-Term Underground Mine Plan Includes assessment of entire resource beneath the Siana open pit For personal use only 1.  Feasibility Study also considered Low cost open pit technical and economic viability production of the entire UG resource – including Indicated and Inferred 2. Undergr

  11. Slide 11: Key Parameters

    Key Parameters From updated Underground Feasibility Study Financial Model For personal use only 1. Summary of Key Parameters from Underground Feasibility Low cost open pit Study Financial Model production Life of Mine (LOM) including development Years ~9 2. Underground LOM Ore Mined Mt 3.8 developme

  12. Slide 12: Major Capital Expenditure Items for FY 2016-17

    Major Capital Expenditure Items for FY 2016-17 Estimated costs For personal use only  Short-term loan facility of 1. • Open Pit Development A$17.2M Low cost 300 million Philippine open pit production • Underground Development A$13.6M pesos (~A$8.8M) secured 2. • Paste-Fill Plant A$18.2M from Philip

  13. Slide 13: Siana Underground – Major Project Risks

    Siana Underground – Major Project Risks Risk Management Strategies For personal use only 1. Risk Area Risk Mitigation Strategies Low cost open pit production • Water ingress into  Upgrade open pit dewatering capability to 1000 litres/second underground mine  Install additional four 250m deep water

  14. Slide 14: Siana Underground – Major Project Risks

    Siana Underground – Major Project Risks Risk Management Strategies For personal use only 1. Risk Area Risk Management Strategies Low cost open pit production • Development rates  Conservatively targeting advance rates of 70m per month in the decline and 30m per month in any ore drive 2. Underground

  15. Slide 15: The Future – Exploration and Growth

    The Future – Exploration and Growth Surigao del Norte – one of the most mineralised provinces in one of the most mineralised countries globally For personal use only 1. • Exploration targets identified Low cost open pit production • Increase in near-mine and regional exploration activities  Near-mi

  16. Slide 16: Mapawa Project

    Mapawa Project Maiden resource paves the way for Scoping Study; longer term exploration upside For personal use only 1. Low cost  20km north of Siana open pit production  JORC 2012 Indicated and Inferred Mineral Resource for LSY deposit of 2. Underground 8.8Mt @ 1.0g/t Au for 289,000oz development

  17. Slide 17: Mapawa Project

    Mapawa Project Scoping Study paves the way for engineering studies; longer term exploration upside For personal use only 1. Low cost  Successful 2016 Scoping Study indicates open pit potential to develop an initial open pit production operation based on the Mapawa LSY 2. deposit, with ore delivered

  18. Slide 18: Processing Plant

    Processing Plant Only modern operating gold plant in a highly endowed world-class mining region For personal use only 1. Low cost  Modern 1.1Mtpa gravity and carbon-in-leach open pit production (CIL) processing facility  Constructed in 2011 2. Underground development  Heart of the plant is an Out

  19. Slide 19: Management Track Record – Recent Achievements

    Management Track Record – Recent Achievements Realising our potential at Siana and beyond For personal use only 1. Low cost  Gold production on track to achieve higher end of open pit FY2016 guidance at 57-60,000oz production  Operational improvements completed – upgrade of haul roads, re-build of

  20. Slide 20: Sustainable Development Initiatives

    Sustainable Development Initiatives Strong commitment to health and safety, community and environmental programs For personal use only 1. Support continues in the areas of: Low cost open pit • Health production • Community education 2. • Welfare • Agricultural Underground developmenjt • Infrastructu

  21. Slide 21: Summary: Key Investment Takeaways

    Summary: Key Investment Takeaways ASX-listed gold producer operating in the Philippines For personal use only 1. Low-cost production from open pit operations at Siana – Projected to achieve higher end of FY2015/16 guidance at 57-60,000oz Red 5 has a clear – Operating cost profile expected to reduce

  22. Slide 22: Disclaimer and Competent Person’s Statement

    Disclaimer and Competent Person’s Statement For personal use only Competent Person’s Statement for JORC 2012 Mineral Resource and Ore Reserve The information in this report that relates to Mineral Resources and Ore Reserves for the Siana Open Pit is extracted from the report titled Siana Open Pit Mi

  23. Slide 23: Thank you.

    For personal use only Thank you. Mark Williams (Managing Director) Kevin Dundo (Chairman) Web: www.red5limited.com E-mail: info@red5limited.com 23 23

Red 5 — Investor Presentation (June 2016) on 6ix