Slide 1: Q2'26 Supplemental Investor Presentation
A u g u s t 2 0 26 Q2’26 Supplemental Investor Presentation A world-leading technology company for AI and Bitcoin mining infrastructure
Slide 2: Disclaimer & Forward-Looking Statements
Disclaimer & Forward- Securities Act of 1933, as amended (the “Securities Act”), Section 21E of the Securities Exchange Act of 1934, as amended, or the Private Securities Litigation Looking Statements Reform Act of 1995. These statements reflect the Company’s intent, beliefs or current expectations
Slide 3: Q2'26 Highlights
Q2’26 Highlights Total Revenue Total Hash Rate Self-Mining(1)(2) Total Mining Rigs Self-mining(1)(2) 73.0 EH/s Revenue ~$229 M 47% 342% 243,000 113% Total Electrical Capacity(1) BTC Mined(3) AI Cloud ARR(4) 3.0 GW 12% 2,694 377% ~$76 M 77%(5) Key Messages: Expanding AI strategy across multiple initi
Slide 4: BITDEER: Vertical Integration Across the Value Chain
BITDEER: Vertical Integration Across the Value Chain ASIC Design & Hardware Self Mining Manufacturing Colocation AI Data Center AI Cloud Powered By: 3.0 GW Total Global Energy Infrastructure NNAASSDDAAQQ: : BBTTDDRR 4
Slide 5: 3.0 GW Capacity Secured and Globally Distributed
3.0 GW Capacity Secured and Globally Distributed Bitdeer has ample growth runway to continue its momentum into AI / HPC Existing Pipeline Total Location MW MW MW Texas, US Ohio, US Tennessee, US Oromia Region, Tydal, Norway Molde, Norway Rockdale, Texas 563 179 742 563 MW 174 MW 86 MW Ethiopia 180 M
Slide 6: Core Business Lines
Core Business Lines NASDAQ: BTDR 6
Slide 7: Colocation AI Data Center Pipeline
Colocation AI Data Center Pipeline New Developments Co-Location Services TYDAL: Rack-Ready Datacenter Signed 16 year AI/HPC Data Center colocation lease with Volta Contract Duration: 10 – 20 Years $4.7 billion contracted revenue over 16 years Capex / MW(1): $8mm - $12mm $8 billion contracted revenue
Slide 8: Tydal HPC Contract: Key Commercial Terms
Tydal HPC Contract: Key Commercial Terms 121 IT MW Remaining Capex of ~$500M Contracted IT Capacity Based on 133 Gross MW and PUE of 1.1 $202 / kW / month payment 3% Expected 16-Year Average Economics Includes 3% annual rent escalators (Base Rent + Service Fee) $4.7B Modified Gross Lease Expected To
Slide 9: Tydal: Renewable-Powered AI Infrastructure
Tydal: Renewable-Powered AI Infrastructure Power Infrastructure Grid Connection: Connects to both Norwegian and Swedish central power grids. Powered by 16 independent hydropower generators and 1 wind farm, 4 of the 16 hydropower generators are directly below the site Reliability: Higher than Tier 3
Slide 10: Tydal Transaction Overview & Economics
Tydal Transaction Overview & Economics: Base-Term Lease Extended Lease (16 Years)1 (24 Years) Assumes exercises of Description 16-Year Base-term Lease 8-year renewal option Expected Total Contracted Value $4.7B $8.0B Implied Average Annual Revenue $293M $333M Implied Average Annual Revenue per IT MW
Slide 11: Bitdeer.AI: Cloud Computing
Bitdeer.AI®: Cloud Computing Cloud Service Provider Signed a strategic 10-year lease for a 21.7 IT MW facility in Johor Bahru, Malaysia (Q1 2027 handover) designed for 128 NVIDIA GB300 NVL72 systems Datacenter & GPU Deployment Contract Duration(1) : 0.5 – 5 Years ARR grew over 77%, to $76M (from $43
Slide 12: Mining
Mining Year over Year Hash Rate Growth of over 342% Significant increase in mined BTC, Continued deployment of SEALMINER A4 benefiting from higher hash rate from expected to drive overall fleet efficiency, energization of SEALMINERs improving cost of BTC (1) (3) Hash rate (EH / S) Fleet Efficiency(J
Slide 13: SEALMINER Technology Roadmap
SEALMINER Technology Roadmap J/T SEAL04 SEALMINER A4 Series The A4 Ultra delivers a power efficiency of 9.45 J/T Mass-production began in Q1 2026 A1 Seal02 Seal01 A3 Seal04 A2 Seal03 A4 SEAL03 SEALMINER A3 Series The A3 Pro series delivers a power efficiency of 12.5 J/T Mass-production start in Q4 2
Slide 14: Key Investment Highlights
Key Investment Highlights 3.0GW total power portfolio, representing one of the largest ~3.0 GW Global power pipelines among publicly listed compute Power Portfolio infrastructure companies. Executed $4.7B, 16 Year Base-term lease with Volta in Tydal, AI Colocation Norway in August. Bitdeer.AI at a $
Slide 15: Financial Performance
Financial Performance NASDAQ: BTDR 15
Slide 16: Q2 2026 Financial Snapshot
Q2 2026 Financial Snapshot Financial REVENUE 228.8 Total revenue of $228.8 million Cost of revenue of $237.3 million 155.6 Gross loss of $8.5 million Net loss of $92.3 million Adjusted EBITDA(1) of $31.1 million Cash, cash equivalents and restricted cash of $496.3 million Q2'25 Q2'26 Digital assets
Slide 17: Appendix
Appendix &> BITDEER NASDAQ: BTDR
Slide 18: Income Statement
Income Statement Three months ended Jun 30 Three months ended Jun 30 (US $ in thousands) (US $ in thousands) 2026 2025 2026 2025 Revenue 228,784 155,582 Net loss (92,278) (62,937) Cost of revenue (237,310) (143,601) Other comprehensive loss Gross profit (loss) (8,526) 11,981 - Foreign currency trans
Slide 19: Balance Sheets
Balance Sheets (US $ in thousands) Jun 30, 2026 Dec 31, 2025 (US $ in thousands) Jun 30, 2026 Dec 31, 2025 ASSETS LIABILITIES Current assets Current liabilities Accounts payable 177,263 119,818 Cash and cash equivalents 456,838 149,352 Accrued expenses and other current liabilities 54,180 54,964 Res
Slide 20: Adjusted EBITDA Reconciliation
Adjusted EBITDA Reconciliation Use of Non-GAAP Financial Measures Three months ended Jun 30 (US $ in thousands) 2026 2025 In evaluating the Company’s business, the Company considers and uses non-GAAP measures, adjusted EBITDA, as supplemental measures to review Adjusted EBITDA and assess its operati
Slide 21: NASDAQ:
NASDAQ: BTDR