BP plc · LSE:BP.

BP — Corporate Update (May 2004)

16 slides from BP's corporate update, May 6, 2004

  1. Slide 1: North West Hutton Stakeholder Meeting

    North West Hutton Stakeholder Meeting 6th May 2004

  2. Slide 2: North West Hutton

    North West Hutton Faroe I s l a n d s NW Hutton Topsides Shetland Islands Orkney Islands Bergen Oslo Stavanger • 130,000 barrels per day oil Aberdeen North Sea capacity production • 2 Drilling rigs - 40 well slots Jacket • Power generation, gas compression, water • 18,000 tonnes - water injection sy

  3. Slide 3: Well abandonment complete

    Well abandonment complete Well abandonment completed last year Biggest ever well abandonment programme in the North Sea Reservoir 3,500 metres below seabed 25 live wells plugged and abandoned – some extending over 6,000 metres Three cement plugs for each well Excellent safety performance – no injuri

  4. Slide 4: They think it's all over…..

    They think it’s all over….. 4

  5. Slide 5: Topsides preparation activity

    Topsides preparation activity 5

  6. Slide 6: Topsides removal

    Drilling Derrick’s & Sub-structures - Pedestal Cranes | mm Accommodation Block Mud & Drilling Utilities Modules Exhaust Towers for Sales —— Gas Compressor Turbines Flare Boom —+< Production Module Intake Ducts Production Module Power Generation Module Utilities Module Exhaust Towers for Main Generat

  7. Slide 7: Pipelines

    SHEL CORMORANT ALPHA 20" Oil Export (PL 148) (untronched) NW HUTTON Grice 10% Gas Import (P1147) fed/&/natural backfill) (Cup, NinianTee

  8. Slide 8: Comparative assessment

    Comparative assessment Framework for the Assessment: • Fully understand the facility and the surrounding environment • Understand and incorporate previous work and learning • Comprehensive and transparent process • Stakeholder Dialogue and Independent Review Legislative Framework Comparative Assessm

  9. Slide 9: Pipelines

    Pipelines EXISTING OIL LINE CUT AND LIFT TRENCH REVERSE S-LAY TRENCH & BURY 9

  10. Slide 10: Jacket decommissioning

    Jacket decommissioning Full removal Cut at “seabed” level Recover to footings 10

  11. Slide 11: Drill Cuttings Pile

    Drill Cuttings Pile COVER RECOVERY DRILL CUTTINGS CONTOUR MAP 11

  12. Slide 12: Study Process and Principles

    Study Process and Principles Safety Safety Environmental Societal Societal Technical Economic Economic - Qualitative - HAZID - Quantitative - Qualitative - Qualitative - Quantitative - Quantitative – QRA and Qualitative and Quantitative - Recognised & - Deterministic based - Potential loss of life -

  13. Slide 13: Oil Pipeline: Comparative Assessment

    Oil Pipeline: Comparative Assessment Oil Line Leave in situ Bury Recover Safety Probability of Loss of Life PLL 0.21% 0.28% 2.1% Environment Waste Generated Tonnes Negligible Negligible 7,600 (figures are GHG CO2 E Tonnes 8,000 11,000 14,000 for both oil Total Energy requirement GJ 110,000 150,000 1

  14. Slide 14: Gas Pipeline: Comparative Assessment

    Gas Pipeline: Comparative Assessment Gas Line Leave in situ Bury Recover Safety Probability of Loss of Life PLL 0.20% 0.20% 1.90% Environment Waste Generated Tonnes Negligible Negligible 7,600 (figures are GHG CO2 E Tonnes 8,000 11,000 14,000 for both oil Total Energy requirement GJ 110,000 150,000

  15. Slide 15: Footings: Comparative Assessment

    Footings : Comparative Assessment Jacket and Jacket and Footings Footings Partial Jacket Removal to - Removal Removal 100m Safety Probability of Loss of Life 14% 13% 5% Probability of Accident (LTI) 16 6 Environment GHG CO2 E Tonnes 45,000 44,000 40,000 Total Energy requirement GJ 520,000 575,000 56

  16. Slide 16: Drill Cuttings Comparative Assessment

    Drill Cuttings Comparative Assessment Leave in situ & Re-inject on Re-inject Monitor Cover Excavate site offsite Onshore treatment Safety Probability of Loss of Life 0.20% 0.6% 0.50% 6.4% 6.4% 2.2% Probability of Accident (LTI) <1 <1 <1 7 7 3 Environment Total Energy 6,500 75,000 35,000 275,000 300,

BP — Corporate Update (May 2004) on 6ix