  1. Slide 1: Lake Erie Works Community Liaison Committee Meeting

    Lake Erie Works Community Liaison Committee Meeting 26 January 2017 K. Chan

  2. Slide 2: Agenda

    Agenda 1. Welcome and Safety Contact 2. Review and Approval of Agenda 3. Review and Approval of Minutes of 6 October 2016 4. Performance under O.Reg. 419/05 Site Specific Standard Order - Particulates 5. Lake Erie Works Winter Dust Management – Overview 6. The New Stelco 7. Community Concerns 8. Adj

  3. Slide 3: Know Your Emergency Exits

    Know Your Emergency Exits Review Evacuation Routes of the room you are located in

  4. Slide 4: Agenda

    Agenda 1. Welcome and Safety Contact 2. Review and Approval of Agenda 3. Review and Approval of Minutes of 6 October 2016 4. Performance under O.Reg. 419/05 Site Specific Standard Order - Particulates 5. Lake Erie Works Winter Dust Management – Overview 6. The New Stelco 7. Community Concerns 8. Adj

  5. Slide 5: Agenda

    Agenda 1. Welcome and Safety Contact 2. Review and Approval of Agenda 3. Review and Approval of Minutes of 6 October 2016 4. Performance under O.Reg. 419/05 Site Specific Standard Order - Particulates 5. Lake Erie Works Winter Dust Management – Overview 6. The New Stelco 7. Community Concerns 8. Adj

  6. Slide 6: Agenda

    Agenda 1. Welcome and Safety Contact 2. Review and Approval of Agenda 3. Review and Approval of Minutes of 6 October 2016 4. Performance under O.Reg. 419/05 Site Specific Standard Order - Particulates 5. Lake Erie Works Winter Dust Management – Overview 6. The New Stelco 7. Community Concerns 8. Adj

  7. Slide 7: Site-Specific Standard Order (Particulates): Performance Review – Daily

    Site-Specific Standard Order (Particulates): Performance Review – Daily Date Doors Lids Off-takes (% Leaks) (% Leaks) (% Leaks) 2015 Limits 54% 2% NA (July 2 start) 2016 Limits 32% 2% NA 2017-2019 Limits 10% 2% 5% 2020 Limits 5% 1% 4% Oct - Dec 2016 0 – 11.6% 0 – 0.7% 0 – 8.8% Range (3.88%) (0.06%)

  8. Slide 8: Site-Specific Standard Order (Particulates): Performance Review – 30 Day Rolling Averages

    Site-Specific Standard Order (Particulates): Performance Review – 30 Day Rolling Averages Date Doors Lids Off-takes Charging (% Leaks) (% Leaks) (% Leaks) (sec) (log avg) 2015 Limits 38% 0.8% 25% 12 sec (July 2 start) 2016 Limits 22.5% 0.8% 15% 12 s 2017-2019 Limits 7% 0.8% 4.2% 12 s 2020 Limits 4%

  9. Slide 9: Performance Review – Daily Observations – Pushing Emissions

    Site-Specific Standard Order (Particulates): Performance Review – Daily Observations – Pushing Emissions Date Pushing Emission (opacity %) 2015 Limit (July 2 start) ≥ 50% 2016 – 2018 ≥ 50% 2019 ≥ 40% 2020 ≥ 30% Oct – Dec 2016 Range 0 – 41.67% (Average) (7.26%) Oct – Dec 2016 Operational Adjustments

  10. Slide 10: Performance Review – Additional Items

    Site-Specific Standard Order (Particulates): Performance Review – Additional Items • There were no community complaints for the period of October – December 2016 • MOECC to provide verbal comments

  11. Slide 11: Agenda

    Agenda 1. Welcome and Safety Contact 2. Review and Approval of Agenda 3. Review and Approval of Minutes of 6 October 2016 4. Performance under O.Reg. 419/05 Site Specific Standard Order - Particulates 5. Lake Erie Works Winter Dust Management – Overview 6. The New Stelco 7. Community Concerns 8. Adj

  12. Slide 12: Lake Erie Works Winter Dust Management

    Lake Erie Works Winter Dust Management D. Palmer Iron Producing Area Manager

  13. Slide 13: Overview

    Overview • Well-established fugitive dust management plan already in place • A “living” document – best management practices for continual improvement • Integrated in Standard Operating Procedures • Dust mitigation practices are customized by season to address different external environmental condit

  14. Slide 14: Raw Material Handling - Dock

    Raw Material Handling - Dock • The Process Coordinator – Raw Materials & Dock oversees dust management of stockpiles at all times of the year • Stockpiles generally arranged to minimize surface area that can be affected by prevailing winds • 9 stock piles reduced to 3 stock piles • Sufficient quanti

  15. Slide 15: Tools For Proactive Approach

    Tools For Proactive Approach • Timely communication with all crews • Detailed current weather and future wind forecasts • USE DUST SUPPRESSION TOOLS PROACTIVELY!

  16. Slide 16: Tools For Proactive Approach

    Tools For Proactive Approach

  17. Slide 17: Tools For High Wind Warning Notification

    Tools For High Wind Warning Notification • Automated email alerts when measured wind at a weather station exceeds an alert setpoint (currently 21kph) • Emails are sent to iron producing management and all blast furnace Shift Managers (24 x 7) • System is integrated with the blast furnace control roo

  18. Slide 18: Coal Field Sprinkler System

    Coal Field Sprinkler System • Video: Drone video of sprinkler system in operation • Future Upgrades: • Additional sprays for increased coverage area • Increased pump size for additional water pressure and flow

  19. Slide 19: In-Plant Roads

    In-Plant Roads • Similar to stock piles management, dust control on plant roadways vary based on seasonal conditions • Internal visual inspection of roadways and related areas are conducted daily • Dust from unpaved and paved roads are managed on a daily, or as- required, basis • Dust management pra

  20. Slide 20: Thank You.

    Thank You. stelcocanada.com

  21. Slide 21: Agenda

    Agenda 1. Welcome and Safety Contact 2. Review and Approval of Agenda 3. Review and Approval of Minutes of 6 October 2016 4. Performance under O.Reg. 419/05 Site Specific Standard Order - Particulates 5. Lake Erie Works Winter Dust Management – Overview 6. The New Stelco 7. Community Concerns 8. Adj

  22. Slide 22: The New Stelco

    | STELCO | we The Steel Company of Canada The New Stelco

  23. Slide 23: The New Stelco

    The New Stelco On December 2, 2016, our company launched our new brand under the Stelco name. This is the next step towards our goal of becoming an independent Canadian business.

  24. Slide 24: The New Stelco

    The New Stelco The new logo marks the return of the iconic dogbone that was first introduced in 1928. The modernization of the design and the inclusion of the maple leaf signals our company’s forward thinking approach and distinguishes us as uniquely Canadian.

  25. Slide 25: Recruiting

    Recruiting It was also announced that Stelco will be recruiting several new employees as we repatriate many jobs that were previously performed by our parent company. These positions will further support our independence and are across several areas including operations, accounting, sales, procureme

  26. Slide 26: Next Steps

    Next Steps As we work towards finalizing a restructuring solution that will allow our business to remain financially sustainable and compete, we will continue to operate under the Stelco name. Our path forwards includes more modern and robust communication with the community through a new website an

  27. Slide 27: Text Slide

    ith Wii) 1 Uy, = = SS S Lh Ml Seen yigeiriiy

  28. Slide 28: Thank You.

    Thank You. stelcocanada.com

  29. Slide 29: Agenda

    Agenda 1. Welcome and Safety Contact 2. Review and Approval of Agenda 3. Review and Approval of Minutes of 6 October 2016 4. Performance under O.Reg. 419/05 Site Specific Standard Order - Particulates 5. Lake Erie Works Winter Dust Management – Overview 6. The New Stelco 7. Community Concerns 8. Adj

  30. Slide 30: Agenda

    Agenda 1. Welcome and Safety Contact 2. Review and Approval of Agenda 3. Review and Approval of Minutes of 6 October 2016 4. Performance under O.Reg. 419/05 Site Specific Standard Order - Particulates 5. Lake Erie Works Winter Dust Management – Overview 6. The New Stelco 7. Community Concerns 8. Adj

  31. Slide 31: Thank You.

    Thank You. stelcocanada.com