Slide 1: Lake Erie Works Community Liaison Committee Meeting
Lake Erie Works Community Liaison Committee Meeting 26 January 2017 K. Chan
Slide 2: Agenda
Agenda 1. Welcome and Safety Contact 2. Review and Approval of Agenda 3. Review and Approval of Minutes of 6 October 2016 4. Performance under O.Reg. 419/05 Site Specific Standard Order - Particulates 5. Lake Erie Works Winter Dust Management – Overview 6. The New Stelco 7. Community Concerns 8. Adj
Slide 3: Know Your Emergency Exits
Know Your Emergency Exits Review Evacuation Routes of the room you are located in
Slide 4: Agenda
Agenda 1. Welcome and Safety Contact 2. Review and Approval of Agenda 3. Review and Approval of Minutes of 6 October 2016 4. Performance under O.Reg. 419/05 Site Specific Standard Order - Particulates 5. Lake Erie Works Winter Dust Management – Overview 6. The New Stelco 7. Community Concerns 8. Adj
Slide 5: Agenda
Agenda 1. Welcome and Safety Contact 2. Review and Approval of Agenda 3. Review and Approval of Minutes of 6 October 2016 4. Performance under O.Reg. 419/05 Site Specific Standard Order - Particulates 5. Lake Erie Works Winter Dust Management – Overview 6. The New Stelco 7. Community Concerns 8. Adj
Slide 6: Agenda
Agenda 1. Welcome and Safety Contact 2. Review and Approval of Agenda 3. Review and Approval of Minutes of 6 October 2016 4. Performance under O.Reg. 419/05 Site Specific Standard Order - Particulates 5. Lake Erie Works Winter Dust Management – Overview 6. The New Stelco 7. Community Concerns 8. Adj
Slide 7: Site-Specific Standard Order (Particulates): Performance Review – Daily
Site-Specific Standard Order (Particulates): Performance Review – Daily Date Doors Lids Off-takes (% Leaks) (% Leaks) (% Leaks) 2015 Limits 54% 2% NA (July 2 start) 2016 Limits 32% 2% NA 2017-2019 Limits 10% 2% 5% 2020 Limits 5% 1% 4% Oct - Dec 2016 0 – 11.6% 0 – 0.7% 0 – 8.8% Range (3.88%) (0.06%)
Slide 8: Site-Specific Standard Order (Particulates): Performance Review – 30 Day Rolling Averages
Site-Specific Standard Order (Particulates): Performance Review – 30 Day Rolling Averages Date Doors Lids Off-takes Charging (% Leaks) (% Leaks) (% Leaks) (sec) (log avg) 2015 Limits 38% 0.8% 25% 12 sec (July 2 start) 2016 Limits 22.5% 0.8% 15% 12 s 2017-2019 Limits 7% 0.8% 4.2% 12 s 2020 Limits 4%
Slide 9: Performance Review – Daily Observations – Pushing Emissions
Site-Specific Standard Order (Particulates): Performance Review – Daily Observations – Pushing Emissions Date Pushing Emission (opacity %) 2015 Limit (July 2 start) ≥ 50% 2016 – 2018 ≥ 50% 2019 ≥ 40% 2020 ≥ 30% Oct – Dec 2016 Range 0 – 41.67% (Average) (7.26%) Oct – Dec 2016 Operational Adjustments
Slide 10: Performance Review – Additional Items
Site-Specific Standard Order (Particulates): Performance Review – Additional Items • There were no community complaints for the period of October – December 2016 • MOECC to provide verbal comments
Slide 11: Agenda
Agenda 1. Welcome and Safety Contact 2. Review and Approval of Agenda 3. Review and Approval of Minutes of 6 October 2016 4. Performance under O.Reg. 419/05 Site Specific Standard Order - Particulates 5. Lake Erie Works Winter Dust Management – Overview 6. The New Stelco 7. Community Concerns 8. Adj
Slide 12: Lake Erie Works Winter Dust Management
Lake Erie Works Winter Dust Management D. Palmer Iron Producing Area Manager
Slide 13: Overview
Overview • Well-established fugitive dust management plan already in place • A “living” document – best management practices for continual improvement • Integrated in Standard Operating Procedures • Dust mitigation practices are customized by season to address different external environmental condit
Slide 14: Raw Material Handling - Dock
Raw Material Handling - Dock • The Process Coordinator – Raw Materials & Dock oversees dust management of stockpiles at all times of the year • Stockpiles generally arranged to minimize surface area that can be affected by prevailing winds • 9 stock piles reduced to 3 stock piles • Sufficient quanti
Slide 15: Tools For Proactive Approach
Tools For Proactive Approach • Timely communication with all crews • Detailed current weather and future wind forecasts • USE DUST SUPPRESSION TOOLS PROACTIVELY!
Slide 16: Tools For Proactive Approach
Tools For Proactive Approach
Slide 17: Tools For High Wind Warning Notification
Tools For High Wind Warning Notification • Automated email alerts when measured wind at a weather station exceeds an alert setpoint (currently 21kph) • Emails are sent to iron producing management and all blast furnace Shift Managers (24 x 7) • System is integrated with the blast furnace control roo
Slide 18: Coal Field Sprinkler System
Coal Field Sprinkler System • Video: Drone video of sprinkler system in operation • Future Upgrades: • Additional sprays for increased coverage area • Increased pump size for additional water pressure and flow
Slide 19: In-Plant Roads
In-Plant Roads • Similar to stock piles management, dust control on plant roadways vary based on seasonal conditions • Internal visual inspection of roadways and related areas are conducted daily • Dust from unpaved and paved roads are managed on a daily, or as- required, basis • Dust management pra
Slide 20: Thank You.
Thank You. stelcocanada.com
Slide 21: Agenda
Agenda 1. Welcome and Safety Contact 2. Review and Approval of Agenda 3. Review and Approval of Minutes of 6 October 2016 4. Performance under O.Reg. 419/05 Site Specific Standard Order - Particulates 5. Lake Erie Works Winter Dust Management – Overview 6. The New Stelco 7. Community Concerns 8. Adj
Slide 22: The New Stelco
| STELCO | we The Steel Company of Canada The New Stelco
Slide 23: The New Stelco
The New Stelco On December 2, 2016, our company launched our new brand under the Stelco name. This is the next step towards our goal of becoming an independent Canadian business.
Slide 24: The New Stelco
The New Stelco The new logo marks the return of the iconic dogbone that was first introduced in 1928. The modernization of the design and the inclusion of the maple leaf signals our company’s forward thinking approach and distinguishes us as uniquely Canadian.
Slide 25: Recruiting
Recruiting It was also announced that Stelco will be recruiting several new employees as we repatriate many jobs that were previously performed by our parent company. These positions will further support our independence and are across several areas including operations, accounting, sales, procureme
Slide 26: Next Steps
Next Steps As we work towards finalizing a restructuring solution that will allow our business to remain financially sustainable and compete, we will continue to operate under the Stelco name. Our path forwards includes more modern and robust communication with the community through a new website an
Slide 27: Text Slide
ith Wii) 1 Uy, = = SS S Lh Ml Seen yigeiriiy
Slide 28: Thank You.
Thank You. stelcocanada.com
Slide 29: Agenda
Agenda 1. Welcome and Safety Contact 2. Review and Approval of Agenda 3. Review and Approval of Minutes of 6 October 2016 4. Performance under O.Reg. 419/05 Site Specific Standard Order - Particulates 5. Lake Erie Works Winter Dust Management – Overview 6. The New Stelco 7. Community Concerns 8. Adj
Slide 30: Agenda
Agenda 1. Welcome and Safety Contact 2. Review and Approval of Agenda 3. Review and Approval of Minutes of 6 October 2016 4. Performance under O.Reg. 419/05 Site Specific Standard Order - Particulates 5. Lake Erie Works Winter Dust Management – Overview 6. The New Stelco 7. Community Concerns 8. Adj
Slide 31: Thank You.