Slide 1: Boral Teven Quarry Community Consultative Committee meeting
Build something great™ ® Boral Teven Quarry Community Consultative Committee meeting 15 October 2015
Slide 2: Agenda
Build something great™ ® Agenda Boral Teven Quarry Community Consultative Committee Meeting 15 October 2015 Welcome and introductions 2015 Whole-of-Community meeting and matters arising 16 July 2015 Quarry operations update Special presentation: dust emissions and management Environmenta
Slide 3: Boral personnel in attendance
Build something great™ ® Boral personnel in attendance Boral Teven Quarry Community Consultative Committee Meeting 15 October 2015 Matt Duff Assistant Quarry Manager, Boral Teven Quarry Dr Richard Strauch Group Environmental Advisor, Boral HSE Rod Wallace Planning & Development Manager (NSW),
Slide 4: Whole-of-Community meeting & matters arising
Build something great™ ® Whole-of-Community meeting & matters arising Boral Teven Quarry Community Consultative Committee Meeting 15 October 2015 Confirmation of the minutes from the 2015 Whole-of-Community meeting 16 July 2015 NOTE: Presentations and meeting notes from previous meetings are a
Slide 5: Quarry operations update
Build something great™ ® Boral Teven Quarry Quarry operations update Matt Duff, Assistant Quarry Manager – Boral Teven Quarry
Slide 6: Operations overview
® Build something great™ Operations overview Boral Teven Quarry Community Consultative Committee Meeting 15 October 2015 Current projects Highway upgrade – Pimlico to Teven Local projects Internal supply to Boral Concrete plants • Highway Tintenbar to Ewingsdale • Smith Street storage sheds
Slide 7: Site Improvements Program
® Build something great™ Site Improvements Program Boral Teven Quarry Community Consultative Committee Meeting 15 October 2015 Before cladding After cladding
Slide 8: Site Improvements Program
® Build something great™ Site Improvements Program Boral Teven Quarry Community Consultative Committee Meeting 15 October 2015 Building 2 (Looking South) Buildings 1, 2 and 3 (Looking East)
Slide 9: Site Improvements Program
® Build something great™ Site Improvements Program Boral Teven Quarry Community Consultative Committee Meeting 15 October 2015 Improvement Projects - Continuing weed management activities - Planting of native seedlings on small earth bund above ROM pad - Development and planting of earth bund near
Slide 10: Site Improvements Program
® Build something great™ Site Improvements Program Boral Teven Quarry Community Consultative Committee Meeting 15 October 2015 Argillite resource access and Argillite high wall stabilization and visual improvements in the long term
Slide 11: Special presentation: dust emissions and management
Build something great™ ® Boral Teven Quarry Special presentation: dust emissions and management Dr Richard Strauch, Group Environmental Advisor, Boral HSE
Slide 12: Dust, fine particles (PM10) & health
® Build something great™ Dust, fine particles (PM10) & health Boral Teven Quarry Community Consultative Committee Meeting 15 October 2015 Concentrations of fine particles (PM10 & PM2.5) in ambient air, mainly due to vehicle pollution particularly in urban areas, can be associated with a range of r
Slide 13: Monitoring & understanding results
® Build something great™ Monitoring & understanding results Boral Teven Quarry Community Consultative Committee Meeting 15 October 2015 PM10 monitors measure all PM10, whether or not it is from the nearby quarry. Average background levels are usually much higher than a quarry’s contribution. Ove
Slide 14: Some of Boral's monitoring experiences
® Build something great™ Some of Boral’s monitoring experiences Boral Teven Quarry Community Consultative Committee Meeting 15 October 2015 Deer Park VIC Linwood SA Orange Grove Teven NSW WA Montrose VIC
Slide 15: Controls
® Build something great™ Controls Boral Teven Quarry Community Consultative Committee Meeting 15 October 2015 If unreasonable contribution against background is detected, an operation can and should act to reduce that contribution The focus should be on roads & traffic, followed by main processi
Slide 16: Environmental management & monitoring
Build something great™ ® Boral Teven Quarry Environmental management & monitoring Nathan Jeffery, HSE Advisor (Northern NSW)
Slide 17: Site environmental management
® Build something great™ Site environmental management Boral Teven Quarry Community Consultative Committee Meeting 15 October 2015 Weed control and rehabilitation Since whole-of-community meeting in July 2015: - 126 man hours on weed control Contractors are scheduled to do 48 hours of on-site wo
Slide 18: Monitoring – Deposited Dust
Build something great™ ® Monitoring – Deposited Dust Boral Teven Quarry Community Consultation Committee Meeting 15 October 2015 Averaging Period g/m2/montha Deposited Dustb Annual 4.00 a – Maximum total deposited dust level b – Dust is assessed as insoluble solids as defined by AS3580.10.1-1991 (AM
Slide 19: Monitoring – Dust Deposition
Build something great™ ® Monitoring – Dust Deposition Boral Teven Quarry Community Consultative Committee Meeting 15 October 2015
Slide 20: Monitoring – Water
Build something great™ ® Monitoring – Water Boral Teven Quarry Community Consultative Committee Meeting 15 October 2015
Slide 21: Monitoring – Blast results
Build something great™ ® Monitoring – Blast results Boral Teven Quarry Community Consultative Committee Meeting 15 October 2015 Boral Teven Quarry Blast Limits; • Only 1 blast per day • Only blast between 9am to 4pm Monday to Friday • Vibration limits •5mm/s 95% •10mm/s 100% • Overpressure Limits •
Slide 22: Complaints Summary
Build something great™ ® Complaints Summary Boral Teven Quarry Community Consultative Committee Meeting 15 October 2015 There have been two incidents reported to the quarry since the meeting in July 2015 - 24/8/2015 – Residential Neighbour (S of Quarry) - Concern: Noise coming from a water pump wh
Slide 23: Annual report
Build something great™ ® Annual report Boral Teven Quarry Community Consultative Committee Meeting 15 October 2015 Annual Report Condition 4 of the Consent states an Annual Report to be prepared and provided to the CCC Reporting period for 2015 Annual Report is from 1/7/2014 to 30/6/2015 Conta
Slide 24: Re-examination of quarry consent
Build something great™ ® Boral Teven Quarry Re-examination of quarry consent Rod Wallace, Planning & Development Manager (NSW)
Slide 25: Re-examination of consent termination date
® Build something great™ Re-examination of consent termination date Boral Teven Quarry Community Consultative Committee Meeting 15 October 2015 Condition 24 of the 1996 development consent states: These conditions shall be re-examined by Council and a final date for the termination of the consen
Slide 26: Proposed consent re-examination and modification
® Build something great™ Proposed consent re-examination and modification Boral Teven Quarry Community Consultative Committee Meeting 15 October 2015 At our meetings with locals during July, we raised our proposal to cease production on Saturdays in exchange for the use of mobile crushing plant (i
Slide 27: Initial results
® Build something great™ Initial results Boral Teven Quarry Community Consultative Committee Meeting 15 October 2015 Air quality - Initial modelling has been conducted against Approved Methods for Modelling and Assessment of Air Pollutants in New South Wales (DEC, 2005) - Modelling has predicted t
Slide 28: Community activities and general business
Build something great™ ® Boral Teven Quarry Community activities and general business Paul Jackson, Stakeholder Relations Manager (Southern Region)
Slide 29: General business
® Build something great™ General business Boral Teven Quarry Community Consultative Committee Meeting 15 October 2015 Items of general business Next meeting of the Community Consultative Committee Mar 2016 (usually meet Mar and Sep) Other meetings may be called as part of consent re-examinat
Slide 30: Thank you for your attendance