    Nordex SE Conference Call H1 2017 Hamburg, 3 August 2017

  2. Slide 2: Disclaimer

    Slide 2: Disclaimer

    Disclaimer All financial figures within this presentation are unaudited. This presentation was produced in August 2017 by Nordex SE solely for use as a source of general information regarding the economic circumstances and status of Nordex SE. It does not constitute an offer for the sale of securiti

  3. Slide 3: Agenda

    Slide 3: Agenda

    Agenda 1 Introduction José Luis Blanco 2 Markets, orders & installations José Luis Blanco 3 Financials Christoph Burkhard 4 “30-by-18” Christoph Burkhard 5 Product development José Luis Blanco 6 Outlook José Luis Blanco 7 Q&A All Board members Conference Call H1 2017 3 August 2017 3

  4. Slide 4: Nordex is on track to meet the 2017 guidance

    Slide 4: Nordex is on track to meet the 2017 guidance

    Introduction Nordex is on track to meet the 2017 guidance H1 2017 Order intake* of EUR 905m, thereof EUR 572m in second quarter Revenues of EUR 1.5bn, thereof EUR 853m in second quarter EBITDA margin of 7.8% Increasing service business supports group results * excl. Service Conference Call H1 2017 3

  5. Slide 5: Priorities clearly set and key actions well under way

    Slide 5: Priorities clearly set and key actions well under way

    Introduction Priorities clearly set and key actions well under way Priorities and key actions presented in Q1 Status of key actions Q2 Key actions progressing according to plan 3 Divisions gone live Progressing according to plan Savings identified, implementation ongoing Ramp up India ongoing Share

  6. Slide 6: Short term uncertainty as markets transition towards auction systems

    Slide 6: Short term uncertainty as markets transition towards auction systems

    Markets, orders & installations Short term uncertainty as markets transition towards auction systems Europe America Rest of World General trend in European US market demand driven Transition to auction markets transitioning by current PTC cycle based systems creates towards auction based shifting to

  7. Slide 7: Q2 order intake of EUR 572m

    Slide 7: Q2 order intake of EUR 572m

    Markets, orders & installations Q2 order intake of EUR 572m Order intake* (in EUR m) Order intake by regions (in %) Europe -32% North America 43% 1,330 Latin America 68% RoW 905 22% 15% 31% 6% 10% 4% H1 2016 H1 2017 H1 2016 H1 2017 *excl. Service Back-end loaded order intake expected for Distributio

  8. Slide 8: Solid growth of service segment

    Slide 8: Solid growth of service segment

    Markets, orders & installations Solid growth of service segment Service sales (in EUR m) Comments Service share increased to around 11% +24% of total sales at the end of H1 2017 150.4 Service sales supported by inorganic 121.2 growth (AWP included from Q2 2016 on) H1 2016* H1 2017 *Adjusted after ch

  9. Slide 9: Turbine and service order backlog stands at EUR 3.6bn

    Slide 9: Turbine and service order backlog stands at EUR 3.6bn

    Markets, orders & installations Turbine and service order backlog stands at EUR 3.6bn Order backlog turbines (EUR m) Order backlog service (EUR m) +63% -15% 2,047 1,864 1,742 1,142* H1 2016 H1 2017 H1 2016 H1 2017 Turbine order backlog shows in correlation Service order backlog increased in Q2 with

  10. Slide 10: Operational performance

    Slide 10: Operational performance

    Markets, orders & installations Operational performance Installations (MW) Production Turbine assembly (MW) Output of 535 -3% +18% units: GER 320, 1,165 1,129 ESP 199, BRA 15, 1,536 IND 1 1,298 Preparing for higher installations H1 2016 H1 2017 Blade production (#) H1 2016 H1 2017 Output: 210 GER, +

  11. Slide 11: Income statement H1 2017

    Slide 11: Income statement H1 2017

    Financials Income statement H1 2017 Comments in EUR m H1 2017 H1 2016 Δ in % Sales in line with Sales 1,501.1 1,483.9 1.2 expectations Total revenues 1,525.7 1,503.0 1.5 Cost of materials -1,111.5 -1,129.8 -1.6 Increased gross profit margin due to favourable Gross profit 414.2 373.2 11.0 project mix

  12. Slide 12: Balance sheet H1 2017

    Slide 12: Balance sheet H1 2017

    Financials Balance sheet H1 2017 Comments in EUR m 30.06.17 31.12.16 abs. Δ in % change Due to increased activity inventories remaining on a Non-current assets 1,273.7 1,275.1 -1.4 -0.1 high level Current assets 1,599.1 1,719.1 -120.0 -7.0 Decrease in current Total assets 2,872.8 2,994.2 -121.4 -4.1

  13. Slide 13: Working capital H1 2017

    Slide 13: Working capital H1 2017

    Financials Working capital H1 2017 Working capital development (in EUR m) Working capital ratio (in % of sales*) 9.8 FY guidance 121 5% - 7% 8.4 213 335 6.8 4.4 4.1 147 100 4 YE Receiva- Inven- Prepay- Pay- Q2 Q2 Q3 Q4 Q1 Q2 2016 bles tories ments ables 2017 2016 2016 2016 2017 2017 Increased workin

  14. Slide 14: Cash flow statement H1 2017

    Slide 14: Cash flow statement H1 2017

    Financials Cash flow statement H1 2017 Comments in EUR m H1 2017 H1 2016 As in Q1 2017 free cash flow impacted by Cash flow from +28.7 +41.8 operating activities high working capital before net working capital Working capital improvement programme Cash flow from -188.7 -145.5 launched in Q2 2017 cha

  15. Slide 15: Total investments H1 2017

    Slide 15: Total investments H1 2017

    Financials Total investments H1 2017 CAPEX (in EUR m) Comments Investments in property, plant, equipment +89% mainly driven by: 70.1* • Heavy investments in new products and supply chain for new product generation with substantial COE reduction 47.1 37.1* • Activity increase on AW platform 21.9 • In

  16. Slide 16: Capital structure H1 2017

    Slide 16: Capital structure H1 2017

    Financials Capital structure H1 2017 Net debt* to EBITDA** (xEBITDA) Equity ratio (in %) 0.9 0.9 1.0 0.8 34 0.6 33.3 33.0 0.5 33 0.0 31.5 32.1 0.0 32 31.4 -0.5 0 Q2 Q3 Q4 Q1 Q2 Q2 Q3 Q4 Q1 Q2 2016 2016 2016 2017 2017 2016 2016 2016 2017 2017 Fairly stable leverage ratio over the past Solid equity ra

  17. Slide 17: "30-by-18" cost reduction programme to support long-term profitability

    Slide 17: "30-by-18" cost reduction programme to support long-term profitability

    „30-by-18" “30-by-18” cost reduction programme to support long-term profitability Programme is progressing well Scope Progress  Target: EUR 30m reduction in Identified potential reaching structural costs target of EUR 30m Focus area: Corporate functions 80% of identified OPEX potential and Division

  18. Slide 18: Product development in land-constrained markets (Delta platform)

    Slide 18: Product development in land-constrained markets (Delta platform)

    Product development Product development in land-constrained markets (Delta platform) 1. Step: Power Shift 2. Step: Wind Class & Power Shift Next Product Move Ø Wind Speed Entering the >140m rotor segment for low-wind sites N131/3600 N131/3900 +300kW power Light Wind Tip heights Tip heights from 150-

  19. Slide 19: Product development in grid-constrained markets (AW platform)

    Slide 19: Product development in grid-constrained markets (AW platform)

    Product development Product development in grid-constrained markets (AW platform) Ø Wind Speed Next Product Move AW132/3000 Enhancing competitiveness in the light-wind segment Steel and concrete Light Wind towers from 84-137.5m AW132/3300 AW125/3000 AW125/3150 Targeting quick time to market Power up

  20. Slide 20: Guidance 2017 confirmed

    Slide 20: Guidance 2017 confirmed

    Outlook Guidance 2017 confirmed 2017e Sales EUR3.1 - 3.3 bn 3.1-3.3bn EBITDA margin 7.8–8.2%* W/C ratio 5.0–7.0% CAPEX approx. EUR 150m *Excluding costs related to “30-by-18” programme Guidance 2018 published in Q1 2018 Conference Call H1 2017 3 August 2017 20

  21. Slide 21: Time for your questions

    Slide 21: Time for your questions

    Q&A Time for your questions Conference Call H1 2017 3 August 2017 21

  22. Slide 22: The management team

    Slide 22: The management team

    The management team José Luis Blanco Christoph Burkhard Patxi Landa CEO CFO CSO CEO Acciona CFO Siemens Wind Business Windpower Power Offshore Development Various Senior Various other Director and Management & positions at Siemens Executive Chief Officer BHF Bank, EBRD Committee member positions at

  23. Slide 23: Financial calendar 2017

    Slide 23: Financial calendar 2017

    Financial calendar 2017 Date Event 1 March Publication of Preliminary Results 2016 and Outlook 2017 (Frankfurt) 30 March Publication of Annual Report 2016 11 May Interim statement Q1 2017 30 May Annual General Meeting (Rostock) 3 August Interim report H1 2017 14 November Interim statement Q3 2017 Co

  24. Slide 24: Together on the same course

    Slide 24: Together on the same course

    Together on the same course Contact Investor Relations: Felix Zander Tobias Vossberg Rolf Becker Nordex SE Langenhorner Chaussee 600 22419 Hamburg Germany Tel: +49-40-30030-1000 Fax: +49-40-30030-1333 Email: info@nordex-online.com Web: www.nordex-online.com