Veolia Environnement Sa · EURONEXT:VIE

Veolia Environnement Sa — Veolia — Corporate Update (February 2025)

34 slides from Veolia Environnement Sa's corporate update, Feb 20, 2025

  1. Slide 1: Woodlawn Eco-Precinct Community Liaison Committee Meeting

    WOODLAWN ECO-PRECINCT COMMUNITY LIAISON COMMITTEE MEETING

  2. Slide 2: Acknowledgement of Country

    ACKNOWLEDGEMENT OF COUNTRY Veolia acknowledges Ngunnawal people as the traditional custodians of the lands and waters in which we live and work and their continuing connection to land, water and community. We pay respects to their Elders past, present and emerging and any first nations people presen

  3. Slide 3: Meeting Agenda

    MEETING AGENDA ITEM TOPIC 1 Introduction and welcome 2 Apologies 3 Actions from previous meeting 4 Commercial agreement disclosure 5 Eco-Precinct Operational Update 1. EPA Clean up notice 6 ARC presentation 7 Environmental Compliance update 8 CLC meeting administration 1. Acceptance of new members 2

  4. Slide 4: Introduction and Welcome

    INTRODUCTION AND WELCOME

  5. Slide 5: Meeting Attendance/Apologies

    MEETING ATTENDANCE/APOLOGIES DATE Thursday 20th February 2025 Time 5:00pm to 7.00pm LOCATION Woodlawn Conference Room 619 Collector Road, Tarago NAME PRESENT NAME PRESENT Justin Houghton (JH) (Veolia) Skye Mcparland (SM) (Veolia - online) CR Keith Smith (KS) (GMC Councillor) No representative (TSA R

  6. Slide 6: Actions from Last Meeting

    ACTIONS FROM LAST MEETING

  7. Slide 7: Meeting Actions

    MEETING ACTIONS ITEM ACTION ASSIGNED TO 1 ACTION: GH to investigate and nominate community Q&A interface options - existing website form GH (Veolia) will be used, drop down list will be built in, and Veolia must ensure questions are answered. GH to organise this and trial it before next meeting. - I

  8. Slide 8: Meeting Actions - Cont'd

    MEETING ACTIONS - Cont’ ITEM ACTION ASSIGNED TO 6 ACTION: Veolia to consider request for a copy of the email sent from Veolia to the NSW EPA GH (Veolia) representatives, declining their request to attend the last CLC meeting. COMPLETE (Veolia see no reason for this, we simply informed the regulator

  9. Slide 9: Eco-Precinct Positive Outcomes Since Last Meeting

    ECO-PRECINCT Positive outcomes since last meeting WINS! • COMMUNITY - Supporting this years Tarago show, painting, skip bins and providing the bus to transport people to the show from town. • WATER MANAGEMENT - All dams continue to reduce further below freeboard. • REGULATORS - New Queanbeyan EPA te

  10. Slide 10: EPA Presentation

    EPA Presentation

  11. Slide 11: NSW EPA Representatives

    EPA NSW EPA representatives: • EPA odour complaint handling • Interface with Veolia re compliance matters • Transfer of responsibilities to the Queanbeyan office • Questions

  12. Slide 12: Eco-Precinct Operational Update

    Traffic Lights Attention required ECO-PRECINCT Area of focus OPERATIONAL UPDATE Going well

  13. Slide 13: Operational Update Performance

    OPERATIONAL UPDATE PERFORMANCE Bioreactor Landfill - Licence tonnage YTD Waste Processed (licence 7 Sep 2024 - 16 February 2025) ● Regional Waste 52,461 t - (licence 125,000t) ● Sydney Waste 322 145 t - (licence 900,000t) ○ Both are within licence limits for Sep 2024 - Sep 25 period Mechanical Biolo

  14. Slide 14: Water Management

    WATER Storage status and location (End of Jan 2024) MANAGEMENT Coffer Dam #2 ED1 Plant Collection Dam Coffer Dam #3 Coffer Dam #1 Office area Leachate Treatment Plant ED3N 1-4 Plant collection catchment ED3S ED3SS Western Ridge catchment Bioreactor Void catchment

  15. Slide 15: Water Management Freeboard Management

    WATER MANAGEMENT FREEBOARD MANAGEMENT * Note: 1 L/s = 86,400 L/day @ 20% evaporation = 17,280 L/day

  16. Slide 16: Water Management Treated Leachate Strategy Summary

    WATER MANAGEMENT TREATED LEACHATE STRATEGY SUMMARY Short term next 18 months ● Temporary tank farm - 48 ML - 4 installed and 3 approved for use ● Integrity testing Cofferdam 1 - March 2025 ● Permanent tank farm 1 - 48ML - Approval application submitted - July 2025 ● Permanent tank farm 2 - up to 96M

  17. Slide 17: Operational Update Bio-Energy

    ECO-PRECINCT OPERATIONAL UPDATE BIO-ENERGY Bioenergy 2024 Biogas Capture ● Gas collected in last 12 months (01/24-12/24) 44,029,023 m3 - (50% methane) ● Energy Generation 57,391 MWh in last 12 months ● In last 12 months, the captured emission is equivalent to removing 82,225 cars off the road throug

  18. Slide 18: Operational Update Odour Management

    ECO-PRECINCT OPERATIONAL UPDATE ODOUR MANAGEMENT Completed ● Waste and rock interface gas collection in the bioreactor along the void perimeter (1000 m of horizontal gas collection) in operation (green lines) since August 2024. In the process of planning replicated system on the new lift. ● Monthly

  19. Slide 19: Operational Update Odour Complaints

    ECO-PRECINCT OPERATIONAL UPDATE ODOUR COMPLAINTS ● Odour complaints and events have decreased compared to the same time last year. ● Odour movement is heavily dependant on weather conditions. Storms in February adding to odour events ● Colder weather conditions show an increase in odour complaints o

  20. Slide 20: ARC Project Update

    ARC PROJECT UPDATE

  21. Slide 21: What's Next

    What’s next January February March April May June July Feb - March: Lodgement of Submissions Report, Amendment Report and Tech Studies March onwards : [TBC] Exhibition for the Amendment Report (if required) May - July: Responding to submissions related to the Amendment Report Late 2025 onwards : IPC

  22. Slide 22: Upcoming Engagement Activities

    Upcoming Engagement Activities 1 4 Community Newsletters Door Knocking & Neighbour Briefings • February 2025 with direct neighbours 2 Shopping Centre Pop Ups • Goulburn Square: TBC March 2025 5 Webinars • TBC (Bungendore): TBC March 2025 • Date TBC • Riverside Plaza (Queanbeyan): TBC March 2025 3 6

  23. Slide 23: Environmental Compliance Update

    ENVIRONMENTAL COMPLIANCE UPDATE

  24. Slide 24: Operational Update EPA Clean Up Notice

    OPERATIONAL UPDATE EPA CLEAN UP NOTICE EPA Clean Up Notice EPA issued Woodlawn a Clean Up Notice freeboard exceedance ○ The clean up notice leachate in regards to tankering has completed ○ The temporary tanks are all built, with the 4th tank CQA being undertaken now EPA issued Woodlawn a Clean Up No

  25. Slide 25: Independent Odour Audit Updates

    INDEPENDENT ODOUR AUDIT UPDATES ACTION STATUS COMPLETION DATE ● Odour mitigation from the void Veolia have engaged a landfill engineer to undertake a review of Engaged Tonkin to undertake the landfill operating practices. ● Active tipping face Site visit 15 May This review will address odour mitigat

  26. Slide 26: PA Modifications & Post Approval Applications

    ENVIRONMENTAL COMPLIANCE UPDATE PA MODIFICATIONS & POST APPROVAL APPLICATIONS APPROVAL TYPE DESCRIPTION STATUS MP 10_0012 Modification Modify the existing project approval for the Bioreactor and MBT to: Revised submission ongoing • Originally to construct an approximately 100 ML dam at the Bioreacto

  27. Slide 27: CLC Meeting Administration

    CLC MEETING ADMINISTRATION

  28. Slide 28: CLC Meeting Administration

    CLC MEETING ADMINISTRATION • New members to be approved • Renomination of members after 2 years please renominate today • Tarago Womens shed - Veolia Trust has been working with the Women’s shed and the show society for an outcome here.

  29. Slide 29: Community Q&A

    COMMUNITY Q&A

  30. Slide 30: CLC Questions

    CLC QUESTIONS ● Are there any questions for Veolia from the CLC ● Review emailed questions if any and have time

  31. Slide 31: CLC New Actions

    CLC NEW ACTIONS ACTION STATUS COMPLETION DATE ● INSERT TEXT Insert text Insert tex

  32. Slide 32: Next Meeting

    NEXT MEETING The next Community Liaison Meeting will be held at the Woodlawn Eco-Precinct Office - TBC agreed.

  33. Slide 33: Vision for Woodlawn

    VISION FOR WOODLAWN appendix 1

  34. Slide 34: Vision for Woodlawn

    ECO-PRECINCT 20 YEAR VISION FOR WOODLAWN We will shortly be releasing a community flyer to show what we’ve achieved in the past 20 years of Woodlawn and to highlight our key areas of focus for the next 20 years. These areas of future focus include: • Operational improvements: We’ll continue to devel