  1. Slide 1: Greater Stella Area Development Update

    Greater Stella Area Development Update September 2013

  2. Slide 2: Disclaimer

    Disclaimer This proprietary presentation (including any accompanying oral presentation, question and answer session and any other document or materials distributed at or in connection with this presentation) (collectively, the “Presentation”) has been prepared by Ithaca Energy Inc. (“Ithaca” or the

  3. Slide 3: Stella A1 well results materially de-risk overall development

    Stella “A1” well… results materially de-risk overall development   High quality Stella Andrew reservoir  1312ft of net pay (53%) in 2499ft horizontal reservoir section  Reservoir properties in line with previous wells on field #4   Strong well test rates – production de-risking #3  10.8kboe/d

  4. Slide 4: Building a highly profitable 25kboe/d North Sea oil and gas company

    Building a highly profitable 25kboe/d North Sea oil and gas company Material GSA  Forecast net Stella production ~16kboe/d (30kboe/d, 100%) initial annualised rate De-risking – A1 well flow test result de-risks the forecast Achieved  Significant increase in cashflow from operations upon Stella sta

  5. Slide 5: Building the Greater Stella Area production hub

    54.67% Working Building the Greater Stella Area production hub Interest PHASE 1 INFRASTRUCTURE  Monetising >30MMboe net 2P reserves* – delivering forecast net initial annualised production of ~16kboe/d  High value development solution  Operated infrastructure – flexibility to optimise production

  6. Slide 6: Development drilling campaign

    Development drilling campaign  Development drilling campaign commenced mid June 2013 using ENSCO 100 jack-up rig  (Transocean subsidiary) - manage drilling and completion operations under ‘turnkey’ contract arrangements  Four initial Stella wells to be drilled for start-up of production  Three h

  7. Slide 7: Start-up well programme

    Start-up well programme  Drilling programme characteristics  Oil rim wells prioritised – maximising initial liquids production  Horizontal wells to maximise deliverability  Stella field production and reservoir #4 #3 management  Natural depletion drive – gas cap expansion / aquifer support  Ga

  8. Slide 8: Subsea infrastructure fabrication

    Subsea infrastructure fabrication  - integrated Engineering, Procurement, Installation and Construction (EPIC) contract covers subsea works   Subsea structures fabricated in UK  Manifolds for production and export of hydrocarbons to / from the FPF-1   10-inch export pipelines fabricated in Ger

  9. Slide 9: Subsea infrastructure installation status

    Subsea infrastructure installation status  Main subsea installation works completed…  Infield subsea structures  60km gas export pipeline – installed and trenched  Infield flowline trenching completed  Excellent weather conditions to date - most weather sensitive activities completed  Less tha

  10. Slide 10: Subsea infrastructure forward programme

    Subsea infrastructure forward programme  Remaining 2013 offshore works  Completion of on-going gas export pipeline backfill operations and as laid survey  Skandi Arctic - installation of flexible infield flowlines and static umbilicals  Orelia diving support vessel - tie-in of gas export pipelin

  11. Slide 11: FPF-1 modification yard works on-going

    FPF-1 modification yard works on-going  - Petrofac completing FPF-1 modification works under a lump-sum contract  GSA field interest underpins performance incentives  Vessel in Remontowa shipyard in Gdansk (Poland), ~10 days towing time from field  Key modification work programme activities  R

  12. Slide 12: FPF-1 dry dock works

    FPF-1 dry dock works  FPF-1 on dry dock barge for completion of marine system / hull life extension workscopes  Hull tank refurbishment operations nearing completion - inspection, repair and coating  Construction of additional buoyancy blocks nearing completion – sponsons and blisters  Buoyancy

  13. Slide 13: FPF-1 processing facilities installation programme

    FPF-1 processing facilities installation programme  Processing facilities workscopes commenced  Fabrication of pre-assembled units / racks – contain pipework spools, cable trays and equipment  Units to be lifted on to vessel for tie-in  Key long lead items flowing to yard  Gas export compressor

  14. Slide 14: Development execution de-risking

    Development execution de-risking  Drilling campaign  High-spec jack-up rig  Turnkey drilling contract  Well clean-up flow tests – production assurance  Horizontal wells to maximise deliverability  Subsea infrastructure  Integrated EPIC contract – fixing majority of pricing  Technip - renowne

  15. Slide 15: Delivering upon long term Greater Stella Area strategic plan

    Delivering upon long term Greater Stella Area strategic plan 2013 Offshore operations and FPF-1 dry dock works commenced 2012 Stella / Harrier Field Development Plan approval Greater Stella Area strategy finalised – development concept selected, 2011 Petrofac introduced as strategic partner, acreage