Ithaca Energy PLC · LSE:ITH
Ithaca Energy — Corporate Update (September 2013)
15 slides from Ithaca Energy's corporate update, September 2013
Slide 1: Greater Stella Area Development Update
Greater Stella Area Development Update September 2013
Slide 2: Disclaimer
Disclaimer This proprietary presentation (including any accompanying oral presentation, question and answer session and any other document or materials distributed at or in connection with this presentation) (collectively, the “Presentation”) has been prepared by Ithaca Energy Inc. (“Ithaca” or the
Slide 3: Stella A1 well results materially de-risk overall development
Stella “A1” well… results materially de-risk overall development High quality Stella Andrew reservoir 1312ft of net pay (53%) in 2499ft horizontal reservoir section Reservoir properties in line with previous wells on field #4 Strong well test rates – production de-risking #3 10.8kboe/d
Slide 4: Building a highly profitable 25kboe/d North Sea oil and gas company
Building a highly profitable 25kboe/d North Sea oil and gas company Material GSA Forecast net Stella production ~16kboe/d (30kboe/d, 100%) initial annualised rate De-risking – A1 well flow test result de-risks the forecast Achieved Significant increase in cashflow from operations upon Stella sta
Slide 5: Building the Greater Stella Area production hub
54.67% Working Building the Greater Stella Area production hub Interest PHASE 1 INFRASTRUCTURE Monetising >30MMboe net 2P reserves* – delivering forecast net initial annualised production of ~16kboe/d High value development solution Operated infrastructure – flexibility to optimise production
Slide 6: Development drilling campaign
Development drilling campaign Development drilling campaign commenced mid June 2013 using ENSCO 100 jack-up rig (Transocean subsidiary) - manage drilling and completion operations under ‘turnkey’ contract arrangements Four initial Stella wells to be drilled for start-up of production Three h
Slide 7: Start-up well programme
Start-up well programme Drilling programme characteristics Oil rim wells prioritised – maximising initial liquids production Horizontal wells to maximise deliverability Stella field production and reservoir #4 #3 management Natural depletion drive – gas cap expansion / aquifer support Ga
Slide 8: Subsea infrastructure fabrication
Subsea infrastructure fabrication - integrated Engineering, Procurement, Installation and Construction (EPIC) contract covers subsea works Subsea structures fabricated in UK Manifolds for production and export of hydrocarbons to / from the FPF-1 10-inch export pipelines fabricated in Ger
Slide 9: Subsea infrastructure installation status
Subsea infrastructure installation status Main subsea installation works completed… Infield subsea structures 60km gas export pipeline – installed and trenched Infield flowline trenching completed Excellent weather conditions to date - most weather sensitive activities completed Less tha
Slide 10: Subsea infrastructure forward programme
Subsea infrastructure forward programme Remaining 2013 offshore works Completion of on-going gas export pipeline backfill operations and as laid survey Skandi Arctic - installation of flexible infield flowlines and static umbilicals Orelia diving support vessel - tie-in of gas export pipelin
Slide 11: FPF-1 modification yard works on-going
FPF-1 modification yard works on-going - Petrofac completing FPF-1 modification works under a lump-sum contract GSA field interest underpins performance incentives Vessel in Remontowa shipyard in Gdansk (Poland), ~10 days towing time from field Key modification work programme activities R
Slide 12: FPF-1 dry dock works
FPF-1 dry dock works FPF-1 on dry dock barge for completion of marine system / hull life extension workscopes Hull tank refurbishment operations nearing completion - inspection, repair and coating Construction of additional buoyancy blocks nearing completion – sponsons and blisters Buoyancy
Slide 13: FPF-1 processing facilities installation programme
FPF-1 processing facilities installation programme Processing facilities workscopes commenced Fabrication of pre-assembled units / racks – contain pipework spools, cable trays and equipment Units to be lifted on to vessel for tie-in Key long lead items flowing to yard Gas export compressor
Slide 14: Development execution de-risking
Development execution de-risking Drilling campaign High-spec jack-up rig Turnkey drilling contract Well clean-up flow tests – production assurance Horizontal wells to maximise deliverability Subsea infrastructure Integrated EPIC contract – fixing majority of pricing Technip - renowne
Slide 15: Delivering upon long term Greater Stella Area strategic plan
Delivering upon long term Greater Stella Area strategic plan 2013 Offshore operations and FPF-1 dry dock works commenced 2012 Stella / Harrier Field Development Plan approval Greater Stella Area strategy finalised – development concept selected, 2011 Petrofac introduced as strategic partner, acreage