Boral Ltd.

Boral — Corporate Update (December 2020)

38 slides from Boral's corporate update, December 2020

  1. Slide 1: Boral Peppertree Quarry

    Build something great™ BORAL PEPPERTREE QUARRY December 2020 > Community Consultative Committee (CCC) Peppertree Quarry 1 meeting Marulan

  2. Slide 2: Agenda

    Agenda ˃ 1. Welcome and introductions ˃ 2. Confirmation of minutes and actions ˃ 3. Business arising ˃ 4. Correspondence ˃ 5. Operations over the last 3 months ˃ 6. Environmental performance ˃ a. Incidents ˃ b. Complaints ˃ c. Air ˃ d. Noise ˃ e. Blast ˃ f. Water – surface and ground ˃ g. Heritage ˃

  3. Slide 3: Welcome, Apologies, Minutes and Business Arising

    Agenda item 1 – Welcome & Apologies Agenda item 2 – Confirmation of Minutes Agenda item 3 – Business Arising 3

  4. Slide 4: Agenda item 4 - Correspondence

    Agenda item 4 - Correspondence ˃ Department of Planning and Environment ˃ Management plan updates and reviews ˃ Site inspection by Compliance officer ˃ Road transport approval letter for overburden to Meridian park in Marulan ˃ EPA ˃ nil ˃ Resource Regulator ˃ Audit on Fire and Explosion associated

  5. Slide 5: Operations

    Build something great™ BORAL PEPPERTREE QUARRY 5 > Operations

  6. Slide 6: Operations over the last 3 months

    ˃ Agenda item 5 - Operations over the last 3 months ˃ Safety ˃ aim for zero LTI ˃ focus on vehicles and prestart checks as well as mental health ˃ Overburden ˃ planning works continuing ˃ Pit Update ˃ extension of fixed conveyors ˃ orientation change for extraction - currently south east, moving to

  7. Slide 7: Operations over the last 3 months

    ˃ Agenda item 5 - Operations over the last 3 months 7

  8. Slide 8: Environmental Performance

    Build something great™ BORAL PEPPERTREE QUARRY 8 > Environmental Performance

  9. Slide 9: Incidents September, October, November

    Agenda item 6 Environmental Performance a. Incidents September, October November ˃ September - nil ˃ October (nil) ˃ November - nil 9

  10. Slide 10: Complaints September, October, November

    Agenda item 6 Environmental Performance b. Complaints September, October November ˃ September (nil) October (nil) November (3 – noise ) 10

  11. Slide 11: Air

    Agenda item 6 Environmental Performance c. Air Annual Average goal of 4gm2/month In compliance Annual average below goal at the boundary 11

  12. Slide 12: Air

    Agenda item 6 Environmental Performance c. Air Annual Average goal of 4gm2/month In compliance Annual average below goal at the boundary 12

  13. Slide 13: Air

    Agenda item 6 Environmental Performance c. Air Annual Average goal of 4gm2/month In compliance Annual average below goal at the boundary 13

  14. Slide 14: Air

    Agenda item 6 Environmental Performance c. Air Annual Average goal of 30ug/m3 until the 27th July now 25ug/m3 In compliance until change in level. Annual average below goal at the boundary 14

  15. Slide 15: Air

    Agenda item 6 Environmental Performance c. Air 24 hour goal of 50ugm3 In compliance Annual average below goal at the boundary 15

  16. Slide 16: Air

    Agenda item 6 Environmental Performance c. Air Annual Average goal of 90ug/m3 In compliance Annual average below goal at the boundary 16

  17. Slide 17: Noise – quarterly monitoring – July

    Agenda item 6 Environmental Performance d. Noise – quarterly monitoring – July Receptor ID Description Date Assessment Period Criteria Quarry Noise R17 Myers 28-Jul-20 Day 40 31 R2 Bartolo 28-Jul-20 Day 40 24 R3 Cooper 28-Jul-20 Day 40 37 R8 Pace 28-Jul-20 Day 40 33 R4 McClean 28-Jul-20 Day 40 34 R1

  18. Slide 18: Noise – quarterly monitoring – July

    Agenda item 6 Environmental Performance d. Noise – quarterly monitoring - July Assessment Receptor ID Description Date Period Criteria Quarry Noise R17 Myers 28-Jul-20 Night 35 27 R17 Myers 28-Jul-20 Night 35 28 R17 Myers 29-Jul-20 Evening 35 25 R17 Myers 29-Jul-20 Evening 35 25 R17 Myers 29-Jul-20

  19. Slide 19: Noise – quarterly monitoring – July

    Agenda item 6 Environmental Performance d. Noise – quarterly monitoring - July Compliance Assessment Site (L1, 1 minute in dBA) ID Description Date Start Time Audible (Y/N) Criteria Quarry Noise R17 Myers 28-Jul-20 06:30 Y 52 39 R17 Myers 28-Jul-20 06:45 Y 52 36 R17 Myers 29-Jul-20 22:00 Y 52 32 R17

  20. Slide 20: Blasts

    Agenda item 6 Environmental Performance e. Blasts ˃ In compliance 20

  21. Slide 21: Blast

    Agenda item 6 Environmental Performance e. Blast ˃ In Compliance 21

  22. Slide 22: Water - surface

    Agenda item 6 Environmental Performance f. Water - surface Quarterly monitoring round undertaken in October 2020. Next sample round quarter of January – March 2020 No issues with water supply or quality over the last 3 months 22

  23. Slide 23: Water - surface

    Agenda item 6 Environmental Performance f. Water - surface ˃ Below guideline for October samples 23

  24. Slide 24: Water - surface

    Agenda item 6 Environmental Performance f. Water - surface ˃ Below guideline for October samples, with the exception of Marulan south creek 24

  25. Slide 25: Water - surface

    Agenda item 6 Environmental Performance f. Water - surface ˃ Below guideline for October samples 25

  26. Slide 26: Water - surface

    Agenda item 6 Environmental Performance f. Water - surface ˃ Below guideline for October samples with the exception of Marulan south creek & U1 26

  27. Slide 27: Water - surface

    Agenda item 6 Environmental Performance f. Water - surface ˃ Below guideline for October samples - U1 and dam above criteria 27

  28. Slide 28: Water – environmental flow

    Agenda item 6 Environmental Performance f. Water – environmental flow year total in flow 10% total out flow in compliance Jan-2020 0 0 0.93 yes Feb-2020 125 12.5 597 yes Mar-2020 2 0.2 36.55 yes Apr-2020 2.6 0.26 2.37 yes May-2020 5.7 0.57 2.88 yes Jun-2020 2.2 0.2 2.65 yes Jul-2020 12.2 1.22 3.57 y

  29. Slide 29: Groundwater

    Agenda item 6 Environmental Performance f. Groundwater ˃ Monitoring conducted in October 2020. report is still pending ˃ Review of the existing wells was undertaken. ˃ Assessment has been made of the existing trigger levels for management ˃ ˃ Assessment has been made as to the need for additional we

  30. Slide 30: Heritage

    Agenda item 6 Environmental Performance g. Heritage ˃ Collation of Artefacts is continuing ˃ Launch of the “Innovate” Reconciliation Action Plan as part of NAIDOC week 30

  31. Slide 31: Ecology

    Agenda item 6 Environmental Performance h. Ecology ˃ No new plantings being undertaken due to weather conditions ˃ Hydro mulching has been undertaken on the eastern end of the Overburden ˃ Annual Rapid visual assessment carried out in November ˃ 2 year Ecological Assessment and monitoring also carri

  32. Slide 32: Stakeholder Engagement

    Build something great™ BORAL PEPPERTREE QUARRY 32 > Stakeholder Engagement

  33. Slide 33: Stakeholder Engagement

    Agenda item 6i – Stakeholder Engagement ˃ Marulan Christmas Fair being planned with support by Boral, Holcim and Gunlake ˃ Tallong Community Resilience day ˃ Assistance with Tallong Park sculptures 33

  34. Slide 34: Forward Plans

    Build something great™ BORAL PEPPERTREE QUARRY 34 > Forward Plans

  35. Slide 35: Operations next 3 months

    Agenda item 7 – Operations next 3 months 35

  36. Slide 36: General Business

    Build something great™ BORAL PEPPERTREE QUARRY 36 > General Business

  37. Slide 37: General Business

    Agenda item 8 – General Business ˃ Marulan South State Significant Development ˃ Still with DPIE for assessment ˃ Heads of Agreement arranged with Council on the upgrade of Marulan south road ˃ Other ˃ Next meeting March 2021 37

  38. Slide 38: Thank you for your attendance

    Build something great™ BORAL PEPPERTREE QUARRY 38 > Thank you for your attendance.