Slide 1: AGM Presentation - June 2014
AGM PRESENTATION - June 2014 This presentation should be read in conjunction with information provided on the Company’s website at www.metalsexploration.com
Slide 2: Important Notice
IMPORTANT NOTICE This presentation has been prepared by the management of Metals Exploration Plc for the benefit of the investing community including, brokers, fund managers, investors and analysts and not for the benefit of any particular person. It should be read in conjunction with information pr
Slide 3: Runruno Gold Project – Advanced Development
RUNRUNO GOLD PROJECT – ADVANCED DEVELOPMENT Philippine focussed mining development company 100% owned Runruno Gold Project - advanced development 75% complete Commissioning commence in Q2 2015 Robust funding model, 62% equity 38% debt Strong major shareholder support - Solomon Capital, Bak
Slide 4: Company Information
COMPANY INFORMATION SHARE CAPITAL (30 November 2014) KEY SHAREHOLDERS - % HOLDING (31 March 2013) Issued ordinary shares 1,374,972,024 Solomon & related parties 49.14% Unlisted options 7,275,000 Baker Steel 24.95% Market Capitalisation (20June 2014) £ 80, million Runruno Holdings 18.72%
Slide 5: Runruno Gold Project
RUNRUNO GOLD PROJECT Status: - in full development - 75% complete - within budget - commissioning forecast – Q2 2015 Initial Mine life: 10.3 years Payable Production: 1,006,000 ozs Annual Production (aver.): 96,700 ozs (101,800 ozs Au years 1-5, 92,700 ozs Au years 6-10.3) • Runruno Capital Cost: US
Slide 6: Debt Package
DEBT PACKAGE Experienced and well qualified banking syndicate HSBC and BNP Paribas Headline Facility $US 83 million $US 70 million construction facility $US 5 million capitalised interest during construction and costs $US 8 million over-run facility – available 55 month term – maturing 3
Slide 7: Construction Philosophy
CONSTRUCTION PHILOSOPHY Strong experienced owners team Self execute strategy using experienced consultants and sub contractors experienced in the Philippines Develop supporting infrastructure using discrete contracts and design and erect packages: Access road - completed Site establishment –
Slide 8: Operational and Construction Management
OPERATIONAL AND CONSTRUCTION MANAGEMENT Operational General Manager Mining – Peter Storey General Manager Maintenance – Kevin Oxenham Technical Services Superintendent – Michael James Mine Production / Training Superintendent – Colin Smith Senior Mine Geologist – Janice Azares-Wayan Ch
Slide 9: Resources and Reserves March 2011 & April 2013
RESOURCES AND RESERVES March 2011 & April 2013 Runruno Main Ore Gold Molybdenum Reserve Category Mt g/t M Oz ppm M lbs Proven 10.2 1.90 0.62 616 13.9 Probable 4.8 1.77 0.27 414 4.4 2P Reserves 15.0 1.85 0.90 603 18.3 Additional Inferred 2.9 1.73 0.16 258 1.7 Resource in-pit Ore Gold Molybdenum Resou
Slide 10: Regional Location
REGIONAL LOCATION Airfield – Bagabag airfield 10 kms north of Solano Road – upgraded – largely concrete. Power supply – switch yard in Bayombong will be the origin for the new 69Kv line to site, running along 5 km the new road • Runruno Project 10
Slide 11: Project Description
PROJECT DESCRIPTION Five key components: Mine Open Pit and Run of Mine (ROM) Pad Process Plant facility consisting of conventional crushing, grinding, flotation, along with BIOX® and gravity recovery Tailings Storage Facility (TSF): to ensure materials are properly managed and to reclaim water
Slide 12: Mining
MINING Open pit area - 600m x 1,500m 1.75 Mtpa ore - transported by conveyor to the Process Plant 9.1 Mtpa overburden - used for the construction of the Tailings Storage Facility and in-pit backfill During the first three years, waste material will be used in the construction of the Tailings
Slide 13: Gold Processing
GOLD PROCESSING Ore contains free and refractory gold Pressure Oxidation, & BIOX® processes tested and molybdenite BIOX® offers: Reduced capital intensity Lower operating costs Gold circuit demonstrated by extensive Proven process testwork including 20t pilot plant Ease of operation Gol
Slide 14: Corporate Social Responsibility
CORPORATE SOCIAL RESPONSIBILITY Education & Training Scholarships and assistance Adopt a school programme Out of work youth skills training programmes Teachers salaries Mature age learning programmes Multiple award winner Health & Nutrition Provision of a professionally staffed clinic inclu
Slide 15: Corporate Social Responsibility
CORPORATE SOCIAL RESPONSIBILITY Environment Protection and Enhancement Environmental monitoring Slope stabilisation and rehabilitation of disturbed areas Forest regeneration Multiple award winner Communication Information and Education To shape desirable social opinion about the compan
Slide 16: Extensively Awarded for Excellence in Environment, Social and Safety Programs
EXTENSIVELY AWARDED for EXCELLENCE IN ENVIRONMENT, SOCIAL and SAFETY PROGRAMS 16