Nordic Mining Asa · OSL:NOM

Nordic Mining Asa — Q3 2018 Earnings Presentation

38 slides from Nordic Mining Asa's earnings presentation, Nov 8, 2018

  1. Slide 1: Q3 2018 Presentation

    OAX: NOM Q3 2018 Presentation Oslo, 8 November 2018 Exploration and production of high-end minerals and metals Nordic Mining ASA | N-0250 Oslo | Norway | Tel +47 22 94 77 90 | Fax +47 22 94 77 01 | Org. no 989 796 739 | post@nordicmining.com 1

  2. Slide 2: Disclaimer

    Disclaimer This document has been used by Nordic Mining during an oral presentation. Therefore, this document is incomplete without the oral explanations, comments and supporting instruments that were submitted during the referred presentation. To the extent permitted by law, no representation or wa

  3. Slide 3: Introduction, Financial status, Update on projects

    1. Introduction 2. Financial status 3. Update on projects - Engebø, rutile and garnet - Keliber, lithium 4. Q&A

  4. Slide 4: Developing high-value assets in the Nordic Region

    Developing high-value assets in the Nordic Region Pd Pt Platinum, Palladium Ti Engebø Rutile and Garnet (100%) Si Li High Purity Quartz Keliber Oy Lithium (22%) 4

  5. Slide 5: Valuable markets for Nordic Mining's minerals

    Valuable markets for Nordic Mining’s minerals Rutile Global market: ~0.8 million tonnes Nordic Mining: ~33 thousand tonnes (~4%) ~850 USDm 2) Lithium ~0.36 million tonnes Nordic Mining*: ~11 thousand tonnes (~3%) Applications Garnet ~3 900 USDm 3) Pigment Titanium Welding rods ~1.4 million tonnes Ke

  6. Slide 6: Two valuable assets in pipeline towards construction

    Two valuable assets in pipeline towards construction 6

  7. Slide 7: Introduction, Financial status, Update on projects

    1. Introduction 2. Financial status 3. Update on projects - Engebø, rutile and garnet - Keliber, lithium 4. Q&A

  8. Slide 8: Consolidated Income Statements

    Consolidated Income Statements Q3-2018 Q3-2017 Acc. 2018 Acc. 2017 2017 Unaudited Unaudited Amounts in NOK million Unaudited Unaudited Audited - - Sales - - - (3.1) (1.8) Payroll and related costs (7.7) (8.1) (10.9) - - Depreciation and amortisation (0.1) (0.1) (0.2) (14.3) (6.7) Other operating exp

  9. Slide 9: Consolidated Statements of Financial Position

    Consolidated Statements of Financial Position 30.09.2018 31.12.2017 Amounts in NOK million Unaudited Audited ASSETS Evaluation and exploration assets 27.9 21.6 Property, plant and equipment 0.3 0.2 Investment in an associate 22.8 29.3 Total non-current assets 50.9 51.1 Cash 29.8 21.5 Other current a

  10. Slide 10: Rights Issue

    Rights Issue • On 1 November, an EGM of the Company resolved a rights issue as follows: • Proceeds up to NOK 40m (~17.4 million shares) • Subscription price of NOK 2.30 • Tradable subscription rights trading 6-16 November • Subscription period for shares 6-20 November • Approx. NOK 11m pre-committed

  11. Slide 11: Introduction, Financial status, Update on projects

    1. Introduction 2. Financial status 3. Update on projects - Engebø, rutile and garnet - Keliber, lithium 4. Q&A

  12. Slide 12: Engebø Rutile and Garnet

    Engebø Rutile and Garnet 13

  13. Slide 13: Engebø timeline towards construction

    Engebø timeline towards construction 2016 2017 2018 2019 2020 2021 2022 Timeline to production Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Resource classification #1 Resource classification #2 Prefeasibility study Definitive feasibility study Offtake agreement

  14. Slide 14: Definitive Feasibility Study – comprehensive test work

    Definitive Feasibility Study – comprehensive test work • Process test work; repeatability and variability tests and optimization studies are ongoing • Certain aspects of the mineralogy and texture of the Engebø deposit is complex. Therefore, the ongoing process test work is comprehensive • Additiona

  15. Slide 15: Mining schedules open pit

    Mining schedules open pit Mining Boundary

  16. Slide 16: Mining schedules open pit

    Mining schedules open pit Pushback 1 – Phase 1 Lowest Level of Mining: 197

  17. Slide 17: Mining schedules open pit

    Mining schedules open pit Pushback 1 – Phase 2 Lowest Level of Mining: 150

  18. Slide 18: Mining schedules open pit

    Mining schedules open pit Pushback 2 – Phase 1 Lowest Level of Mining: 225

  19. Slide 19: Mining schedules open pit

    Mining schedules open pit Pushback 2 – Phase 2 Lowest Level of Mining: 150

  20. Slide 20: Mining schedules open pit

    Mining schedules open pit Pushback 2 – Phase 3 Lowest Level of Mining: 105

  21. Slide 21: Mining schedules open pit

    Mining schedules open pit Pushback 2 – Phase 4 Lowest Level of Mining: 45

  22. Slide 22: Mining schedules open pit

    Mining schedules open pit Ultimate Pit Lowest Level of Mining: 45

  23. Slide 23: Underground facilities for crushing, ore storage and conveying

    Underground facilities for crushing, ore storage and conveying 24

  24. Slide 24: 25

    25

  25. Slide 25: fon

    er fon co-tterol NURSES

  26. Slide 26: Zoning plan for fresh water pipeline & powerline

    Zoning plan for fresh water pipeline & powerline 27

  27. Slide 27: Engineering, county road 611

    Engineering, county road 611 Kote 46 Kote 36 28

  28. Slide 28: Archeological investigations completed

    Archeological investigations completed All areas clarified for construction 29

  29. Slide 29: Infrastructure and operational readiness

    Infrastructure and operational readiness Activity Completion ---------------------------------------------------------------------------- • Detailed regulation of process and mining area May 2019 • Regulation of pipeline for water supply March 2019 • Review of infrastructure for power supply Dec 201

  30. Slide 30: Rutile is on an upward cycle

    Rutile is on an upward cycle Supply issues and increasing demand tighten the feedstock markets “…… means the already tight rutile market, plagued by supply disruptions, will tighten further this year. Illuka also said that demand for high-grade titanium ores remains very strong. Tight market conditi

  31. Slide 31: Introduction, Financial status, Update on projects

    1. Introduction 2. Financial status 3. Update on projects - Engebø, rutile and garnet - Keliber, lithium 4. Q&A

  32. Slide 32: Keliber – Lithium from Europe for future energy solutions

    Keliber – Lithium from Europe for future energy solutions

  33. Slide 33: Finland well positioned for battery production growth

    Finland well positioned for battery production growth Raw materials From mines to chemicals Strong political support • Keliber May 2018: The Finnish Li Norilsk Nickel worlds largest government announced Ni producer (30 % of production significant support for Ni refined in Finland) the Finnish batter

  34. Slide 34: Concentrator plant in Kalavesi

    Concentrator plant in Kalavesi Concentrator plant in Kalavesi Designed for ore throughput of 600 000 tpa (nominal value)

  35. Slide 35: Chemical plant in Kokkola Industrial Park

    Chemical plant in Kokkola Industrial Park Nameplate capacity of 11,000 tons Area reservation for possible expansions

  36. Slide 36: Keliber adopts to market changes in the battery manufacturing

    Keliber adopts to market changes in the battery manufacturing November 6th:

  37. Slide 37: Introduction, Financial status, Update on projects

    1. Introduction 2. Financial status 3. Update on projects - Engebø, rutile and garnet - Keliber, lithium 4. Q&A

  38. Slide 38: Safety – Environment - Innovation

    Safety – Environment - Innovation www.nordicmining.com 3 9

Nordic Mining — Q3 2018 Earnings Presentation on 6ix