Nbcc (india) Limited · NSE:NBCC
Nbcc (india) — Investor Presentation (November 2023)
96 slides from Nbcc (india)'s investor presentation, Nov 30, 2023
Slide 1: One-on-One Institutional Investor Meeting Presentation (exchange letter)
No NBCC/BS/BSENSE/2023-24 November 30, 2023 नेशनल स्टॉक एक्सचेंज ऑफ़ इं डिया डलडिटे ि बीएसई डलडिटे ि एक्सचेंज प्लाजा, डिरोज जीजीभोय टॉवर, प्लॉट नंबर सी/1, जी ब्लॉक, दलाल स्टर ीट, बांद्रा-कुलाा कॉम्प्प्लेक्स िुंबई -400001 बांद्रा (ई) िुंबई 400051 एनएसई प्रतीक: एनबीसीसी/EQ स्क्रिप कोि: 534309 National
Slide 2: Investors & Analyst Presentation 2023
Annexure-I 30th Nov 2023 NBCC (INDIA) LIMITED INVESTORS & ANALYST PRESENTATION 2023
Slide 3: NBCC Journey So Far
NBCC JOURNEY SO FAR… 1960 1977 1988 2012 2014 2017 2018 2019 2021 2022-23 CONSOLIDATED REVENUE – CROSSED : RECORD SALE OF REAL INCORPORATION DIVERSIFIED INTO NAVRATNA 10,000 + CRORE ESTATE IN WORLD REAL ESTATE STATUS & TRADE CENTER, NSL INCORPORATION NAUROJI NAGAR HSCC HSCL ACQUISTION FOOTPRINTS IN
Slide 4: Company Snapshot
COMPANY SNAPSHOT ONE OF THE LARGEST CONSTRUCTION CPSE IN INDIA DEBT FREE, CASH SURPLUS & NEGATIVE WORKING CAPITAL PAN INDIA & GLOBAL PRESENCE INTEGRATED OPERATIONS - PMC, EPC, REAL ESTATE UNIQUE BUSINESS MODEL - SELF REVENUE GENERATION LISTED COMPANY IN BOTH THE EXCHANGES STRONG GROWTH & REVENUE VIS
Slide 5: NBCC's Business Composition
NBCC’s BUSINESS COMPOSITION Institutional, Housing & Industrial Buildings SEGMENTAL REVENUE FY 2022-23 Redevelopment work of Govt. Colonies & Properties, Land Monetization PMC EPC RE PMC Roads, Hospitals, Medical 6% 2% Colleges, Offices, Airports, Bridges Stressed Real Estate & Overseas Work NBCC Ci
Slide 6: PMC Business Model - Concept to Commissioning
PMC BUSINESS MODEL - CONCEPT TO COMMISSIONING Project Management Consultancy (PMC) Services: CONCEPT TO COMMISSIONING. • Institutional, Housing & Industrial Buildings • Re-development of Govt. Colonies & Govt. Properties, Land Monetization • Stressed Real Estate Projects NBCC • Educational & office
Slide 7: NBCC Consolidated Financial Performance
NBCC CONSOLIDATED FINANCIAL PERFORMANCE FINANCIAL YEAR TOTAL INCOME (Cr) PBT- Gross Profit (Cr) 2020-21 7134 287 2021-22 7885 388 2022-23 8962 542
Slide 8: Subsidiaries & JVs
SUBSIDIARIES & JV’s NBCC SERVICES LIMITED HSCC (INDIA) LTD . WHOLLY OWNED SUBSIDIARY NBCC DWC- LLC (DUBAI) NBCC (INDIA) LTD SUBSIDIARY OTHER SUBSIDIARY HINDUSTAN STEELWORKS CONSTURCTION LIMITED : 51% REAL ESTATE DEVELOPMENT & JOINT VENTURE CONSTRUCTION CORPORATION OF RAJASTHAN LIMITED : 50%
Slide 9: NBCC's Subsidiaries
NBCC's SUBSIDIARIES NSL NBCC SERVICES LIMITED • Specialized in Developing • Specialized in Steel Plants & Specialized in Hospitals & Medical Colleges infrastructure projects. • Post Construction Works • NBCC acquired 100% stakes in • NBCC acquired 51% stakes in • Maintenance Works HSCC from Ministry
Slide 10: Order Book Status & Business Secured in 2023-24
ORDER BOOK STATUS & BUSINESS SECURED IN 2023-24 Standalone Order Book Summary Major Works Secured in FY 2023-24: as on 01.11.2023 (Cr) Development and Monetisation of major land Standalone Total 44,700 (approx.) parcel of Kerala state Housing Board (KSHB) Order Book – Rs. 2000 Cr Government Pres
Slide 11: Manpower Details
MANPOWER DETAILS NBCC EMPLOYEE STRENGTH Engineers 726 Finance/HRM/etc. 270 C&D Level Employees 336 Total Strength 1332 10
Slide 12: List of Major Clients
LIST OF MAJOR CLIENTS OVERSEAS AUTONOMO CENTRAL STATE CPSEs/PSU CLIENT US BODIES GOVT. GOVT. Republic of IIMS MOHUA BHEL Haryana Mauritius IITs MHA NTPC North Republic of NITS MOD SJVN Eastern Maldives CBI MEA CCL States Republic of NIA MoE AAI West Seychell
Slide 13: Major Executed Projects: Domestic
MAJOR EXECUTED PROJECTS: DOMESTIC DOMESTIC MAJOR EXECUTED PROJECTS : DOMESTIC MAJOR EXECUTED PROJECTS : • Bharat Mandapam, New Delhi • Dr. Ambedkar International Centre For • Vanijya Bhawan Building Social Justice. • Kaushal bhawan Building • Pt. Deendayal Upadhaya Archaeology • Garvi Gujarat Sadan,
Slide 14: Major On-Going Projects: Domestic
MAJOR ON-GOING PROJECTS: DOMESTIC • DOMESTIC MAJOR ON-GOING PROJECTs • NIT Patna, Bihar Campus • Redevelopment of Nauroji Nagar, Sarojini • National Sports University at Manipur Nagar And Netaji Nagar in Delhi • IIT Bhubaneswar Campus • Amrapali Projects • Border Fencing & Road Works • Bharat Vandan
Slide 15: Major Overseas On-Going & Executed Projects
MAJOR OVERSEAS ON-GOING & EXECUTED PROJECTS OVERSEAS MAJOR EXECUTED PROJECTS : OVERSEAS MAJOR PROJECT ON-GOING: • New Supreme Court Building, Mauritius • Construction of 2000 Social Housing • Social Housing Projects, Mauritius Units in Maldives • Mahatma Gandhi Convention Centre (MGCC) at Niger • In
Slide 16: NBCC Redevelopment Business Overview
NBCC REDEVELOPMENT BUSINESS OVERVIEW 15
Slide 17: Self Sustainable Business Model - Re-Development
SELF SUSTAINABLE BUSINESS MODEL - RE-DEVELOPMENT WHY TO RE-DEVELOP PROPERTIES ? WHAT IS RE-DEVELOPMENT MODEL ? • High Repair and Maintenance Cost require for dilapidated Buildings . • Demolishing prevailing old buildings. • Constructed in Post Independence era - Govt. • Construction of new site with
Slide 18: Self Sustainable Development - Financial Models
SELF SUSTAINABLE DEVELOPMENT - FINANCIAL MODELS Model 1 Outright sale of part of land Re-Development Model 2 Long term lease of part BUA Re Model 3 Freehold Sale of part BUA. UNIQUE SELLING PROPOSITION : NBCC has expertise in PMC+ REAL ESTATE + MAINTENANCE. • Dedicated in-house Real Estate team for
Slide 19: New Moti Bagh Project
NEW MOTI BAGH PROJECT • Pre- development Houses - 82 • Post development Value additions • Additional Houses Developed: 910 nos • Surplus Cash of 328 Crs. (Incl. Interest ) was handed over to Government. • 105 Acres Senior Govt. Officer complex (with villas & apartment). • Social Infra.: 1.57 Lakh sf
Slide 20: East Kidwai Nagar Project
EAST KIDWAI NAGAR PROJECT • Area - 86 acres land. • Project Cost - Rs 5200 Cr (approx.) • Fund Raised by Long term Lease Commercial /Residential Area • Plot Area is 86 Acres out of which 14 Acres is of Darya Khan Tomb, a protected monument. RESIDENTIAL BUILDINGS OFFICE SOCIAL INFRASTRUCTURE BASEMENT
Slide 21: Kidwai Nagar (East) Project
KIDWAI NAGAR (EAST) PROJECT 20
Slide 22: Kidwai Nagar (East) Office cum Commercial Project
KIDWAI NAGAR (EAST) OFFICE CUM COMMERCIAL PROJECT 21
Slide 23: Redevelopment of 7 GPRA Colonies
REDEVELOPMENT OF 7 GPRA COLONIES NBCC CPWD NAUROJI NAGAR KASTURBA NAGAR NETAJI NAGAR THYAGRAJ NAGAR SAROJINI NAGAR SRINIVASPURI MOHAMMADPUR
Slide 24: Background
BACKGROUND • To address the acute shortage of Government Housing and Office in the NCR, Union Cabinet has approved Re-development of Seven (GPRA). • The cost of project comprising of GPRA, Social infrastructure & Commercial space and maintenance of GPRA for 30 years is to be met by sale of Commercia
Slide 25: World Trade Center Nauroji Nagar
WORLD TRADE CENTER NAUROJI NAGAR 24
Slide 26: Progress Photographs (Nauroji Nagar)
Progress Photographs (Nauroji Nagar) 25
Slide 27: Progress Photographs (Nauroji Nagar)
Progress Photographs (Nauroji Nagar) 26
Slide 28: Handing Over to Buyers (Nauroji Nagar)
HANDING OVER TO BUYERS (Nauroji Nagar) Client Name: HANDED 5th Floor TO PFRDA Handed over to private client tower E 6th & 7th floor 27
Slide 29: Redevelopment of Sarojini Nagar (GPRA)
REDEVELOPMENT OF SAROJINI NAGAR (GPRA) 28 Pre-development Houses: 3,976 nos. Post Development Value Additions: • Total House Developed: 10,190 nos • Commercial Built up Area for Sale : 48.19 Lakh sft • Estimated Commercial Value (Fund Realization): 20,000 Cr • Social Infra. : 8.90 Lakh sft • Complet
Slide 30: Redevelopment of Netaji Nagar (GPRA)
REDEVELOPMENT OF NETAJI NAGAR (GPRA) 29 Pre- development Houses – 2,886 nos Post Development Value Additions will be • Total House Developed: 4,737 nos • GPOA Office Accommodation : 23.20 Lakh sft • Social Infra. : 5.7 Lakh sft • Completion Time : 5 Years Area under Development: Over 110.88 acres
Slide 31: Other Major Completed Projects
OTHER MAJOR COMPLETED PROJECTS 30
Slide 32: Bharat Mandapam - Pragati Maidan Development
BHARAT MANDAPAM - PRAGATI MAIDAN DEVELOPMENT IECC (EXHIBITION AND CONVENTION CENTER) DEVELOPMENT • Project Cost: 2350 Cr • Inaugurated by Hon’ble PM on July 26, 2023
Slide 33: Bharat Mandapam - Pragati Maidan Development
BHARAT MANDAPAM - PRAGATI MAIDAN DEVELOPMENT • The redeveloped ITPO complex will host India’s G20 Leaders meetings • With a campus area of approximately 123 acres, the Complex proudly holds the title of India's largest MICE (Meetings, Incentives, Conferences, and Exhibitions) destination. • Magnific
Slide 34: Garvi Gujarat Sadan, New Delhi
GARVI GUJARAT SADAN, NEW DELHI दो साल पहले िसतम्बर म मु ख्यमं ी, उप-मुख्यमं ी जी ने इसका िशलान्यास िकया था और आज िसतम्बर के ारं भ म ही इसका • Project Cost: 131 core उद् घाटन करने का मौका मु झे िमला है । मुझे खुशी है िक समय पर • Completion: 21 months (three months before the deadline) ोजे क्ट् स पू र
Slide 35: Garvi Gujarat Sadan, New Delhi
GARVI GUJARAT SADAN, NEW DELHI
Slide 36: AIIMS Bilaspur Himachal Pradesh
AIIMS BILASPUR HIMACHAL PRADESH 35 • Project Cost: 1250 Cr & Spread over 247 acres • Inaugurated by Hon’ble Prime Minister of India on 05.10.2022 Hospital with 18 specialty & 17 super specialty departments, 18 modular operation theaters, 750 beds with 64 ICU beds.
Slide 37: India Institute of Ayurveda (AIIA) Goa
INDIA INSTITUTE OF AYURVEDA (AIIA) GOA 36 • Project Cost: 268 Cr • Inaugurated by Hon’ble Prime Minister of India on 11.12.2022 Institute consists of an academic block, a hostel, a convenience centre, a sports facility, and a dietary centre.
Slide 38: Vanijya Bhavan, New Delhi
VANIJYA BHAVAN, NEW DELHI, MINISTRY OF COMMERCE AND INDUSTRY 37 Construction of Office building (2 INAUGURATED BY HON’BLE PM ON 23.06.2022 basement + Ground + 5 floors) including other Infrastructure, etc. PROJECT COST : RS. 210 Cr.
Slide 39: Kaushal Bhawan, MOSDE
KAUSHAL BHAWAN , MINISTRY OF SKILL DEVELOPMENT & ENTREPRENEURSHIP (MOSDE) 38 Construction of Office building (3 DATE OF COMPLTION: 25.05.2023 basement + Ground + 7 floors) including Security & IT Infrastructure, etc. PROJECT COST : RS. 172 Cr.
Slide 40: Statue of Netaji Subhash Chandra
STATUE OF NETAJI SUBHASH CHANDRA – INSTALLATION & ILLUMINATION WORK • Hon’ble Prime Minister unveiled a grand statue of Netaji Subhas Chandra Bose AT India Gate on 8th Sep, 2022. • The 28 feet tall towering statue of Netaji is one of the tallest, monolithic, handmade sculptures in India.
Slide 41: MP Bhawan, New Delhi
MP BHAWAN, NEW DELHI 40 PROJECT COST : RS. 149 Cr. INAUGURATED BY HON’BLE CM, MP ON 02.02.2023
Slide 42: Ispat PG Institute and Super Speciality Hospital, Rourkela
ISPAT PG INSTITUTE AND SUPER SPECIALITY HOSPITAL AT RSP SAIL, ROURKELA 41 • Project Cost: 295 Cr • Inaugurated by Hon’ble President of India on March 21, 2021. • 200 bed super-speciality hospitaL
Slide 43: National Police Memorial
NATIONAL POLICE MEMORIAL - INAUGURATED BY HON'BLE PRIME 42 Great Challenge : 270 tonnes, 31 X 10 feet wide single piece of stone transported from Telangana, unloaded & • Project Cost: 50 Crore erected with extreme precaution & technicalities. • Date of Completion : 21.10.2018
Slide 44: Pt. Deendayal Upadhaya Institute of Archaeology
PT. DEENDAYAL UPADHAYA INSTITUTE OF ARCHAEOLOGY, GREATER NOIDA 43 • Project Cost: 288 Crore • Inaugurated by Hon’ble PM on March 09, 2019.
Slide 45: Dr. Ambedkar International Centre for Social Justice
DR. AMBEDKAR INTERNATIONAL CENTRE FOR SOCIAL JUSTICE, NEW DELHI • Project Cost: 185 Crore Hon'ble PM stated that this is first time, he laid foundation & inaugurated also. • Inaugurated by Hon’ble PM Dec 08, 2017 44
Slide 46: 2400 Seater Auditorium Work, Kolkata
2400 SEATER AUDITORIUM WORK, KOLKATA 45 • Project Cost: 418 Cr Completed on April’2023 MODEL • IBC Awards to NBCC for execution of this iconic project.
Slide 47: 2400 Seater Auditorium Work, Kolkata
2400 SEATER AUDITORIUM WORK, KOLKATA 46 The six-floor auditorium having a conch shape structure is 510 feet in length and 210 feet in width.
Slide 48: Indian Institute of Management (IIM) Ranchi
INDIAN INSTITUTE OF MANAGEMENT (IIM) RANCHI • Project Cost: 297 Cr • Date of Completion: 28.02.2022 47
Slide 49: Corporate Office National Insurance Company Limited
CORPORATE OFFICE NATIONAL INSURANCE COMPANY LIMITED 48 • Project Cost: 328 Cr PROPOSED MODEL • Date of Completion : July’2022
Slide 50: Jallianwala Bagh Renovation
JALLIANWALA BAGH RENOVATION 49 • Project Cost: 23 Crore • Inaugurated by Hon’ble PM on Aug 28, 2021.
Slide 51: Border Fencing Works
BORDER FENCING WORKS Border Fencing works at Dampa Tiger Reserve, Mizoram • Project Cost:- Rs 597.00 Cr •Scope of Work:- Border Fencing with patrol road for 58 Kms stretch in Mizoram falling under Dampa Tiger Reserve. Indo-Pak Border Fencing Works in Gujarat • Project Cost:- Rs 763.26 Cr •Scope of W
Slide 52: Heritage Restoration - Purana Qila Restoration
HERITAGE RESTORATION - PURANA QILA RESTORATION UNDER ADOPT A HERITAGE 51
Slide 53: Illuminating the Historic Lal Qila & Qutub Minar
ILLUMINATING THE HISTORIC LAL QILA & QUTUB MINAR 52
Slide 54: National Museum of Indian Cinema, Mumbai
NATIONAL MUSEUM OF INDIAN CINEMA, MUMBAI PROJECT COST : RS 135 Crs INAUGURATED ON 19 JANUARY, 2019. 53
Slide 55: Central Information Commission HQ, New Delhi
CENTRAL INFORMATION COMMISSION HQ, NEW DELHI INAUGURATED BY HON'BLE PRIME MINISTER - Rs. 55 Crore
Slide 56: NIA New Delhi
NIA NEW DELHI INAUGURATED BY HON'BLE EX- HOME MINISTER : Rs. 35 Crore
Slide 57: ESIC Hospital, KK Nagar, Chennai
ESIC HOSPITAL, KK NAGAR, CHENNAI SCOPE OF WORK : Medical college, OPD Block, 24X7 Block, Boys Hostel, Girls Hostel, Interns Hostel, PG Hostel, External Services COST OF THE PROJECT: Rs.365 Cr Project Dedicated to the Nation by Honorable Prime Minister of the India on 10.02.2019. INTERNS/HOUSE SURG
Slide 58: Major Ongoing Projects
MAJOR ONGOING PROJECTS 57
Slide 59: Amrapali Projects
AMRAPALI PROJECTS In 2019, Hon’ble Supreme Court assigned this work to NBCC on PMC Basis Total 25 nos. Projects in Noida & Gr. Noida Execution Status as per Residential Units Execution Status as per Value No of Units Project Value (Cr.) Total no of Residential 46575 Total Project Sanction Units Rs
Slide 60: Amrapali Project Achievement
AMRAPALI PROJECT ACHIEVEMENT Financial Year Achievement (Cr) 2021-22 1166 Cr 2022-23 1734 Cr GOLF HOMES & KINGSWOOD, GREATER NOIDA 59
Slide 61: Amrapali Project - Sapphire, Noida
AMRAPALI PROJECT - SAPPHIRE, NOIDA 60
Slide 62: Amrapali Project - Sample Flat, Leisure Park, Greater Noida
AMRAPALI PROJECT - SAMPLE FLAT, LEISURE PARK, GREATER NOIDA 61
Slide 63: Amrapali Project Dream Valley Phase-II, Greater Noida
AMRAPALI PROJECT DREAM VALLEY PHASE-II, GREATER NOIDA
Slide 64: AIIMS, Deoghar, Jharkhand
AIIMS, DEOGHAR, JHARKHAND 63 • Project Cost: 863 Cr • Progress : 97 % • Likely Date of Completion : December, 2023 ACADEMIC BUILDING AYUSH BLOCK
Slide 65: IIM Sambalpur
IIM SAMBALPUR • Project Cost : Rs. 401.94 Cr. • Scope of work: Academic Block, Hostel Block, Admin Building, Mess & External Development. • Likely Date of Completion: November, 2023 • Progress Achieved – 100% Project Brief: • Client: IIM • All buildings in the project have been divided into 2 differ
Slide 66: IIM Sambalpur
IIM SAMBALPUR Academic Block (Two Wings) Hostel Block
Slide 67: IIM Visakhapatnam
IIM VISAKHAPATNAM • Project Sanction Cost : Rs. 445 Cr. • Scope of work: o Construction of Academy Blocks, Hostel Block and Married Studio Block etc. with allied services • Date of Start: 15.04.2019 • Likely Date of Completion: 31.03.2024 • Progress Achieved – 88% Project Brief: o Client: IIM o Acad
Slide 68: IIM Visakhapatnam
IIM VISAKHAPATNAM alata
Slide 69: IIT Bhubaneswar
IIT BHUBANESWAR • Project Cost : Rs. 560 Cr. • Scope of work: o Construction of Hostels, Housing block, Director Bungalow, Student Activity centre, o Lecture theatre complex, central workshop, o Commercial complex, auditorium and external development works. • Likely Date of Completion: March, 2024 P
Slide 70: NIT, Patna, Bihar
NIT, PATNA, BIHAR Front View • Project Cost: 525 Cr • Progress : 34% Back View • Likely Date of Completion : April, 2024
Slide 71: Bharat Vandana Park
BHARAT VANDANA PARK Plot area : 200 acres land at Dwarka, New Delhi, First of its kind in India being developed as a major tourist destination. Project aims for sustainable and environment friendly development like Eco Park, Landscape creations, Water bodies, Pylons with Skywalks, cultural and adven
Slide 72: Slide 72
Slide 73: East Delhi Hub - Karkadooma
EAST DELHI HUB- KARKADOOMA Integrated Development Name of of East Delhi Hub, Work Karkardooma, New Delhi on TOD Norms Name of Delhi Development Client Authority (DDA) Approximate Cost of Rs. 1,168 .54Cr. Construction Size of Plot 25.47 Hectare Physical 34% Progress Likely Date of October, 2024 Compl
Slide 74: East Delhi Hub - EWS Block
EAST DELHI HUB - EWS BLOCK- 73
Slide 75: Major Real Estate Projects
MAJOR REAL ESTATE PROJECTS 74
Slide 76: Real Estate Division Highlights
REAL ESTATE DIVISION HIGHLIGHTS Started Real Estate Business in year 1988 Established brand with Govt. Support & Guidance First Central Public Sector Enterprise to enter into Real Estate Experienced Management team with strong corporate governance Strong Fundamentals & Financial Health Developed num
Slide 77: Project Gallery - Real Estate Projects
PROJECT GALLERY - REAL ESTATE PROJECTS NBCC VALLEY VIEW, KOCHI NBCC TOWER, BAHADURPUR, PATNA
Slide 78: Project Gallery - Real Estate Projects
PROJECT GALLERY - REAL ESTATE PROJECTS NBCC IMPERIA, BHUBANESWAR, ODISHA NBCC COMMERCIAL COMPLEX, LUCKNOW
Slide 79: Major EPC Projects
MAJOR EPC PROJECTS 78
Slide 80: EPC Sector Highlights
EPC SECTOR HIGHLIGHTS Established as an EPC company in 1960 Specializes in Cooling Towers, Chimneys, other high rise structures Executed - Roads, Bridges, Flyovers, Metro Stations, WTPs, STPs. Technical & Experience Manpower for EPC work Specialized state of art slip-form shuttering technology DELHI
Slide 81: NDCT, Wanakbori, Gujarat
NDCT, WANAKBORI, GUJARAT 80 • Project Cost: 67 crore • Date of Completion : 31.01.2021
Slide 82: Major Overseas Projects
MAJOR OVERSEAS PROJECTS 81
Slide 83: NBCC Overseas Presence
NBCC OVERSEAS PRESENCE PAST FUTURE ONGOING PRESENCE PLAN DUBAI YEMEN BURUNDI MALDIVES TURKEY MONGOLIA BOTSWANA MAURITIUS IRAQ & LIBYA SEYCHELLES OMAN NEPAL NIGER
Slide 84: Construction of New Supreme Court Building, Mauritius
INAUGRATION OF CONSTRUCTION OF NEW SUPREME COURT BUILDING-MAURITIUS INAUGURATED ON 30 JULY, 2020. Hon'ble Prime Minister stated that the project got completed with-in time and with-in budget. 83
Slide 85: 84
84
Slide 86: Mahatma Gandhi Convention Centre (MGCC) at Niamey Niger
MAHATMA GANDHI CONVENTION CENTRE (MGCC) AT NIAMEY NIGER Project Cost: $ 56 Million (Rs. 400 Cr ) Duration : 13 months, Date of Completion : 31.12.2019 Major Highlights : Fabricated Steel Structure airlifted from Ahmedabad 85
Slide 87: Mahatma Gandhi Convention Centre (MGCC) at Niamey Niger
MAHATMA GANDHI CONVENTION CENTRE (MGCC) AT NIAMEY NIGER
Slide 88: India Pavilion, World Expo, Dubai (Completed)
INDIA PAVILION, WORLD EXPO, DUBAI (Completed) Inaugurated on 02nd October 2021. Project Cost : US $ 48 Million (Rs. 340 Crore) First Ever dynamic Façade. 87
Slide 89: Photographs India Pavilion, World Expo, Dubai
PHOTOGRAPHS INDIA PAVILION , WORLD EXPO, DUBAI 88
Slide 90: Institute of Security & Law Enforcement at Maldives
INSTITUTE OF SECURITY & LAW ENFORCEMENT AT MALDIVES Project Cost = 210 Crores Along with Construction, NBCC has also done partly Land reclamation for the project. Project Completed on 89
Slide 91: Institute of Security & Law Enforcement at Maldives
INSTITUTE OF SECURITY & LAW ENFORCEMENT AT MALDIVES Scope - Admin block, Male & Female Qrtrs & barracks, Guest Houses, Auditorium, Gymnasium, Primary Health Centre, Training facilities etc. Total BUA : 2.47 Lakhs sft 90
Slide 92: 2000 Social Housing Units at Hulhumale, Maldives
2000 NOS. SOCIAL HOUSING UNITS AT HULHUMALE, MALDIVES • Project Sanction Cost : USD 130 Million (Rs. 988 Crore INR) • Funded by EXIM Bank of India under Buyer’s credit • NBCC is working as EPC Contractor. • Scope of work: o 2000 Residential Units in 16 Blocks o 1400 units of 3 BHK & 600 units of 2BH
Slide 93: Construction of 2000 Social Housing Units in Maldives
CONSTRUCTION OF 2000 SOCIAL HOUSING UNITS IN MALDIVES
Slide 94: NBCC Services Limited - Facility & Maintenance Management
NBCC SERVICES LIMITED - FACILITY & MAINTENANCE MANAGEMENT NBCC Services Limited" (NSL) is a separate subsidiary of NBCC incorporated in 2014 to provide post construction maintenance services to the clients. PROVIDING COMPREHENSIVE MAINTENANCE SERVICES LIKE : - Civil & Electrical Plumbing, Sanita
Slide 95: Recognitions
RECOGNITIONS 94 Great Place to Work® ISO Certified Company GRIHA RATING CONSTRUCTION Certification
Slide 96: Thank You.
NBCC (India) Limited Lodhi Road New Delhi - 110003 Thank You. 95 www.nbccindia.com