Turquoise Hill Resources — Technical Presentation (November 2016)
44 slides from Turquoise Hill Resources's technical presentation, Nov 8, 2016
Slide 1: Annual Oyu Tolgoi Mine Visit
Annual Oyu Tolgoi Mine Visit November 8-10, 2016
Slide 2: Forward-looking statements
Forward-looking statements This presentation includes certain “forward-looking information” within the meaning of applicable Canadian securities legislation and “forward-looking statements” within the meaning of the “safe harbour” provisions of the United States Private Securities Litigation Reform
Slide 3: Oyu Tolgoi underground mine briefing
Annual Oyu Tolgoi Mine Visit NOVEMBER 8-10, 2016 Oyu Tolgoi underground mine briefing
Slide 4: Hugo North and South Progression
Hugo North and South Progression
Slide 5: Execution
Execution Hugo North Lift 1 (NHL1) Underground Mine Physical infrastructure Operational capability • Underground mine able to • Underground operations team produce 95ktpd. (production + ongoing • Five shafts (personnel and construction + maintenance + equipment access and technical services). ventil
Slide 6: Expansion Scope
Expansion Scope Key aspects • Development of HNL1, by panel cave mining method • High grade ore body ~2km long and 280m wide, containing 499Mt ore at 1.66% copper, 0.34g/t gold • >200km of underground lateral development • Five vertical shafts and a decline incorporating conveyor to surface • Concen
Slide 7: Key underground components
Key underground components Shaft 1 Shaft 2 Shaft 5 Shaft 3 Shaft 4 (early development (production and (ventilation) (ventilation) (ventilation) and ventilation) ventilation) Total Depth 1,385 metres 1,284 metres 1,178 metres 1,148 metres 1,149 metres Diameter 6.7 metres 10 metres 6.7 metres 10 metre
Slide 8: Ore Flow
Ore Flow APEX LEVEL Lateral Development le UNDERCUT LEVEL a= @ —> ag, — Lateral Development Undercutting Undercut Mucking & Ground Support EXTRACTION LEVEL \s/ Lateral Development Drawpoint / Drawbell Production & Ground Support Construction ag HAULAGE LEVEL Ce CG ome ame DUMP AT DUMP AT Fill Trucks
Slide 9: Geotechnical
Geotechnical • Hugo North orebody is – Highly faulted – Fair rock mass strength – Relatively high insitu (horizontal) stresses and abutment stresses • This is good for promoting caving and minimising secondary breaking • The challenge and key focus for the Oyu Tolgoi design and operating plan is aro
Slide 10: Cave support
Cave support Ground Support Major faults and strain Fair to good rockmass, High stress Major faults and weak burst prone rockmass static conditions environment rock mass ground support regime Minimum 2.4m bolt and Add mesh; cables and Add cables and Add yieldable support shotcrete strapping @1m stra
Slide 11: Cave monitoring
Cave monitoring • Cave growth and flow monitoring systems will be in place before start up of the undercut: – Seismic system – TDR and open holes – Smart/network markers – Cave Tracker • Regular surface subsidence monitoring will be carried out 11
Slide 12: Cave management
Cave management Single data repository Real-time hazard recognition CaveCad Collecting, validating, processing, analyzing Pillar stability and reporting data Standardised cave automatically 3D analysis and reporting management systems Reports HOD Convergence High Medium Low Integrated system; reduce
Slide 13: Undercut
Undercut • Undercut blasted in advance of drawpoint and drawbell excavation • Undercut face length < 350m and retreats at > 80m per year • Undercut lead/lag is 10m • Undercut face orientation + drives favourable to stress and structure Undercut 13
Slide 14: Undercut
Undercut APEX To Drilling Blasting Drill 28m 28m 17m UNDERCUT 17m EXTRACTION 28m The ‘Wide W’ has significant benefits over traditional ‘Small W’ • Improved stability • Improved operability 14
Slide 15: Extraction
Extraction Drawbell Ore Steel Set Pass Drawpoint Extraction Drift Vent IDZ Raise 10 m 28m Mine Spacing Fragmentation Drawbell Andina 26m x 13m Very Fine blast New Afton 28m x 15m Fine 12 m Oyu 28m x 15m Fine (Expected) Tolgoi 15m DOZ 30m x 18m Mid Palabora 34m x 17m Coarse 15
Slide 16: Ore Handling
Ore Handling Shaft #2 • 10m dia service and production shaft 30kt/d • 2 x 60t skips • 1,630tphr (~19hr/d) 16
Slide 17: Ore Handling
Ore Handling Conveyor to Surface • 3 x 2.2km legs • 1,600mm wide belt @ 6m/s • 6,500 tphr • 2 x 6 MW gearless drives each leg • Commission six months before 30kt/d 30kt/d 95kt/d 17
Slide 18: Oyu Tolgoi open-pit operations
Annual Oyu Tolgoi Mine Visit NOVEMBER 8-10, 2016 Oyu Tolgoi open-pit operations Steve Jones Acting CEO, Oyu Tolgoi
Slide 19: Production achievements
Production achievements All injury frequency rate Total material mined (per 200,000 hours worked) ('000 tonnes) 27% 2015 vs. 2013 72% 2016 YTD vs. 2013 91,771 0.47 0.43 76,919 72,032 71,322 0.33 0.12 2013 2014 2015 2016 YTD 2013 2014 2015 2016 YTD Industry-leading safety performance Strong haul tr
Slide 20: Oyu Tolgoi's Q3'16 cost curve position
Oyu Tolgoi’s Q3’16 cost curve position 2016 copper mine C1+royalties+sustaining normal cost curve C/lb, 2016$ 400 Q1 Q2 Q3 Q4 300 Oyu Tolgoi Other Mines 200 100 0 kt 0 2,000 4,000 6,000 8,000 10,000 12,000 14,000 16,000 18,000 Cumulative production (‘000 tonnes) -100 Source: Wood Mackenzie (Q3’16 Co
Slide 21: Managing current ore grade challenges
Managing current ore grade challenges Open pit Phase 1 finished and Phases 2 and 3 nearly complete Lower-grade Phase 6 and stockpile ore processed from mid-2016 to mid-2018 Waste movement from Phase 4 critical to uncover medium-grade ore in 2017, then higher-grade ore beginning in mid-2018 201
Slide 22: Continued focus on reducing cash costs
Continued focus on reducing cash costs • Business improvement programs have been in place since 2014 delivering value across productivity, operating costs, sustaining capex and working capital. • The program values one-off savings, sustaining capital reductions and net working capital (NWC) reductio
Slide 23: Oyu Tolgoi underground development
Annual Oyu Tolgoi Mine Visit NOVEMBER 8-10, 2016 Oyu Tolgoi underground development Marco Pires Chief Development Officer Oyu Tolgoi Underground
Slide 24: Unlocking value through underground project
Unlocking value through underground project First drawbell production expected in mid-2020 with full ramp-up by 2027 Average of 560,000 tonnes of copper from open pit and underground 2025- 20301 First quartile, low-cost operation 1. 2016 Oyu Tolgoi Technical Report 24
Slide 25: Oyu Tolgoi underground a Tier 1 asset
Oyu Tolgoi underground a Tier 1 asset 2025 copper mine C1+royalties+sustaining normal cost curve C/lb, 2016$ 400 Q1 Q2 Q3 Q4 300 Oyu Tolgoi Other Mines 200 100 0 kt 0 2,000 4,000 6,000 8,000 10,000 12,000 14,000 16,000 18,000 Cumulative production (‘000 tonnes) -100 Source: Wood Mackenzie (Q3’16 Cos
Slide 26: Panel block cave development
Panel block cave development Highly productive mass mining method with low operating costs. Substantial upfront investment and lower operating costs make block caving suitable for larger deposits. Resource recovery is effective as the low operating costs support economic extraction of a lower sh
Slide 27: Robust mine design
Robust mine design Footprint size 2,000m x 280m and 1,300m below surface 203km tunnel, 137,000m3 mass excavation Five shafts (three air intake and two exhaust) Advance undercut, wide “W” profile with anti-socket drive, 567,000m2 2,231 drawpoints (El Teniente layout), 28m x 15m spacing, cen
Slide 28: Complete ramp-up expected by 2027
Complete ramp-up expected by 2027 Sustainable underground production Complete convey to surface Project 1st draw Complete concentrator Complete re-start bell firing upgrade ramp-up 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 Pre-start Excavation (lateral / mass / vertical) Excav
Slide 29: Key underground components
Key underground components Shaft 1 Shaft 2 Shaft 5 Shaft 3 Shaft 4 (early development (production and (ventilation) (ventilation) (ventilation) and ventilation) ventilation) Total Depth 1,385 metres 1,284 metres 1,178 metres 1,148 metres 1,149 metres Diameter 6.7 metres 10 metres 6.7 metres 10 metre
Slide 30: Processing plant upgrade
Processing plant upgrade Concentrate from Hugo North Lift 1 ore Higher copper grade Higher recovery Chalcopyrite/bornite Plant upgrade Addition of 5th ball mill Additional flotation line Additional concentrate filtering and bagging capacity Plant capacity of 40 million tonnes per year
Slide 31: Approved underground CAPEX
Approved underground CAPEX $1.3 $1.2 $1.2 $1.0 $0.8 $0.5 $0.5 $0.3 $0.4 $0.4 $0.4 $0.3 Underground expansion capital, VAT and escalation of $5.3 billion Underground sustaining capital, VAT and escalation of $2.8 billion to full ramp-up expected in 2027 31
Slide 32: Underground contracts awarded to date
Underground contracts awarded to date Key Contracts Awarded Supplier Key contracts split Description Group Contractor EPCM Onshore National Jacobs EPCM Offshore International Jacobs Boxcut and Decline National Theiss Khishig (C2S) Arvin JV Explosives Supply and National Maxam National Services Explo
Slide 33: Strong project momentum
Strong project momentum Currently Workforce ~1,600 Major contracts fully mobilized Lateral development occurring as planned Boxcut well advanced Steady progress of sinking Shafts 2 and 5 Expected by 2017 Workforce of ~2,400 Dual decline commenced Decline box cut Left: belt conveyor ram
Slide 34: Oyu Tolgoi's long-term potential
Annual Oyu Tolgoi Mine Visit NOVEMBER 8-10, 2016 Oyu Tolgoi’s long-term potential Jeff Tygesen, Chief Executive Officer Steeve Thibeault, Chief Financial Officer Brendan Lane, Vice President Operations and Development
Slide 35: Achievements 2015-2016
Achievements 2015-2016 1 May 2015 – Underground Development Plan approved 2 August 2015 – Underground pre-start activities begin 3 December 2015 – Project finance facility signed 4 May 2016 – Notice to proceed and 2016 Feasibility Study approved 5 June 2016 – Drawdown of project finance facility 6 A
Slide 36: Long-term copper fundamentals strong
Long-term copper fundamentals strong Copper mine supply/demand outlook (Mt) Copper market likely to be in balance in 2017. Base Highly Probable Primary Demand 30 Ongoing attrition at existing Forecast mines driven by declining 25 grade 20 Continued demand growth requires new capacity in the 15
Slide 37: 2016 Reserves Case
2016 Reserves Case Concentrator capacity 40mtpa, 10% above nameplate capacity 2016 Reserves Case Mining Areas Open pit utilized to top-up concentrator Underground ramp-up to full production (~33mtpa) expected 2020-2027 Highest grade ore mined first – initial underground copper grades expecte
Slide 38: Alternative Production Cases
Alternative Production Cases Plant 38
Slide 39: 2016 Resources Case
2016 Resources Case 2016 Resources Case Processing Production Assumes concentrator capacity of 40mtpa for life Base Case NPV8% $8.37 billion1 Expansion capital costs $9.73 billion2 Plant 1. Base case NPV8% assumes $3.00/lb copper and $1,300/oz gold 2. Expansion capital costs inclusive of 2016
Slide 40: Resources 50 Case
Resources 50 Case Resources 50 Case Processing Production Concentrator creep from 40mtpa to 50mtpa with little capital Assumes 5% improvement in concentrator capacity per year for five years Base case NPV8% $9.32 billion1 Expansion capital costs $9.73 billion2 Plant 1. Base case NPV8% assume
Slide 41: Resources 100 Case
Resources 100 Case Resources 100 Case Processing Production Assumes ~Year 20, concentrator expanded to 100mtpa Base Case NPV8% $8.88 billion1 Expansion capital costs $13.47 billion2 Plant 1. Base case NPV8% assumes $3.00/lb copper and $1,300/oz gold 2. Expansion capital costs inclusive of 2016
Slide 42: Resources 120 Case
Resources 120 Case Resources 120 Case Processing Production Assumes ~Year 20, concentrator expanded to 120mtpa Base Case NPV8% $8.80 billion1 Expansion capital costs $14.86 billion2 Plant 1. Base case NPV8% assumes $3.00/lb copper and $1,300/oz gold 2. Expansion capital costs inclusive of 2016
Slide 43: Cost sensitivity options
Cost sensitivity options 1 Underground construction capital reduced by 30% 2 Operating costs reduced by 15% 3 G&A costs assumed to reach long-term average cost of $50 million from Year 7 4 Rail freight available to project after 2020 and concentrate freight cost is reduced to $25 per tonne 43
Slide 44: Oyu Tolgoi– a long-term growth opportunity
Oyu Tolgoi– a long-term growth opportunity Open pit performing as expected in low gold areas Demonstrated productivity and cost improvements Underground development progressing Long-term development optionality and plant expansion opportunities Oyu Tolgoi best copper asset in development t