Turquoise Hill Resources Ltd.

Turquoise Hill Resources — TD Securities Mining Conference 2014

14 slides from Turquoise Hill Resources's conference presentation, Jan 29, 2014

  1. Slide 1: Oyu Tolgoi – a world-class copper and gold mine

    Oyu Tolgoi – a world-class copper and gold mine January 29, 2014 TD Securities Mining Conference

  2. Slide 2: Forward-looking statements

    Forward-looking statements This presentation includes certain “forward-looking information” within the meaning of applicable Canadian securities legislation and “forward-looking statements” within the meaning of the “safe harbour” provisions of the United States Private Securities Litigation Reform

  3. Slide 3: Long-term growth opportunity

    Long-term growth opportunity 1 Pure copper and gold exposure with attractive industry fundamentals 2 World class asset, strategically located 3 Flexible growth profile with further prospectivity 4 Commenced production, cash flow generation in 2014 5 Partnership with best-in-class operator and develo

  4. Slide 4: Oyu Tolgoi – a tier 1 asset

    Oyu Tolgoi – a tier 1 asset Copper mine cost curve in 2020 (c/lb, 2013$) 400  Oyu Tolgoi is in the first quartile of the industry 350 Oyu Tolgoi cost curve Other Mines 300 250  Third largest copper mine after planned expansion1 200 150  Top 10 copper deposit by 100 contained reserves and resource

  5. Slide 5: Fundamentals for copper remain strong

    Fundamentals for copper remain strong  Copper market likely to see Copper mine supply/demand outlook (Mt) small surplus in coming years 30 Base  Ongoing attrition at existing Forecast mines driven by structural 25 Highly Probable decline in grade; continued Primary Demand demand growth means the 2

  6. Slide 6: Strategically located next to key growth market

    Strategically located next to key growth market Strategic location:  At the doorstep of the major growth market, 80km from Chinese border Near-term and large scale:  Long-life mine  2.2bt measured & indicated and 4.4bt inferred resource  1.5bt mineral reserve, 26.5Mlb. of copper and 12.9Moz. of

  7. Slide 7: Our People, Our Impact

    Our People, Our Impact  All Injury Frequency Rate performance good at 0.43 per 200,000 hours worked  HSE System certified to ISO 14001 and OSHAS 18001  Mongolians now occupy more than 90% of roles  Over $1 billion in taxes, pre-payments and fees paid to the Government since 2010  Partnered with

  8. Slide 8: From construction to operations

    From construction to operations Q1’13 Q2’13 Q3’13 Q4’13 • Initial construction • Concentrator • Commercial • Customers begin substantially complete continued to improve production achieved collecting concentrate stabilizing at rates • First copper-gold above 70% design • Commenced shipping • Produce

  9. Slide 9: Current development plan

    Current development plan Southern Oyu Tolgoi Pits Concentrator Facility Southwest Southwest Central Hugo North Lift 1 Hugo North Lift 1 9

  10. Slide 10: Potential for significant development opportunities

    Potential for significant development opportunities Southern Oyu Tolgoi Pits Concentrator Facility Heruga Southwest Central Hugo South Underground Hugo North Lift 1  All options being evaluated to ensure optimum development pathway  Actual operating performance will inform choice of expansion path

  11. Slide 11: Vast resources and further prospectivity

    Vast resources and further prospectivity  Proven mineralized trend ~26km, exploration focused on higher value targets 11

  12. Slide 12: Unlocking Oyu Tolgoi’s value

    Unlocking Oyu Tolgoi’s value  Fund ongoing development of the project Main Objectives  Diversify sources of project funding through involvement of International Financial Institutions, Export Credit Agencies and international commercial banks Rights  Successfully completed ~$2.4 billion rights of

  13. Slide 13: 2014 Outlook

    2014 Outlook  150,000 to 175,000 tonnes of copper in concentrates  700,000 to 750,000 ounces of gold in concentrates  Operating costs of approximately $1 billion  Capital expenditure of $160 million 13

  14. Slide 14: Turquoise Hill – a long term growth opportunity

    Turquoise Hill – a long term growth opportunity  Pure copper and gold exposure with expansive resources  Generating positive cash flow in 2014  Progressing Project Financing for funding of underground development  Significant growth, development and expansion opportunities  Strategically locate