Agrium — Corporate Update (2002)
32 slides from Agrium's corporate update, 2002
Slide 1: Gypsum Storage Area Extension
Gypsum Storage Area Extension 1
Slide 2: Project Description: Redwater Facility
PROJECT DESCRIPTION Northern Extension of the Existing Gypsum Ponds REDWATER FACILITY Our fertilizer operation at Redwater is an integrated complex which produces both nitrogen and phosphate fertilizers. This presentation deals with the planned extension to the existing gypsum storage area. Gypsum i
Slide 3: Objectives
Objectives • Overview • Why we need to extend the stack • Describe public consultation process • Describe environmental assessments • Describe project features • Describe construction process • Present project schedule • Discuss next steps • Obtain feedback As you can see we have several objectives
Slide 4: Overview
Overview • Our existing Phosphate facility was built in 1969 • Current Gypsum Pond and Storage area 425 acres • Planned extension (north) of 295 acres • Utility relocations in 2003 • If project is approved, construction will take place in phases Our phosphate facility at Redwater was constructed in
Slide 5: Location Plan
Location Plan This aerial photograph shows the existing cooling pond and gypsum storage area. Outlined in red near the top of the photograph is the planned 295 acre extension to the north of the existing storage area. 5
Slide 6: Why we need to extend the stack
Why we need to extend the stack • At current production rates we make about 1.5 million tonnes of gypsum per year. • Each year the available surface area for storing gypsum becomes smaller. • By 2004, if new surface area is not made available for gypsum storage, plant production rates will have to b
Slide 7: Public Consultation
Public Consultation • Obtain Community Advisory Panel input • Employee information sessions • Information sessions with Strathcona and Sturgeon County elected officials and county managers • Obtain input from close neighbors in both Strathcona and Sturgeon counties through meetings at Redwater Site
Slide 8: Environmental Assessments
Environmental Assessments (will form part of our operating approval amendment application) • Groundwater – protection incorporated into stack design – computer modeling to assess impact on regional groundwater movement – expanded groundwater monitoring network • Air Quality – computer modeling to as
Slide 9: Environmental Assessments (continued)
Environmental Assessments (continued) • Aquatic Resources – establish baseline condition of the North Saskatchewan River in this area – sample water in river bed – biological survey of river bottom to assess aquatic life – no additional water will be diverted from the river • Noise – we are sensitiv
Slide 10: Environmental Assessments: Materials Management
Environmental Assessments (continued) • Materials Management – Agrium has been active in investigations of alternative gypsum uses – Examples include • oilfield reclamation • composting of manure at feedlots • tar sands tailings settling and consolidation (Fort McMurray) • soil treatment for high sa
Slide 11: Environmental Assessments: Soils, Vegetation, Wildlife
Environmental Assessments (continued) • Soils management – topsoil will be removed from the extension area prior to construction – a plan is being developed, in accordance with Alberta Environment guidelines, to best preserve this resource • Vegetation and wildlife – the extension area is currently
Slide 12: Environmental Assessments: Surface Water, Historical Resources
Environmental Assessments (continued) • Surface Water – no adverse impacts from surface water runoff are anticipated – surface water runoff from the outside slopes of the new stack will be collected in a perimeter ditch system within the liner area and returned to the process • Historical resources
Slide 13: Schedule
Schedule • Project description to be issued Q2, 2002 • Community consultation Q2-Q3, 2002 • Application to Alberta Environment Q3, 2002 • Utility relocation in 2003 • If project is approved: Phase I Construction in 2004, followed by Phase II and III construction 2008 or later A description of the pr
Slide 14: Project Features
Project Features • Design based on industry best practices and best available technology • Continuous clay base (minimum 0.6 m thick) • 1.5 mm (60 mil) synthetic high density polyethylene liner (HDPE) • Perimeter dyke and under-drain system • Phased construction We will be using best available techn
Slide 15: Starter Dyke and Position of HDPE liner
Starter Dyke and Position of high density polyethylene liner (HDPE) This drawing shows a simplified cross sectional view of the gypsum stack extension. Key features include the clay fill liner and clay dyke. The high density polyethylene liner is the blue line that is notched into the perimeter clay
Slide 16: High Density Polyethylene Liner
High Density Polyethylene Liner This photograph shows two different samples of the liner material. The sample on the left is smooth high density polyethylene which is used for linin g horizontal surfaces such as the base of the extension area. The sample on the right is textured high density polyeth
Slide 17: Site Preparation
Site Preparation Prior to construction, gas and power utilities in the extension area will be relocated. The first step in the construction process is removal of topsoil. After the topsoil has been removed, the surface is graded and prepared for installation of the synthetic liner above the natural
Slide 18: Site Preparation
Site Preparation This photograph shows the clay perimeter dyke in the background. During the process of preparing the base for the synthetic liner, we remove some of the clay and use it to construct the perimeter clay dyke which is keyed into the underlying clay till layer. 18
Slide 19: High Density Polyethylene Liner
High Density Polyethylene Liner (60 mil smooth liner) Following site preparation and construction of the clay perimeter dyke, the synthetic liner is installed. This picture shows a roll of high density polyethylene liner material. It comes in 23 foot width, in lengths of up to 1,000 feet. 19
Slide 20: Liner Welding Equipment
Liner Welding Equipment The rolls of high density polyethylene material are joined together using a process similar to welding. This photograph shows a set up of a typical extrusion welding machine in the process of welding a patch. On the reel is high density polyethylene material used to join the
Slide 21: Liner Welding
Liner Welding Here you can see a closer view of the equipment used to join the high density polyethylene liner together using an extrusion welding machine. 21
Slide 22: Vacuum Testing Liner
Vacuum Testing Liner After the liner sections are joined together by welding, the joints are tested. There are several different method for testing. This picture shows a welded joint being tested by the “vacuum box method”. The vacuum box is made of clear plastic with a shop vacuum motor setup creat
Slide 23: High Density Polyethylene Liner
High Density Polyethylene Liner Shown here is the synthetic liner as it nears completion. The two individuals on the right of the photograph are actually welding the liner together. 23
Slide 24: High Density Polyethylene Liner
High Density Polyethylene Liner This is another view of the synthetic high density polyethylene liner as it nears completion. It shows the joints after they have been fused together. 24
Slide 25: Gypsum Over Synthetic Liner
Gypsum Over Synthetic Liner After completing the synthetic liner and all the necessary design testing to ensure there are no faulty joints or leaks in the liner has been completed, it is covered with a protective gypsum layer. 25
Slide 26: Slotted Pipe for Under-Drain System
Slotted Pipe for Under-Drain System After the synthetic liner has been completed and it has been covered with gypsum, the perimeter under drain system is installed. The purpose of the under drain system is to increase the overall stability of the dyke. This slide shows the slotted piping used for th
Slide 27: Under-Drain System
Under-Drain System To install the under-drain a trench is dug into the gypsum that was placed over the liner. A geo-textile fabric is then placed into the trench. The fabric is then covered with non-reactive aggregate. The slotted pipe, shown in the previous photograph is laid on top of the aggregat
Slide 28: Under-Drain Discharge
Under-Drain Discharge This picture shows the perimeter collection ditch. The under-drains discharge into this area through a series of pipes. You can see the pipes sticking out in rows on this photo. The water is collected from the lined gypsum pond through these pipes into this perimeter ditch and
Slide 29: Completed Under-Drain System
Completed Under-Drain System Pictured here is the completed under drain system covered with gypsum. You can see three completed under-drain systems in this photo. 29
Slide 30: Gypsum Perimeter Dyke Construction
Gypsum Perimeter Dyke Construction Here you can see the use of trucks for constructing the gypsum perimeter dyke. This is the final step prior to beginning operation of the new storage area. 30
Slide 31: Next Steps
Next Steps • Obtain additional public feedback • Complete environmental assessments • Continue design activities • Continue regulatory approval process Our next step is to continue to obtain public feedback, through open houses, mailouts, our website and any direct contacts that we may receive. We’l
Slide 32: Feedback
Feedback Thank you for taking the time to learn about our gypsum storage area extension. If you have any questions or would like more information, please do not hesitate to ask us. 32