  1. Slide 1: Western Massachusetts Reliability Project Community Virtual Open House

    Western Massachusetts Reliability Project Community Virtual Open House Evening: 11/09/2021 6:00 PM – 8:00 PM Day: 11/10/2021 1:00 PM – 3:00 PM

  2. Slide 2: Open House Translation Services

    Open House Translation Services Thank you for joining us A few announcements: – This meeting is being recorded – Translation of tonight's presentation in Spanish is available – Please click on the globe symbol below and choose Spanish if you would like to hear the presentation in Spanish. Thank you

  3. Slide 3: Western Massachusetts Reliability Project Community Open House

    Western Massachusetts Reliability Project Community Open House Evening: 11/09/2021 6:00 PM – 8:00 PM Day: 11/10/2021 1:00 PM – 3:00 PM

  4. Slide 4: Project Team Members

    Project Team Members Richard Salvarezza - Project Manager Mark Gunsalus - GM for Eversource Gas of Mass. Chris Luca - Project Management Ryan Barnes - Engineering Matt Waldrip - Licensing and Permitting Jeff Brandt - Eversource contractor from TRC Nikki Bruno - Clean Technologies Shaela Collins - Re

  5. Slide 5: Presentation Topics

    Presentation Topics 1. Project Need 2. Impact of Service Interruption 3. Project Scope 4. Routing Analysis 5. Evaluation of Alternatives 6. Potential Routes 7. Longmeadow POD 8. Safety 9. Regulatory Approval Process 10. Additional Project Approvals 11. Schedule 12. Community Outreach 13. Contact Inf

  6. Slide 6: Project Need

    Project Need Why is Eversource proposing this project?​ • This Project is needed to provide necessary system reliability to approximately 58,000 customers in the Greater Springfield Area • This area is currently served by single source of supply that is 70 years old and located within the Memorial B

  7. Slide 7: Project Need & Community Benefits

    Project Need & Community Benefits • This Project is designed to: • Update and strengthen the backbone of the gas system • Reduce the risk of gas service interruption due to an unexpected disruption to the single supply line • Risk: • Interruption of supply along this pathway would result in customer

  8. Slide 8: Impact of Service Interruption

    Impact of Service Interruption Unprecedented Community Impact ▪ Community Safety, Health & Security • Includes: food and water supply, shelter and transport, distribution of supplies • Temporary housing, warming shelters • Emergency law enforcement and patrolling ▪ Activation of Incident Command Sys

  9. Slide 9: Proposed Solution

    Proposed Solution • The Proposed Project will create an independent source of supply to the Greater Springfield Area. • Scope Includes: • Construction of a new Point-of- Delivery (POD) Station in Longmeadow • Installation of a new 16-inch pipeline and upgrade of existing pipeline segments • From: Th

  10. Slide 10: Routing Analysis

    Routing Analysis • Eversource has identified several potential alternatives for locating pipelines between Longmeadow POD and Bliss Street Station • Route options were analyzed based on extensive regulatory precedent balancing consideration of reliability, environmental and community impacts, and co

  11. Slide 11: Project Alternatives Considered

    Project Alternatives Considered • Non-Pipeline Alternatives • Energy Efficiency • Demand Response • Electrification • Geothermal • Pipeline Alternatives • Alternative POD Locations • Alternative Pipeline Routing Options Alternatives do not meet the current need for reliability to our customers. 10

  12. Slide 12: Potential Routes

    Potential Routes Preferred and Noticed Alternatives/Variations ▪ Preferred Route – (solid purple) – I-91 (MassDOT) – Approximately 5.4 miles – Approximately 1,000 abutters ▪ Noticed Variation 1 to Preferred Route – (dotted orange) – Approximately 5.4 miles – Approximately 900 abutters ▪ Noticed Vari

  13. Slide 13: Proposed Longmeadow Point of Delivery Station

    Proposed Longmeadow Point of Delivery Station • A POD is a site where natural gas is transferred from the interstate transmission supplier -Tennessee Gas Pipeline (TGP) – and then prepared for delivery to our customers. • POD buildings are being designed to match existing structures in the area and

  14. Slide 14: Proposed Longmeadow POD Layout

    Proposed Longmeadow POD Layout 13

  15. Slide 15: Proposed Longmeadow POD Buildings

    Proposed Longmeadow POD Buildings 14

  16. Slide 16: Enhancements Focused on Safety

    Enhancements Focused on Safety ▪ 24/7 Remote Monitoring and Onsite Inspections – Security alarms, leak detection, remote control & emergency shutdown ▪ Automatic Alarming to Gas Control Room ▪ Damage prevention – Regular patrols by trained technicians and supervisors – DigSafe and excavator monitori

  17. Slide 17: Regulatory Approval Process

    Regulatory Approval Process • Eversource will submit a proposal to the Massachusetts Energy Facilities Siting Board (EFSB) in late 2021 • This opens a comprehensive regulatory review before the EFSB • EFSB reviews major energy facility projects and is charged with ensuring a reliable and safe energy

  18. Slide 18: Project Approvals

    Project Approvals* • Local Street Opening Permits • Building Permits (for POD-Meter Station) • Massachusetts Environmental Policy Act (MEPA) Certificate, Executive Office of Energy and Environmental Affairs • Massachusetts Wetlands Protection Act and local bylaws • Park Land Permitting • National Po

  19. Slide 19: Projected Schedule

    Projected Schedule Milestones Target Dates* Stakeholder Outreach Ongoing (Government, Agencies, Landowners, other Stakeholders) Submit Massachusetts Environmental Policy Act December 2021 (Environmental Notification Form) Submit EFSB Petition December 2021 Submit MassDOT State Highway Access Permit

  20. Slide 20: Municipal and Community Outreach

    Municipal and Community Outreach • Stakeholders • Municipal officials - Springfield, Longmeadow, Southwick, West Springfield, Agawam, Chicopee, East Longmeadow • Property owners & residents • State and federal elected officials, regulators, and agencies • Businesses • Community groups • Project Comm

  21. Slide 21: Project Contact Information

    Project Contact Information For More Information: 1-800-793-2202 ProjectInfo@eversource.com www.eversource.com/wma-gas-reliability You can also keep up-to-date on happenings in your community by providing your contact information via phone, email or by scanning the QR code with your smart device. Jo