Slide 1: Proposed Carver to Kingston Reliability Project
Proposed Carver to Kingston Reliability Project Department of Public Utilities (DPU) Public Hearing Towns of Carver, Plympton, and Kingston October 27, 2020 Safety First and Always
Slide 2: Table of Contents
Proposed Carver to Kingston Reliability Project Table of Contents ▪ Proposed Project Overview ▪ Project Need ▪ Proposed Project Cross Sections ▪ Typical Overhead Construction ▪ Estimated Project Construction, Permitting and Estimated Timeline ▪ Community Outreach ▪ Contact Information Safety First a
Slide 3: Overview
Proposed Carver to Kingston Reliability Project Overview ▪ Currently, Eversource has one overhead transmission line in the right of way between the Carver Substation, off Route 58, and the Kingston Substation on Pembroke Street in Kingston ▪ The Carver to Kingston Project proposes constructing a new
Slide 4: Project Need
Proposed Carver to Kingston Reliability Project Project Need ▪ A reliable electrical transmission grid is vital to the safety, security and economic prosperity of the region. The transmission system serves a critical role to ensure the electricity flows with a high degree of reliability to where pow
Slide 5: Structure Cross Sections – Carver Substation to Spring Street
Proposed Carver to Kingston Reliability Project Structure Cross Sections – Carver Substation to Spring Street In this section, H-frame steel structures are proposed. 4 Safety First and Always
Slide 6: Structure Cross Sections – Spring Street to Brook Street
Proposed Carver to Kingston Reliability Project Structure Cross Sections – Spring Street to Brook Street Due to the existence of a distribution line, the structures in this section will be steel monopoles to adjust to the proper distancing needed between circuits. 5 Safety First and Always
Slide 7: Structure Cross Sections – Brook Street to Bog View Drive
Proposed Carver to Kingston Reliability Project Structure Cross Sections – Brook Street to Bog View Drive With the distribution line present, the structures in this section will be steel monopoles to allow for proper distancing between circuits. 6 Safety First and Always
Slide 8: Structure Cross Sections – Bog View Rd to Kingston Substation
Proposed Carver to Kingston Reliability Project Structure Cross Sections – Bog View Rd to Kingston Substation With a distribution line present, the structures in this section will be steel monopoles to allow for proper distancing between circuits. 7 Safety First and Always
Slide 9: Typical Overhead Construction
Typical Overhead Construction 8 Safety First and Always
Slide 10: Construction
Proposed Carver to Kingston Reliability Project Construction • Where applicable, crews will secure police details and implement traffic management plans to: ✓ Access the right of way ✓ Maintain residential street access ✓ Maintain pedestrian and motorist safety • Eversource will communicate and work
Slide 11: Permitting
Proposed Carver to Kingston Reliability Project Permitting Permits or Permitting Agency Jurisdiction Army Corps of Engineers Federal Environmental Protection Agency Federal Massachusetts Department of Environmental Protection State (MassDEP) Massachusetts Department of Transportation State Massachus
Slide 12: Estimated Timeline
Proposed Carver to Kingston Reliability Project Estimated Timeline* Q3 2019 Q4 2019 Q1 2020 Q2 2020 Q3 2020 Q4 2020 Q1 2021 Q2 2021 Q3 2021 Q4 2021 Community Open House (complete) Chapter 72 Application Filed with DPU (complete) Public Comment Hearing* Other Federal, State & Local Environmental Perm
Slide 13: Community Outreach
Proposed Carver to Kingston Reliability Project Community Outreach Stakeholders ▪ Municipal officials ▪ State and federal elected officials and regulators ▪ Property owners & tenants ▪ Businesses Project Communication for Municipalities ▪ Briefings & Presentations ▪ E-mail updates Project Communicat
Slide 14: Team Contact Information
Proposed Carver to Kingston Reliability Project Team Contact Information Project Manager Nathan Dennis Phone: (774) 404-4400 Email: Nathan.Dennis@eversource.com Project Community Outreach Representative (Siting and Construction Services) Megan Aconfora Phone: (203) 499-9245 Email: Megan.Aconfora@eve