Fresnillo Plc · LSE:FRES

Fresnillo — Denver Gold Forum 2012

17 slides from Fresnillo's conference presentation, Sep 11, 2012

  1. Slide 1: Strengthening our precious metals position

    Strengthening our precious metals position Denver Gold Forum September 11, 2012 Octavio Alvídrez, CEO Fresnillo plc LSE:Fres BMV:Fres www.fresnilloplc.com

  2. Slide 2: Disclaimer

    Disclaimer This document includes statements that are, or may be deemed to be, “forward-looking statements”. These forward- looking statements can be identified by the use of forward-looking terminology, including the terms “believes”, “estimates”, “plans”, “projects”, “anticipates”, “expects”, “int

  3. Slide 3: Company profile

    Company profile • We are the world’s leading silver producer and Mexico’s second largest gold Who we are producer. • Headquartered in Mexico City, our shares trade on the London and Mexican Stock Exchanges. • Our business spans the full mining value chain: exploration, development, What we do constr

  4. Slide 4: Fresnillo plc at a glance

    Fresnillo plc at a glance • Seven operating mines and one Silverstream 2011 PRODUCTION SILVER GOLD (Koz) (Oz) Fresnillo mine Silver underground mine 30,295 26,237 Saucito mine Silver underground mine 5,904 33,493 Ciénega unit: Ciénega mine Gold-Silver underground mines 1,474 116,841 San Ramón satell

  5. Slide 5: Fresnillo plc at a glance

    Fresnillo plc at a glance 2011 Highlights • Revenues US$2.2 billion • Operating profit: US$1.4 billion • Total assets: US$2.8 billion • Risk capital invested in exploration US$179 million • Market cap @ 31/Aug/12: US$17.6 billion • Total workforce: 5,303 (57.5% unionised employees and 42.5% contract

  6. Slide 6: Our business model and the disciplined execution of our strategy

    Our business model and the disciplined execution of our strategy seek to create shareholder value across precious metal prices 1 Maximise the potential of existing operations • Operate at 100% capacity • Low-cost producer 2 • Optimise mining method and Deliver growth through metallurgy to maintain h

  7. Slide 7: H1 2012 Operational Highlights

    H1 2012 Operational Highlights • Record attributable gold production of 248,795oz, up 20.5% • Gold production profile strengthened due to the start-up of Noche Buena • Silver production, including Silverstream, decreased by 6.5% as a result of the expected lower ore grade at Fresnillo • On track to

  8. Slide 8: H1 2012 Financial Highlights

    H1 2012 Financial Highlights Profit and Loss: • Average realised silver price US$30.97 per oz, down 13.3% • Average realised gold price US$1,645.50 per oz, up 12.5% • Adjusted Revenue of US$1,141.7m, up 2.5% • Gross Profit of US$705.4m, down 8.9% • EBITDA decreased by 9.2% to US$684.4m with strong E

  9. Slide 9: H1 2012 Financial Highlights

    H1 2012 Financial Highlights Cash Flow: • Cash generated by operations before changes in working capital US$715.8 million • US$140.5 million capital invested in exploration (including US$36.5 million which were capitalised) • US$239.6 million invested in CAPEX • US$312.6 million paid in dividends •

  10. Slide 10: Operations Review – Fresnillo District

    Operations Review – Fresnillo District FRESNILLO SAUCITO H1 2012 H1 2011 Change % H1 2012 H1 2011 Change % Attributable production Silver m oz 13.4 16.9 -3.5 -20.7 3.2 1.9 1.3 68.1 Gold k oz 15.9 12.5 3.4 27.2 21.7 9.1 12.6 137.9 Lead kt 8.7 6.7 2.0 29.1 1.1 0.6 0.6 105.0 Zinc kt 8.3 6.6 1.7 26.3 0.

  11. Slide 11: Operations Review – Ciénega District

    Operations Review – Ciénega District CIÉNEGA H1 2012 H1 2011 Change % Attributable production Gold k oz 65.3 53.4 12.0 22.4 Silver m oz 1.2 0.6 0.6 106.6 1 Adjusted Revenue Adj Revenue US$ m 148.4 108.0 40.4 37.5 Contribution % 13.0 9.7 Costs Cost per tonne US$/t 74.1 70.1 4.1 5.8 Cost per AU oz US$

  12. Slide 12: Operations Review – Herradura District

    Operations Review – Herradura District HERRADURA SOLEDAD-DIPOLOS NOCHE BUENA H1 2012 H1 2011 Change % H1 2012 H1 2011 Change % H1 2012 H1 2011 Attributable production Gold k oz 94.4 88.2 6.2 7.0 38.9 43.3 -4.4 -10.2 12.6 0.0 Adjusted Revenue 1 Adj Revenue US$ m 278.8 231.6 47.1 20.3 113.8 111.4 2.4

  13. Slide 13: Exploration update

    Exploration update Fresnillo District: • 60moz resource identified deep near Total revised exploration budget for 2012: US$338 m San Carlos shaft • New vein drilled south of mine area Budget Herradura District allocation • Drilling continued at Centauro pit with good intersections to over 1400 m bel

  14. Slide 14: Estimated project delivery programme

    Estimated project delivery programme On track to produce 65moz of silver and 500,000 oz of gold by 2018 09/11/2012 14

  15. Slide 15: On track to produce 65 million ounces of silver and over 500,000 ounces of gold by 2018

    On track to produce 65 million ounces of silver and over 500,000 ounces of gold by 2018 SILVER GOLD MOz KOz 65 MOz 500 KOz Saucito I (ramp-up) Dynamic leaching plant Saucito II Noche Buena (ramp-up San Julián and expansion) Juanicipio San Julián Expansion at Fresnillo Centauro Deep …and to support t

  16. Slide 16: Conclusion and Outlook

    Conclusion and Outlook • Amidst the uncertain global economic climate, Fresnillo delivered on all fronts as expected • Cost inflation was controlled, strong EBITDA margins maintained, and Fresnillo remains a lowest quartile cash cost precious metals producer • We remain committed to delivering on th

  17. Slide 17: Conclusion and Outlook

    Conclusion and Outlook We will continue to build upon our competitive differentiators: Operational excellence World class assets Experienced personnel, efficient mining We operate the largest primary silver mine in methods, continuous reserve replenishment the world and control the largest area of a

Fresnillo — Denver Gold Forum 2012 on 6ix