  1. Slide 1: Sikacrete 321 FS Application Instructions

    Construction Sikacrete 321 FS Application Instructions Sika Corporation

  2. Slide 2: Sikacrete 321 FS product description

    Construction Sikacrete 321 FS  One-component.  Fast setting concrete mix.  Portland –cement concrete containing factory blended coarse aggregate designed for quick turnaround patching and overlay needs. Sika Corporation

  3. Slide 3: Where to use

    Construction Sikacrete 321 FS  Where to use: • On grade, above, and below grade on concrete. • On horizontal, vertical and overhead surfaces when formed and pumped or poured. • Full depth repairs. • Filler for voids and cavities. • As a structural repair material for: – Parking facilities – Industr

  4. Slide 4: Packaging and coverage

    Construction Sikacrete 321 FS  Packaging: • 65 lb. multi-wall bag.  Coverage: • .50 cu. ft / unit. • 864 cu. inches per unit. Sika Corporation

  5. Slide 5: Surface Preparation: Cementitious Substrates

    Construction Surface Preparation  Cementitious Substrates: • Should be clean and sound. • Remove contaminants and bond inhibiting materials from repaired area. • Obtain exposed/fractured aggregate surface ~1.0 to 1/8 inch profile (ICRI CSP 7 & above). • Substrate must be saturated surface dry (SSD)

  6. Slide 6: Surface Preparation

    Construction Surface Preparation  Cementitious Substrates: • Surface should be cleaned and roughened to create a profile. Sika Corporation

  7. Slide 7: Surface Preparation: Saw Cut

    Construction Surface Preparation  Saw cut around perimeter of repair area to achieve a minimum 3/8” shoulder.  Eliminates feathered edges giving a clean repair transition Sika Corporation

  8. Slide 8: Surface Preparation: Steel

    Construction Surface Preparation  Steel: • Remove all corrosion and contaminants from exposed steel. • Surface should be cleaned thoroughly by blast cleaning or other mechanical means. • Exposed steel should be cleaned to white steel. • If half of the diameter is exposed, chip behind bar, 3/4” mini

  9. Slide 9: Steel Preparation

    Construction Steel Preparation  Steel should be cleaned to a bright metal finish. Sika Corporation

  10. Slide 10: Tools Required

    Construction Tools Required  ½” Drill Motor  Low speed drill 400-600 rpm  Large mixing paddle  Margin trowel Sika Corporation

  11. Slide 11: Mixing

    Construction Mixing  Pour water into clean pail.  Adjust water to achieve the required flow. Do not add more than 5 pints of water. Sika Corporation

  12. Slide 12: Mixing

    Construction Mixing  Add Sikacrete 321 FS to pail with water already inside, while mixing continuously. Sika Corporation

  13. Slide 13: Mixing

    Construction Mixing 1. Slowly add powder. 2. Once all the powder is added mix for 3 minutes. 3. Do not add any more than the recommended liquid. Sika Corporation

  14. Slide 14: Mixing

    Construction Mixing 1. While mixing for 3 minutes stop at 1.5 min to scrape down the sides to insure all material is fully mixed. 2. Thorough mixing and proper proportioning is necessary. Sika Corporation

  15. Slide 15: Application: Scrub Coat

    Construction Sikacrete 321 FS - Application  SSD the surface and scrub coat the repair concerte into the substrate filling all pores and voids. Sika Corporation

  16. Slide 16: Application

    Construction Sikacrete 321 FS + Application  Apply Sikacrete 321 to the prepared area.  Press concrete behind rebar and make sure the material is consolidated and compacted fully. Sika Corporation

  17. Slide 17: Application

    Construction Sikacrete 321 FS + Application  Complete filling patch area.  Work concrete from the center of the patch to the outside. Sika Corporation

  18. Slide 18: Min / Max application thickness

    Construction Min / Max application thickness  Thickness • Min 1.0 inch • Max 8.0 inch Sika Corporation

  19. Slide 19: Finish

    Construction Sikacrete 321 FS Finish  Ensure good intimate contact with the substrate is achieved.  Materials should be scrubbed into the substrate or other suitable means should be employed such as vibration of the materials.  Vibrate form while pouring.  Finished as desired. Sika Corporation

  20. Slide 20: Curing

    Construction Sikacrete 321 FS Curing  Cure as per ACI recommendations. Curing is required.  Moist cure with wet burlap and polyethylene, a fine mist of water or water based curing compound  Moist curing should commence immediately after finishing.  Protect newly applied material from direct sun