  1. Slide 1: Investor and Analyst Day

    Investor and Analyst Day November 23, 2016

  2. Slide 2: Agenda

    Agenda – November 23, 2016 1:15 pm INTRODUCTIONS 1:30 pm OPERATIONS 3:00 pm EXPLORATION 3:30 pm QUESTION PERIOD 4:15 pm COCKTAIL HOUR

  3. Slide 3: Cautionary Statement

    Cautionary Statement All information included in this presentation, including any information as to the Company’s future financial or operating performance, and other statements that express management’s expectations or estimates of future performance, other than statements of historical fact, const

  4. Slide 4: CEO Perspective

    CEO Perspective – Steve Letwin

  5. Slide 5: Management Participants

    Management Participants OPERATIONS / EXPLORATION CORPORATE Operations Team Board of Directors Don Charter REGIONAL VPs Mahendra Naik Gilles Ferlatte – Americas Sybil Veenman Oumar Toguyeni – West Africa OPERATIONS – ESSAKANE, BURKINA FASO Bruno Lemelin – General Manager Executive Leadership Team Tid

  6. Slide 6: Performance Checklist

    Performance Checklist On track to meet 2016 production and cost guidance Achieve targeted ramp up schedule for Westwood mine Install secondary crusher at Rosebel Agreement to acquire Saramacca property in Suriname Get AGA / IAMGOLD board approvals for Sadiola Sulphides Start mining from Falagountou

  7. Slide 7: Potential Production Pipeline

    Potential Production Pipeline 1,200,000 1,000,000 800,000 600,000 400,000 200,000 0 2016 2017 2018 2019 2020 Essakane Rosebel Westwood Sadiola Oxide Sadiola Sulphide Potential Targeting AISC of $900-$950/oz by 2020 l TSX: IMG l NYSE: IAG l 7

  8. Slide 8: Financial Review

    Financial Review – Carol Banducci

  9. Slide 9: Financial Highlights

    Financial Highlights • Exceptionally strong balance sheet • Continuous improvement and disciplined financial management driving strong financial results • Q3/16 compared to Q3/15  Net earnings $17M, up $102M  Revenue $282M, up $75M; higher gold sales drove 42% of the increase  Operating costs dec

  10. Slide 10: Net Cash from Operating Activities

    Steady Growth in Operating Cash Flow in 2016 Net Cash from Operating Activities Average Realized Gold Price ($Millions) ($/oz) Average Realized Gold Price Operating Cash Flow The trend in operating cash flow is keeping pace with a rising gold price due to continued focus on cost management l TSX: IM

  11. Slide 11: Capitalization

    Well Capitalized Position (as at September 30, 2016) Capitalization $M Cash and cash equivalents (Excludes restricted cash) 627 Restricted Cash 123 Available Credit Facility1 168 LTD - senior unsecured notes 489 Shareholder’s Equity (incl. non-controlling interests) 2,270 Total Capitalization 2,759

  12. Slide 12: Total Liquidity

    Strongest Liquidity Amongst Intermediate Producers Intermediate Producers $900 $794 …with 80% cash & cash $167 equivalents $649 $600 Total Liquidity (US$ mm) $240 $437 $427 $150 $324 $627 $292 $300 $276 $200 $217 $150 $409 $74 $287 $151 $142 $143 $124 – IAMGOLD Eldorado Alamos New Gold B2 Gold Tahoe

  13. Slide 13: Industry Leading Leverage Multiples

    Industry Leading Leverage Multiples Senior Producers Intermediate Producers 2.5x 2.6x Yamana New Gold 2.1x 2.1x 2.0x 1.4x Goldcorp B2 Gold 1.7x 1.0x 2.1x 2.9x Barrick Eldorado 1.5x 0.9x 1.4x Kinross 1.5x Detour 0.8x 0.8x 1.7x 2.0x Newmont Alamos 0.7x 0.1x 1.3x 0.1x Agnico Tahoe 0.5x nmf 1.5x 1.5x IA

  14. Slide 14: Operational Overview

    Operational Overview – Gord Stothart

  15. Slide 15: Operations Organizational Structure

    Operations – Organizational Structure l TSX: IMG l NYSE: IAG l 15

  16. Slide 16: 2016 Outlook for Production & Costs

    2016 Outlook for Attributable Production & Costs Cumulative Attributable Production 900 Outlook • Near the high end of 2016 attributable production guidance Attributable Production (000 oz) 800 700 range of 770,000 to 800,000 oz 600 • Lowered 2016 total cash costs1 guidance range to $740 to 500 $770

  17. Slide 17: Geographically Diversified Asset Base

    Geographically Diversified Asset Base* NORTH AMERICA Westwood Côté Gold Monster Lake Nelligan CENTRAL AMERICA Eastern Borosi SOUTH AMERICA Rosebel Pitangui Americas – Gilles Ferlatte Gold Mine Development Project * Attributable basis. Advanced Exploration l TSX: IMG l NYSE: IAG l 17

  18. Slide 18: Westwood

    x< =) fe) <& oD —! — © > > Y Westwood

  19. Slide 19: Westwood Progression

    Westwood Progression 2017 • Production to 2016 double vs 2016 • Operational • High 2015 objectives expectations to largely achieved be met 2014 • Seismicity halts progress but • Significant • Commercial allows strategic progress 2008-2013 Production improvements towards ramp- up • Project • Implemen

  20. Slide 20: 2016 Successes

    2016 Successes • Key Health, Safety & Sustainability results better than budget • Production ahead of budget; on track for development target • Cost targets achieved • Success in resource conversion objectives • $50M investment from Investissements Québec • Sustainable cost reductions through negoti

  21. Slide 21: Westwood Development – Q3'16 Progress Update

    Westwood Development – Q3’16 Progress Update Key Performance Indicators YTD Target YTD Actual Variance No lost time DART Rate* 3.30 0.8 -75% incidents Safety or injuries TRIR+ 8.8 8.0 -9% Underground lateral development 16,684 16,899 1% Development (m) Underground vertical development 3,080 2,138 -3

  22. Slide 22: Development Update: Re-opening

    Development Update: 104 Re-opening  All by-pass drifts complete, all rehabilitation zones accessible  15 vehicles recovered (value of = $4.5 M CAD)  All damaged areas inspected by external consultant  Final rehabilitation and backfill sequences in progress  Analysis of mining sequence in progre

  23. Slide 23: Development Update: Rockbreaker/192 Loading

    Development Update: 180 Rockbreaker/192 Loading  Project Scope: › Loading 192 › Rockbreaker #1 & #2 on level 180 › Rockbreaker #3 on top of ramp on level 192 › Casing Orepass #1 between levels 180 and 192  Commissioning loading Q4 2016  Allows greater development capacity from 156 and 180 horizon

  24. Slide 24: Development Update: Rockbreaker/192 Loading

    Development Update: 180 Rockbreaker/192 Loading 180 Rockbreaker #2 Orepass Casing 192 Conveyor l TSX: IMG l NYSE: IAG l 24

  25. Slide 25: Development Update: Battery Scoops

    Development Update: Battery Scoops  Extensive testing program in place prior to selection › 2014: 1 prototype tested › 2016: 3 models tested (different suppliers) › Next test scheduled Q4 2016  Key selection criteria: › Charge life and recharge process › Reliability › Efficiency › Ease of operatio

  26. Slide 26: Westwood Strategy Overview

    Westwood Strategy Overview 2017 2020 5 Year • Full, sustainable production; Vision • Advance strategic plan and maximum profitability • Ramp-up Complete priority projects for each of the four pillars of the vision • Infrastructure development for Mining Blocks 3 and 4 • Construction of Block 5-6 • C

  27. Slide 27: 2017 Strategic Priorities

    2017 Strategic Priorities Labour Sustainability Resources Operations • Rigorous and • Continue • Resource • Develop proactive labour deposition plan conversion communications management for waste and • Revise mining network strategy • Reinforcement of tailings strategy for new and plans H&S culture,

  28. Slide 28: 2017 Production Plan Summary

    2017 Production Plan Summary  Production from Blocks 1 and 2  Reopening of 104 mining area  Infrastructure and development in blocks 3 and 4  Diamond drilling begins below 180-level (Blocks 5-6) l TSX: IMG l NYSE: IAG l 28

  29. Slide 29: Westwood Potential

    Westwood Potential  Westwood has significant resource potential undrilled in existing mining blocks, at depth and to the west  Development completed in 2016 and scheduled for 2017 is essential to Westwood ramp-up and expansion plans › Diamond drilling rate increases in 2017 with available infrastr

  30. Slide 30: Rosebel

    § % ae 2 ace >< — ye ‘ oe be a ae | ~ stage ue a $ we x soon ENG x hese Rosebel Suresh Kalathil

  31. Slide 31: Operations Layout

    Operations Layout l TSX: IMG l NYSE: IAG l 31

  32. Slide 32: Foundation of Rosebel Strategy

    Foundation of Rosebel Strategy Business Objectives Achieving excellence through Operations & Improvement initiatives Improving operating efficiency and reducing unit operating costs through optimization of key value Life of Mine (LOM) Plan drivers: Cost Optimization Zero Harm (HSE) Improvement Produ

  33. Slide 33: DART & TRIR 2016 YTD

    DART & TRIR 2016 YTD 1.60 1.42 1.40 1.20 1.00 0.79 0.80 0.75 0.60 0.60 0.44 0.46 0.40 0.39 0.29 0.20 0.00 0.00 Q1 Q2 Q3 Q4 DART Rate TRI Rate DART Target TRIR Target l TSX: IMG l NYSE: IAG l 33

  34. Slide 34: Objectives

    Objectives  Focusing on ZERO HARM, empowering people, operational excellence and building on stakeholder relations to maximize operating margin  Transitioning from Continuous Improvement to Sustainable Business Excellence  Step-Change Innovation – Significant departure from business-as-usual proc

  35. Slide 35: Strategic Imperatives and Outcomes

    Strategic Imperatives and Outcomes Strategic Imperatives Outcome 1. Engineered Stockpile 1. Stable process parameters and plant performance 2. Reverse Circulation Drilling 2. Reduce per unit operating costs 3. Mill Optimization initiatives 3. Reduce grade variation and increase confidence a. Solutio

  36. Slide 36: Disciplined Approach

    Disciplined Approach  Focus on economic returns • Return on capital is the main criteria for investment decisions  Cost containment • Focus on managing costs in the current gold price environment  Innovation • Apply innovation where possible to generate superior return  Positioning for the futur

  37. Slide 37: Priorities

    Priorities  Mine operations optimization  Mill throughput model optimization  Grade control  Covert to 8 meter benches, rather than 5/6meter  Six Sigma implementation  Workforce and community engagement  Exploration → Near Mine: Saddles, East Roma → Regional Exploration: Saramacca, Sarafina,

  38. Slide 38: 2017 Key Opportunities

    2017 Key Opportunities Mill Operations strategy to reduce Cyanide & Grinding Media consumption Production Cost Drilling & Blasting accuracy and productivity optimization $/Tonne Mined Loading & Hauling efficiency and Cost optimization OPEX Enhanced Business Parts management Intelligence (BI) Systems

  39. Slide 39: Operating Cost Trend

    Operating Cost Trend 350.0 7 300.0 273 278 6 252 252 243 250.0 227 5 $/Tn milled or mined 200.0 4 150.0 3 $M 100.0 2 50.0 1 - 0 2011A 2012A 2013A 2014A 2015A 2016F G&A Cost 32.3 36.1 41.3 31.7 29.9 25.2 Power Cost 35.9 39.1 22.8 32.9 24.7 26.5 Milling Cost 51.2 55.2 65.3 64.4 60.8 58.9 Mining Cost 1

  40. Slide 40: Continued Reduction of Mine Costs

    Continued Reduction of Mine Costs: 15% below 2013/2014 Continued reduction in mining costs by approx. $0.28/t Almost $0.20/t of reduction due to lower fuel costs Partly offset by +$0.15/t due to RC Drilling $0.23/t improvement due to productivity initiatives l TSX: IMG l NYSE: IAG l 40

  41. Slide 41: Capital Costs

    Capital Costs 160.0 Milestone 1 – Milestone 3 – Milestone 4 – 2012/2013: Solar plant and TSF 2014/2015: Ball Mill 3: $47M expansion 8 777 HTs, 2 6030 LU’s 140.0 6 MD6290 Drills, 6 D9’s 120.0 Milestone 5 – Secondary 100.0 crusher: $14M 80.0 60.0 40.0 Milestone 2 – 2012/2013: 20.0 18 785 HTs, 3 6030 L

  42. Slide 42: Drilling & Loading Performance

    Drilling & Loading Performance (2015-2016 YTD) 22 Drill Productivities (EHM/NOH) 21 • 5.3% improvement in drill productivities compared 20 to same period of 2015 19 21.3 20.7 • Proper pattern sequencing and equipment 20.2 20.1 20.0 19.9 19.7 19.7 18 19.5 19.3 19.2 19.1 19.1 19.0 scheduling resulted

  43. Slide 43: Blasting Performance

    Blasting Performance (2015-2016 TYD) Tonnes Blasted 70 x 100000 60 • Total tonnes blasted is 8.6% above the budget 2016 50 40 • Optimization of Drill & Blast designs to obtain higher 65 30 yield/meter without compromising post blast results 53 53 53 51 48 47 46 45 45 44 44 43 43 41 20 › Drill patter

  44. Slide 44: Drilling & Blasting Cost

    Drilling & Blasting Cost (2015-2016 YTD) $0.40 Total Blasting Cost ($/T) • 32% reduction in average blasting cost ($/T) compared to the $0.35 budget. $ 3.78M variance compared to budget even after blasting additional 8.6% $0.30 $0.25 • Trials are planned to further control costs $0.37 $0.20 $0.36 ›

  45. Slide 45: Loading & Hauling

    Loading & Hauling (2015-2016 YTD) $0.14 Loading ($/Tonnes Moved) $0.12 • 20% reduction in average loading cost compared to same period in 2015 $0.10 $0.08 • Major contributors include: $0.13 › ~7% higher loading unit productivities compared $0.12 $0.11 $0.11 $0.06 $0.11 $0.10 to same period in 2015

  46. Slide 46: Cost Optimization

    Cost Optimization Avg. Tire hours 2012 - 2016 YTD 6,000 5,408  Cost reductions across Tire life (hours) 4,639 4,749 5,000 4,239 operations, including: 4,137 3,759 3,520 3,756 4,000 3,167 3,000  Tire life 2,000 2012 2013 2014 2015 2016  Powder factor 777 3,167 3,759 3,520 3,756 4,137 785 4,639 4,2

  47. Slide 47: Gold from Hard Rock: 2013 to Present

    Gold from Hard Rock: 2013 to Present  Negative variance between mill and mine became pronounced in Q3 2013  Stabilization in H2 2014  May 2015 (ROM stockpile & increased BMM usage) = improvement & stabilization l TSX: IMG l NYSE: IAG l 47

  48. Slide 48: Dilution Management Methodologies

    Dilution Management Methodologies BMM + Standup blast  Blast design and requirements are Segregation decided by size and shape of ore packets › Uniform movement along the strike › Reduce movement in ore shoots › Segregation of ore from Waste Ore  Irregular shape ore bodies using blast movement mon

  49. Slide 49: Workforce Rationalization

    Workforce Rationalization 1,400 80.0 1,200 70.0 63.5 63.6 61.4 61.8 Number of Employees 57.2 Tonnes mined (M) 53.1 60.0 1,000 990 973 983 937 50.0 800 825 40.0 696 600 492 487 459 460 449 30.0 426 400 20.0 200 10.0 74 74 65 70 50 43 0 - 2011A 2012A 2013A 2014A 2015A 2016A Sept Hourly Staff Expat Ton

  50. Slide 50: Productivity Per Employee (Tonnes Mined)

    Productivity Per Employee (Tonnes Mined) Tonnes Mined per Man-hour 70 16.0 60 14.0 13.2 13.5 12.4 12.0 50 11.5 10.5 PER MAN/HOUR TONNES MINED 10.2 10.2 TONNES MINED 10.0 (MILLIONS) 40 8.0 30 61 63 64 57 52 53 6.0 47 20 4.0 10 2.0 0 0.0 2010 2011 2012 2013 2014 2015 2016 (sept) 2010 2011 2012 2013 20

  51. Slide 51: Productivity Per Employee (Tonnes Milled)

    Productivity Per Employee (Tonnes Milled) Tonnes Milled per Man-hour 14 2.8 12 2.7 2.7 10 2.6 PER MAN/HOUR TONNES MILLED TONNES MILLED 2.5 (MILLIONS) 8 2.5 2.5 2.5 13 13 12 13 6 12 12 2.4 2.4 2.4 9 4 2.3 2.3 2 2.2 0 2.1 2010 2011 2012 2013 2014 2015 2016 (sept) YEARS Total Tonnes Milled Tonnes Mille

  52. Slide 52: Grinding Circuit Milestones

    Grinding Circuit Milestones Sept 2015 January 2016 March 2016 April 2016 May 2016 Nov 2016 Dec 1, 2016 • SAG – complete • Project • Powerflex • SAG – change to • SAG Liners – • Commissioning • 7’ Secondary orders to replace engineering Drive 140mm media 30 row liners complete Crusher current media w

  53. Slide 53: 2017 Mill Optimization (Phase 1)

    2017 Mill Optimization (Phase 1)  Base case - 1SAG + 3BM LCI Drive  6.9Mtpa at 90% Hard Rock  PowerFlex – Increased torque = +5% HR  7.5Mtpa at 90% Hard Rock – March 2016  30 row SAG shell liner installation = +5%  8.0Mtpa at 90% Hard Rock – May 2016  Secondary Crusher installation = +10%  9

  54. Slide 54: Secondary Crusher – Current Status

    Secondary Crusher – Current Status December 2016 * 2017 in service TRANSFER TOWER / CRUSHER  Ahead of schedule and on cost  Crusher was handed over to operations in mid-November and roles and responsibilities were established for a smooth handover l TSX: IMG l NYSE: IAG l 54

  55. Slide 55: 2017 Mill Optimization (Phase 2)

    2017 Mill Optimization (Phase 2) SECOND STAGE PEBBLE CRUSHING January 2018 – 2nd pebble crusher installed Phase 2  Pebble crusher optimization to be determined following operation with phase Pebble Crush #1 CV6 1 complete  Maintain current installation  Increase capacity with single stage CV4 cru

  56. Slide 56: 2017 Mill Optimization (Phase 3)

    2017 Mill Optimization (Phase 3) TERTIARY GRINDING June 2018 Phase 3 Ball Mill 1  Convert secondary grinding to include tertiary grinding  SAG discharge to Ball Mill 3  Ball Mill 3 to Ball Mills 1 & 2 Trash Screen Ball Mill 2 SAG CV3 Thickener Ball Mill 3 l TSX: IMG l NYSE: IAG l 56

  57. Slide 57: Comminution Optimization Phases 1, 2 & 3

    Comminution Optimization – Phase 1, 2 & 3 POTENTIAL GAINS  20 % increase in hard rock capacity – 9Mtpa at 90% HR vs 7.5Mtpa  >5% reduction in media consumption  >5% reduction in cyanide consumption  = reduced unit costs  = reduced unit power consumption  = increased gold production l TSX: IMG

  58. Slide 58: 2016 Achievements

    2016 Achievements  94% overall plant availability  94% recovery → Cyanide addition strategy and feed management being main contributors  Costs → Mill has seen significant forecast cost reductions for 2016 including  Grinding media – $2M – continued focus on expert system optimization and seconda

  59. Slide 59: Exploration Pipeline

    Exploration Pipeline RGM exploration Concession RGM Option Agreement Gross Rosebel Exploitation Concession Near mine exploration – Several exploration targets in and around Overman – Existing inferred resource of 8.2 current pits. Drilling ongoing and Mt @ 1.0g/t Au – 276koz (December 2015 planned i

  60. Slide 60: Gross Rosebel: Near Pit Exploration - North Trend

    Gross Rosebel: Near Pit Exploration - North Trend North trend Koolhoven J-Zone West Apex area Exploration target direct and indirect ounces P1 J-Zone East West Pay Caro Pay Caro 1km 2 Moz Au mined to date East Pay Caro Caution: All exploration targets are East Pay Caro saddle: conceptual in nature E

  61. Slide 61: Gross Rosebel: Near Pit Exploration - South Trend

    Gross Rosebel: Near Pit Exploration - South Trend South trend Royal Hill: Exploration target Roma: Exploration target P2 P2 Advanced Project Caution: All exploration targets are conceptual in nature Inactive Pit Pit in production Rosebel in-pit exploration and extensions: Exploration Target Saddle P

  62. Slide 62: Near Pit Exploration – Royal Hill Cross Section

    Near Pit Exploration – Royal Hill Cross Section Looking East Existing pit Royal Hill NW Royal Hill SE Final pit Existing pit Final pit Saddle targets and extensions target: P2 Testing potential at depth in the saddle between the NW & SE pits; does the mineralization link-up? 400m Caution: All explor

  63. Slide 63: Near Pit Exploration – Roma Pits

    Near Pit Exploration – Roma Pits Current drilling Recent drilling Roma West Pit Roma East Pit design Roma: Exploration target P2 South trend 1km Caution: All exploration targets are conceptual in nature l TSX: IMG l NYSE: IAG l 63

  64. Slide 64: Côté Gold

    Cdoté Gold Gilles Ferlatte

  65. Slide 65: Regional Infrastructure

    Regional Infrastructure  Highway 144 • Conceptual pit is 6 km off all weather highway  Mining Centres • Timmins 144km • Sudbury 175km  Canadian National Railway • In Gogama 25km • Existing rail siding  115kV power from Shining Tree sub- station • Tap Line 44km • Could supply 70MW from the north

  66. Slide 66: Regional Geology

    Regional Geology Timmins West 139,000 oz (2015) Bell Creek – 39,700 oz (2015) Alamos Gold Young-Davidson Mine 160,353 Oz in 2015, Est 170,000- 180,000 Oz in 2016 15 years mine life Goldcorp Projects Juby (Tahoe Resources) 122.8Mt @1.017 g/t (4 m Oz.) Borden (GoldCorp) - Young-Davidson 8.87 Mt @ 6.0

  67. Slide 67: Resource Drilling

    Resource Drilling 50 x 50m hole spacing 25 x 25m hole spacing l TSX: IMG l NYSE: IAG l 67

  68. Slide 68: Côté Gold – Evolved Resource Estimate

    Côté Gold – Evolved Resource Estimate* Quantity Grade Au Metal Quantity Grade Au Metal (Mt) (g/t Au) (Koz) (Mt) (g/t Au) (Koz) Trelawney 35.0 0.82 930 204 0.91 5,940 IMG 289.2 0.90 8,354 66.9 0.60 1,174 Since IAMGOLD’s acquisition in 2012:  Indicated resources have increased by ~7.4Moz  Average gr

  69. Slide 69: Grade-Tonnage Curve

    Grade – Tonnage Curve 289Mt @ 0.9 g/t Au (8.4Moz) 190Mt @ 1.14 g/t Au (7.0Moz) Resource not very sensitive to cut-off grade l TSX: IMG l NYSE: IAG l 69

  70. Slide 70: Environmental Studies On-going

    Environmental Studies On-going  Currently awaiting a provincial Environmental Assessment Decision by the end of 2016  The Federal Minister of the Environment & Climate Change stated in May 2016 that the project is not likely to cause signifiant adverse environmental effects  AMEC Foster Wheeler h

  71. Slide 71: Modifications to Plan Underway

    Modifications to Plan Underway Main differences under consideration:  TMF location and disposal approach  Watercourse realignments  Removed tailings pipeline 7.9km  Relocated camp to facilitate emergency access while minimizing operating traffic congestion  Increased stockpile from 7mt to 30mt

  72. Slide 72: Community Relations

    Community Relations • IAMGOLD has actively engaged local and regional communities, as well as other stakeholders, to gain a better understanding of their issues and interests, identify potential partnerships and to ultimately secure social licence to operate • The range of stakeholders is expected t

  73. Slide 73: Aboriginal Communications

    Aboriginal Communications • Based on federal and provincial advice and information gathered through engagement activities, the following groups have been consulted about the project: Algonquin Anishinabeg Nation Tribal Council Chapleau Ojibwe First Nation Brunswick House First Nation Abitibiwinni Fi

  74. Slide 74: Conclusions

    Conclusions  Regional Infrastructure – highway access, power, railway siding & proximity to major mining centres reduces working capital  Labour - lower due to CAD$ against USD$ & manpower readily available as regional mines reach end of mine life  Geology – large intrusion-hosted deposit  Geote

  75. Slide 75: Geographically Diversified Asset Base

    Geographically Diversified Asset Base * WEST AFRICA Essakane Sadiola Boto Gold Siribaya West Africa – Oumar Toguyeni Gold Mine Development Project * Attributable basis. Advanced Exploration l TSX: IMG l NYSE: IAG l 75

  76. Slide 76: Essakane

    Essakane Bruno Lemelin

  77. Slide 77: Continuous Improvement – Guiding Principles

    Continuous Improvement – Guiding Principles  To further increase free cash flow generation and extend the LOM, Essakane has set a strech target of +400 000 ounces at an AISC of $850/oz  Each initiative must: › Contribute to cost efficiently debottlenecking the entire value chain › Not have a negat

  78. Slide 78: Major Achievements for 2016

    Major Achievements for 2016  YTD DART of 0.10 vs 0.16 in 2015 (YTD Oct)  Launch of the ‘+400,000 oz at AISC $850/oz’ initiative  Falagountou East technical-economical analysis submitted to Ministry of Mines  Renewed partnerships with newly elected officials  Gold production above budget by 9,25

  79. Slide 79: Life-of-Mine: 400k + Strategy Recovery

    Life-of-Mine: 400k + Strategy Recovery Current Status 2017 2018+ 90.07% Recovery 90.68%+ Recovery 90.88%+ Recovery By pass leach tank to Transform leach tanks reduce graphite Oxygen addition to CIL to CIL negative impact Impact of TTP water Increase elution return (preg robbing) recovery and mitigat

  80. Slide 80: Intensive Leach Reactor Plant Project

    Intensive Leach Reactor Plant Project  Operations Results › Gold recovery from gravity concentrates 1.2 1.0 • 75-80% using shaking tables 0.8 • 99.3% on average with ILR - systematically Arsenic (%) above 98.5% 0.6 › Arsenic content in gold bars 0.4 • Well below the limit of 0.5% when ILR is used 0

  81. Slide 81: Intensive Leach Reactor Project

    Intensive Leach Reactor Project VUE ISOMÉTRIQUE ARRIÈRE ECH 1:100 DESSIN RÉFÉRENCE N/A PROJET/SECTEUR / TYPE / DESCRIPTION DESSINÉ PAR ÉCHELLE NO. PROJET DISCIPLINE REV. DATE DESCRIPTION PAR APP. DONALD GNANOU INDIQUÉE P0345 ACHITECTURE 0 2016-01-07 ÉMIS POUR CONSTRUCTION DG ML INTENSIVE LEACH REACT

  82. Slide 82: Carbon Fines Recovery and Treatment

    Carbon Fines Recovery and Treatment  Operation Results 100% Leached Ash Gold › Carbon mass reduction in the incinerator 90% Recovery (%) • Average reduction is 82% 80% • Values over 90% were obtained; tests are 70% ongoing to increase the mass reduction › Recovery of the leached ash : 60% • Average

  83. Slide 83: Fine Carbon Treatment System

    Fine Carbon Treatment System l TSX: IMG l NYSE: IAG l 83

  84. Slide 84: Reconciliation Factors Summary

    Reconciliation Factors Summary Final 2015 Reconciliation  Better YTD 2016 F1 & F3 Factors (grade & ounces) compared to 2015 due to: Changes in the interpolation parameters of grade control model Density adjustments YTD Sept. 2016 Reconciliation Improvements to grade control practices l TSX: IMG l N

  85. Slide 85: Growth Option – Heap Leach

    Growth Option – Heap Leach  Why Heap Leaching at Essakane ? • Provide additional ounces at low CAPEX • Essakane contains significant non-economic low grade (COG are 0.60 g/t) • Possibility to extend the LOM (New Whittle assumption) • May decrease pressure on crusher and mill (OPEX) → Must test the

  86. Slide 86: Heap Leach Test Project Timeline

    Heap Leach Test Project Timeline 2016 - Pursue lab testwork & initiate scoping study 2017 - Start small-scale pilot test of 2,500 t if positive results returned 2018 - Start large scale pilot test for 1.5 Mt if positive results continue. › Pilot test would generate cash flow to finance further studi

  87. Slide 87: Growth Option – Falagountou East

    Growth Option – Falagountou East  Falagountou East has significant potential to host low-cost, near-surface, high-grade saprolite ore  New drilling program is expected to provide additional short-term saprolite and transition resources  The immediate north extension is actively mined by the local

  88. Slide 88: Falagountou East – Final Footprint

    Falagountou East – Final Footprint l TSX: IMG l NYSE: IAG l 88

  89. Slide 89: Drilling Projects

    Drilling Projects EMZ Deep Drilling Essakane 3 EMZ South 2 Falagountou East 1 2017 drilling projects in soil anomalies and structural trends l TSX: IMG l NYSE: IAG l 89

  90. Slide 90: Sadiola

    Sadiola Oumar Toguyeni

  91. Slide 91: Sadiola- Mali (41%)

    Sadiola- Mali (41%) Sadiola’s Historical Gold Production1 700,000 600,000 500,000 400,000 300,000 200,000 100,000 0 1997 1998 1999 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 1 On a 100% basis. l TSX: IMG l NYSE: IAG l 91

  92. Slide 92: Sadiola Sulphide Expansion Project

    Sadiola Sulphide Expansion Project Project Highlights  Intend to move ahead by year-end conditional upon partner AngloGold Ashanti’s decision to proceed and renewal of construction and operating permits, power agreement and fiscal terms relating to the project  Currently refining project economics

  93. Slide 93: Sadiola Sulphide Expansion Project – Economic Assumptions

    Sadiola Sulphide Expansion Project – Economic Assumptions 1 Main Economics Parameters for Pit Optimization Gold price (P) US$/oz 1,200 Tax and Royalty Assumptions: Long term oil price US$/bbl 75 Site diesel price US$/litre 0.83  30% as per the mining convention between SEMOS Tax and the Government

  94. Slide 94: Exploration Review

    Exploration Review

  95. Slide 95: Exploration Department

    IAMGOLD CORPORATION EXPLORATION DEPARTMENT Senior Vice President, Exploration Craig MacDougall Exploration Administrator Rose Valle-Mena GLOBAL EXPLORATION CORPORATE General Manager Director Exploration Canadian Shield & Chief Geologist Brownfields Exploration New Opportunities Exploration Manager E

  96. Slide 96: Exploration Vision and Mandate

    Exploration Vision and Mandate Brownfields  Discover satellite deposits and deposit extensions to enhance and extend existing operations (Essakane, Rosebel, Sadiola – Oxide) Greenfields  Discover or acquire undeveloped gold deposits capable of producing +100koz of gold (or gold equivalent) per yea

  97. Slide 97: IAMGOLD Resources: M&I and Inferred

    IAMGOLD Resources: M&I (excl. 2P Reserves) and Inferred M&I resources have increased by 11.2 Moz since 2012 25,000 20,000 6,733 6,299 7,018 15,000 10,000 10,990 15,793 13,281 12,804 5,000 4,600 0 2012* 2013 2014 2015 M+I (excl) Inf. 2012*: reflects Côté Gold as at acquisition June 2012 Source: IMG R

  98. Slide 98: Development & Resource Projects >0.5 Moz

    Development & Resource Projects >0.5 Moz North America, South America, West Africa, & Europe (n = 359) 20 Westwood Brucejack 11 g/t Au Exploration Yaramoko 10 Monster >12 g/t Au IMG Mineral Ellipse Resources = 75% of deposits Exploration 5 M+I Resources: 23.5Moz Major axis = 1.1 g/t Au@ 1.2 g/t Au M

  99. Slide 99: Americas

    Americas

  100. Slide 100: Saramacca, Suriname - Option Agreement

    Saramacca, Suriname - Option Agreement  Initial Cash Payment USD$200,000 on signing • Provides access to the property  Staged Purchase Totaling USD$10 million and 3.125 million IAMGOLD shares • Held in escrow and released over 3 x 1 year intervals • Price Adjustment based on gold oz above 1.0 Moz

  101. Slide 101: Saramacca Prospect – Small Scale Mining

    Saramacca Prospect – Small Scale Mining Small scale mining appears to be limited l TSX: IMG l NYSE: IAG l 101

  102. Slide 102: Historical Drilling – Selected Results

    Historical Drilling – Selected Results on Auger Geochem Note: Historical results have not been verified and should not be relied upon GMDH-061 22.0m at 10.71 Au g/t GMDH-038 13.50m at 4.72 Au g/t 5.50m at 8.20 Au g/t 9.00m at 0.90 Au g/t GMDH-013 12.02m at 6.52 Au g/t 24.00m at 1.46 Au g/t GMDH-039

  103. Slide 103: Exploration Plan

    Exploration Plan  Data Package  Environment  Geophysics and geochemistry  Base line soil sampling of artisanal pits reprocessed and interpreted commenced prior to drilling  3D deposit models created  Base line water sampling commenced prior to  Additional targets identified drilling  Drillin

  104. Slide 104: Planned Drilling 2016

    Planned Drilling 2016 Historical Drilling 90 diamond drill holes (9,000m) 2016 Planned Drilling 54 DDH - infill holes (9,000 m) 77 RC - Exploration (9,000 m) Footwall, hanging wall and geochemical footprint RC drill pattern Historical Geochemistry Au ppm 100m x 50m diamond drill pattern l TSX: IMG l

  105. Slide 105: Saramacca Cross Section – 500NW

    Saramacca Cross Section – 500NW planned GMDH-036 planned 12.00m at 7.54 Au g/t 12.00m at 8.22 Au g/t 11.65m at 0.69 g/t 16.97m at 2.66 Au g/t planned 21.53m at 0.89 Au g/t Saprolite = ~100m thick 500NW Caution: Drill holes and assay results are previous explorers and cannot be considered NI43-101 co

  106. Slide 106: Breccia – Qtz Stockwork – Assays Pending

    Breccia – Qtz Stockwork – Assays Pending l TSX: IMG l NYSE: IAG l 106

  107. Slide 107: Geophysics and Geochemistry

    Geophysics and Geochemistry Airborne Potassium Gold Geochemistry Tigri Tigri No Previous Drilling Anomaly M Anomaly M K-Anomaly 4km Gridded Au from DD and DA K anomaly SW of mineralized trend indicative of hydrothermal alteration l TSX: IMG l NYSE: IAG l 107

  108. Slide 108: Exploration Potential

    Exploration Potential Saramacca Deposit Poorly tested Parallel IP Trend l TSX: IMG l NYSE: IAG l 108

  109. Slide 109: Monster Lake - Quebec

    Monster Lake - Quebec l TSX: IMG l NYSE: IAG l 109

  110. Slide 110: Monster Lake - Quebec (Earn-in option with TomaGold)

    Monster Lake - Quebec (Earn-in option with TomaGold)  High-grade 325-Megane Zone extends at depth  High-grade intervals from historical exploration (25-30 g/t Au)  Completing geological and structural mapping and selected geochemical and geophysical surveys in advance of follow-up drill program e

  111. Slide 111: Monster Lake – Megane Zone – Drilling Highlights

    Monster Lake – 325 Megane Zone – Drilling Highlights - Historic & IAMGOLD ML-14-119 ML-14-117 Area of More Recent Drilling ML-12-57 M-25-11 101.2 g/t Au / 4.5m ML-16-171 ML-16-179 6.79 g/t Au / 0.42m 5.33 g/t Au / 2.35m ML-14-130 0.96 g/t Au / 3.78m M-13-99 ML-14-132 20.16 g/t Au / 1.21m ML-15-147 3

  112. Slide 112: Monster Lake – High Grade Gold Mineralization

    Monster Lake – High Grade Gold Mineralization 325-Megane Main Zone VG Shear zone hosted smokey grey to black quartz veining with coarse visible gold 11 2 l 112 l TSX: IMG l NYSE: IAG

  113. Slide 113: Monster Lake – Drill Targets

    Monster Lake – Drill Targets Megane1&2* 325-Megane West Shoot Annie* Erratix* 7.8 g/t / 4.5m 46.3 g/t Au / 9.2m 20.2 g/t Au / 1.2m 237.6 g/t Au / 5.7m 51.0 g/t Au / 2.9m -350m ? -350m ML-15-147 325 Ore Shoot – located in the ‘Main Shear Zone’ ML-14-110 13.65g/t Au over 3.26 t.w. including 46.17 g/t

  114. Slide 114: Nelligan - Quebec

    Nelligan - Quebec Before After l TSX: IMG l NYSE: IAG l 114

  115. Slide 115: Nelligan – Quebec (Earn-in option with Vanstar Mining)

    Nelligan – Quebec (Earn-in option with Vanstar Mining)  Located 15 km south of Monster Lake within a major deformation corridor with other Au showings  Interest prompted by new discovery - the Liam Zone  In 2016 announced new discovery north of Liam; 2017 drilling program to follow Total Field Ma

  116. Slide 116: Nelligan – Potential Targets

    Nelligan – Potential Targets New Discovery in North Sector  Underexplored area New Discovery – North Sector  Wide zone of alteration and mineralization Open  Open along strike and width to northern structural corridor (i.e. +1,000m)  2017 Objective – follow up on north sector that is open along

  117. Slide 117: Nelligan – Results of Drilling Program

    Nelligan – Results of Drilling Program 2.13g/t Au 3.20g/t Au/ 7.39m 17.97m 1.23g/t Au 1.30g/t Au 23.02m N / 27.8m 4.43g/t Au 10.34m LI-13-09: 2.1g/t Au/24.3m 0.74g/t Au 28.58m LI-14-17A (North Zone) 3.04g/t Au/8.40m LI-14-12: 1.64g/t Au/15.70m LI-14-17A (Dan Zone) 1.05g/t Au/33m 300m 117 l TSX: IMG

  118. Slide 118: Nelligan – Core Samples – Assay Highlights

    Nelligan – Core Samples – Assay Highlights LIAM ZONE Iron formation host rock Hole Li-14-21 - 2.34 g/t Au / 17.6m DAN ZONE Brecciated conglomerate with alteration Hole NE-14-25 - 9.58 g/t Au / 6.0m NORTH ZONE Quartz-carbonate alteration Hole NE-16-44 - 4.43 g/t Au / 10.3m 118 l TSX: IMG l NYSE: IAG

  119. Slide 119: Pitangui Gold Project - Brazil

    Pitangui Gold Project - Brazil l TSX: IMG l NYSE: IAG l 119

  120. Slide 120: Pitangui – Brazil (100% owned)

    Pitangui – Brazil (100% owned) Tonnes Grade Contained Ounces (000) (g/t) (000 Au)  180 square kilometre land package Measured & Indicated1 -- -- --  Located in the Iron Quadrangle, the Inferred1 4,252 5.0 679 second largest gold producing region in the country  Focused on São Sebastião deposit 

  121. Slide 121: Pitangui - São Sebastião Deposit

    Pitangui - São Sebastião Deposit Now drilling at 50m x 50-100m spacing 121 l TSX: IMG l NYSE: IAG l 121

  122. Slide 122: São Sebastião Deposit – Highlights Biquinho Zone

    São Sebastião Deposit – Highlights Biquino Zone Cross-section 15.85m@4.03g/t Au; including 7.38m@8.12g/t Au Gold mineralization hosted by multiple banded iron formation horizons l TSX: IMG l NYSE: IAG l 122

  123. Slide 123: São Sebastião Deposit – Geological Modelling

    São Sebastião Deposit – Geological Modelling Up-Plunge Mineralization: N Permits in place for 2017 drilling E Weathering Zone S Biquinho Zone Shallow-Dipping Mineralization Pimento Zone 3d Geological Model – NE View W l TSX: IMG l NYSE: IAG l 123

  124. Slide 124: São Sebastião Deposit, Biquinho Horizon

    São Sebastião Deposit, Biquinho Horizon 124 l TSX: IMG l NYSE: IAG l 124

  125. Slide 125: Eastern Borosi - Nicaragua

    Eastern Borosi - Nicaragua La Sorpresa Vein Guapinol Vein l TSX: IMG l NYSE: IAG l 125

  126. Slide 126: Eastern Borosi – Option Agreement with Calibre Mining

    Eastern Borosi – Nicaragua – (Option Agreement with Calibre Mining)  180 square kilometre land package  Region of several >2 million oz Au deposits  Property hosts >40 km of multiple gold/silver epithermal vein systems (historic resources)  2017 focused on expanding vein systems to resource stag

  127. Slide 127: Eastern Borosi Discoveries

    Eastern Borosi  10 discoveries  Targeting parallel-trending Guapinol and Vancouver veins and the Blag vein system  Assay results include: › East Dome target, including*: 16.5 m grading 2.27g/t Au and 127.9g/t Ag › Veta Loca target*: 6.3 m grading 10.15g/t Au and 6.9g/t Ag  Veta Loca is a new dis

  128. Slide 128: Eastern Borosi - Riscos de Oro Intercept

    Eastern Borosi - Riscos de Oro Intercept – Historic Mining Area Classic Epithermal Vein System l TSX: IMG l NYSE: IAG l 128

  129. Slide 129: Eastern Borosi - Veta Loca – New Discovery in 2016

    Eastern Borosi - Veta Loca – New Discovery in 2016 l TSX: IMG l NYSE: IAG l 129

  130. Slide 130: Africa

    Africa

  131. Slide 131: West Africa – Long History of Gold Mining

    West Africa – Long History of Gold Mining The Kenema – Man Shield l TSX: IMG l NYSE: IAG l 131

  132. Slide 132: West Africa – Host to Numerous Large Gold Deposits

    West Africa – Host to Numerous Large Gold Deposits Boto Diakha * Caution: compilation of past production and deposit resources to demonstrate geologic endowment, not NI 43-101 resource statements l TSX: IMG l NYSE: IAG l 132

  133. Slide 133: Boto-Siribaya Mineralization Trend

    Boto-Siribaya Mineralization Trend  Similar geology  Challenges of international borders l TSX: IMG l NYSE: IAG l 133

  134. Slide 134: Boto Gold Project, Senegal

    Boto Gold Project, Senegal Local Village Artisanal Mining Laterite Cap l TSX: IMG l NYSE: IAG l 134

  135. Slide 135: Boto Gold – Senegal (100% owned)

    Boto Gold – Senegal (100% owned) Tonnes Grade Contained Ounces (000) (g/t) (000 Au) Measured & Indicated1 27,670 1.8 1,563 Inferred1 2,922 1.3 125  236 square-kilometre land package in Senegal  Five deposits - Malikoundi deposit accounts for ~89% of the indicated resource.  Assay results confirm

  136. Slide 136: Boto Gold – Malikoundi High-Grade Drill Intersection

    Boto Gold – Malikoundi High-Grade Drill Intersection Crackle Breccia Sulphide Zones l TSX: IMG l NYSE: IAG l 136

  137. Slide 137: Boto Gold – Footwall Extension - 2016 Drilling

    Boto Gold – Footwall Extension - 2016 Drilling Drilling Highlights  DBDD-2125, the previous interval of 25m @ 1.65 g/t Au is part of 50m @ 1.57 g/t Au  DBDD-2218, 30m @ 3.82 g/t Au is now part of 42m @ 3.60 g/t Au  DBDD-2222, 13m @ 7.94 g/t Au is now part of 32m @ 5.19 g/t Au Cross-Section (looki

  138. Slide 138: Boto Gold – Depth Extension – 2016 Drilling

    Boto Gold – Depth Extension – 2016 Drilling DBDD-2294 84m @ 4.12 g/t Au (including 22m @ 11.25 g/t Au, and 69m @ 1.56 g/t Au) 2017 Cross-Section (looking north) l TSX: IMG l NYSE: IAG l 138

  139. Slide 139: Siribaya Project, Mali

    Siribaya Project, Mali July – Dec. - Rainy Season Health Centre l TSX: IMG l NYSE: IAG l 139

  140. Slide 140: Diakha-Siribaya – Mali (50/50 JV with Merrex Gold)

    Diakha-Siribaya – Mali (50/50 JV with Merrex Gold) Tonnes Grade Contained Ounces (000) (g/t) (000 Au) Measured & Indicated1,2 2,102 1.9 129 Inferred1.2 19,816 1.7 1,092  Located 10 km south of Boto  Similar gold mineralization characteristics to Boto  Multiple zones of mineralization over 800m x

  141. Slide 141: Diakha Drill Section (A-A')

    Diakha Drill Section (A-A’) 4.34 g/t Au / 4m 4m@4.34 2.36 g/t Au / 24m 3.61 g/t Au / 11m 11.99 g/t Au / 34m Grade Range (Looking north) Gold mineralization extended to -250m vertical l TSX: IMG l NYSE: IAG l 141

  142. Slide 142: Diakha Zone Mineralization

    Diakha Zone Mineralization Drill Hole SRD14-148: 34m grading 4.85 g/t Au 1.56g/t 1.06g/t 7.93g/t 8.15g/t 51.00 g/t VG 11.55g/t 0.36g/t 157.0 m – 161.0m: 19.66 g/t Au over 4.0m Similar to Boto Deposit l TSX: IMG l NYSE: IAG l 142

  143. Slide 143: Diakha Zone

    Diakha Zone  Permit extension approved in 2016  Excellent potential to extend known mineralization along strike  Potential to increase current mineral resource l TSX: IMG l NYSE: IAG l 143

  144. Slide 144: Diakha Zone – 2016 Exploration

    Diakha Zone – 2016 Exploration “First Pass” drilling along northern extension (6,623m RC) 70m @1.55 g/t Au 26m @1.16 g/t Au Infill drilling (6,414m DD)  Convert Inferred Resource to Indicated  Extend zones of higher grade mineralization at depth 18m@6.73g/t Au 38m@2.37g/t Au 19m@9.28g/t Au l TSX:

  145. Slide 145: Appendices

    Appendices

  146. Slide 146: 2016 Production and Cost Guidance

    2016 Production and Cost Guidance Previous Guidance4 Revised Guidance3 Essakane (000s oz.) 365 – 375 365 – 375 Rosebel (000s oz.) 285 – 295 285 – 295 Westwood (000s oz.) 50 – 60 50 – 60 Total owner-operated production (000s oz.) 700 -730 700 -730 Joint ventures (000s oz.) 70 70 Total attributable pr

  147. Slide 147: Capex Outlook

    Capex Outlook $millions Sustaining Non-Sustaining Total Previous Revised Previous Revised Previous Revised Essakane 85 100 - - 85 100 Rosebel 50 60 15 15 65 75 Westwood 15 20 65 65 80 85 150 180 80 80 230 260 Corporate and Development Projects - - 10 5 10 5 Total owner-operator 150 180 90 85 240 265

  148. Slide 148: Mineral Reserves and Resources

    Mineral Reserves and Resources Contained Gold (000s attributable oz.) 2015 Change 2014 As of December 31, 2015 Total proven and probable mineral reserves 7,690 (11%) 8,608 Total measured and indicated mineral resources 2,3 23,482 10% 21,412 Total inferred resources 6,733 (4%) 7,018 • Gold reserves h

  149. Slide 149: Technical Information and Qualified Person/Quality Control Notes

    Technical Information and Qualified Person/Quality Control Notes The mineral resource estimates contained in this presentation have been prepared in accordance with National Instrument 43-101 Standards of Disclosure for Mineral Projects (“NI 43-101”). The “Qualified Person” responsible for the super

  150. Slide 150: IAMGOLD – Directors in Attendance

    IAMGOLD – Directors in Attendance Don Charter, Chairman Mr. Charter became the Chairman of the Board of Directors of IAMGOLD Corporation on May 11, 2015. An experienced corporate director, he serves on four public company boards, which, in addition to IAMGOLD, include Lundin Mining, Dream Office REI

  151. Slide 151: IAMGOLD – Executive Leadership Team

    IAMGOLD – Executive Leadership Team Steve Letwin, President & CEO Steve Letwin was appointed President and Chief Executive Officer of IAMGOLD on November 1, 2010. Specializing in corporate finance, operational management, and merger and acquisitions, Steve brings over 30 years of experience from the

  152. Slide 152: IAMGOLD – Executive Leadership Team

    IAMGOLD – Executive Leadership Team Benjamin Little, Senior VP Corporate Affairs, HSS & People Benjamin Little is Senior Vice President at IAMGOLD Corporation. Ben is also Chief Executive Officer of Euro Ressources SA, a French affiliate of IAMGOLD focused on precious-metal royalties. Prior to joini

  153. Slide 153: IAMGOLD – Regional VPs

    IAMGOLD – Regional VPs Oumar Toguyeni, Regional VP, West Africa Oumar Toguyeni joined IAMGOLD 2012 and is currently Regional Vice-President, West Africa. . In previous roles, Oumar had accumulated over 25 years of international experience in exploration, project development and operations for variou

  154. Slide 154: IAMGOLD – General Managers

    IAMGOLD – General Managers Bruno Lemelin, Essakane Mine, Burkina Faso Bruno Lemelin was appointed General Manager of the Essakane mine in May 2016, after having previously held the positions of Manager, Mine, and Manager, Operations. Before joining IAMGOLD, Bruno developed his mining expertise at di

  155. Slide 155: IAMGOLD – Other Participants

    IAMGOLD – Other Participants Michael Michaud, Chief Geologist, Corporate Michael Michaud, M.Sc., P.Geo., is IAMGOLD’s Chief Geologist and brings almost 30 years of experience in exploration and mining that was gained from a number of different geographical and geological environments in North and So

  156. Slide 156: Investor Relations Contact

    Bob Tait Laura Young Shae Frosst VP, Investor Relations Director, Investor Relations Associate, Investor Relations T: 416-360-4743 T: 416-933-4952 T: 416-933-4738 TSX: IMG NYSE: IAG