Essar Shipping Limited. · NSE:ESSARSHPNG
Essar Shipping — Essar Oil — Q3 FY2012 Earnings Presentation
53 slides from Essar Shipping's earnings presentation, Feb 17, 2012

Slide 1: Essar Oil Limited Analyst Presentation
Essar Oil Limited Analyst Presentation Results for quarter ended 31st Dec, 2011

Slide 2: Disclaimer
Disclaimer This Document and any information made available orally or in writing at any presentation or delivery of this Document (together the “Materials”) do not constitute or form part of and should not be construed as, any offer or invitation to sell or issue, or any solicitation of any offer to

Slide 3: Agenda of Presentation
Agenda of Presentation Performance Snapshot Industry & Market Outlook Operations Refinery Projects Exploration & Production Financials 2

Slide 4: Performance Snapshot
4 ESSAR’ OIL & GAS Performance Snapshot

Slide 5: Performance Highlights for Q3 FY12
, Performance Highlights for Q3 FY12 Good operating performance of refinery with throughput 2.81 mmt, demonstrating increased capacity of Refinery 1 post shut-down. Revenue & EBIDTA at Rs 13897 crore & 490 crore respectively as compared to Revenue & EBIDTA of Rs 13809 crore & 2 Rs 827 crore respecti

Slide 6: Industry Overview & Market Outlook
Industry Overview & Market Outlook 5

Slide 7: Crude Market Dynamics
Crude Market Dynamics WTI Brent Dubai USD/bbl 125 123 Crude marker difference between Brent & 120 114 116 114 117 113 115 WTI has gone down during the quarter in 110 109 111 110 108 108 106 anticipation of removal of supply / offtake 105 108 110 105 109 106 110 104 bottleneck for moving the crude

Slide 8: Light & Heavy differential & Products cracks
Light & Heavy differential & Products cracks Arab Light - Arab Heavy Arab Light - Norooz BL - Maya Difference between Arab light & Arab USD/bbl 20 heavy has gone down to average 18.1 18 14.5 17.0 16.2 16.4 14.9 $3.23/bbl during Q3 FY12 as compared to 16 13.7 15.6 15.8 14 13.8 avg. US$ 3.83/bbl for

Slide 9: Operations
4 ESSAR’ OIL & GAS Operations

Slide 10: Vadinar Refinery
4 nw Vadinar Refinery OIL & GAS . a eh... a ee

Slide 11: Operating Performance – Refinery
Operating Performance – Refinery Crude Throughput Processed 2.81 million tonnes of crude during the quarter ended Dec-2011, 4.0 3.73 3.5 3.03 throughput lower by 0.88 million tones on 3.0 0.88 Million Tonnes 2.5 2.81 account of planned shut-down for 22 days in 2.0 Oct, 2011. 1.5 1.0 0.5 Processe

Slide 12: Operating Performance - Refinery
Operating Performance - Refinery Processed more than 15 types of crudes Crude Mix including ultra heavy & tough crudes like Light Heavy Ultra Heavy Nowrooz, Ras Gharib & Mangala during 100% 31% 25% 26% the Q3 FY12 . 80% Million Tonnes 60% 60% 50% 52% Usage of Ultra Heavy & Heavy crude 40% improv

Slide 13: Operating Performance - Refinery
Operating Performance - Refinery Product Mix Optimised production of middle & light Light Middle Heavy 100% distillates – High margin segment 26% 29% 25% 80% 60% 45% 42% 44% Commencement the production of 40% 20% superior performance VG grade bitumen 29% 28% 31% 0% (VG 30) by processing a judici

Slide 14: Operating Performance - Refinery
Operating Performance - Refinery Sales Mix Continue to focus on domestic market due 80% to better price realization of petro products Bulk Retail PSUs Exports 70% 5% 6% 2% 60% 5% 5% Increased in Sales to PSU mainly due to 7% 50% supply of products in domestic market 40% during shutdown. 65% 30%

Slide 15: Projects
4 ESSAR’ OIL & GAS Projects 14

Slide 16: Refining Expansion - Phase I
Refining Expansion - Phase I Expansion to 18 MMTPA Amine Regeneration Unit Complexity to improve to 11.8 from 6.1 Achieved Mechanical Completion for all the units under Refinery Expansion Project ISOM, ARU, HMU,SWS, Nitrogen & Air Generations units Raw water treatment plant, Demineralisation pla

Slide 17: Refining Optimization Project
Refining Optimization Project Expansion to 20 MMTPA Delayed Coker Unit – Six Coker Drums Overall progress : 74.65% Engineering : 98.80% Procurement : 80.55% Construction : 60.25% Optimization Project is on schedule & expected to complete by Sept, 2012 New Units/ Facilities under optimization

Slide 18: Crude Mix & Sourcing Strategy
Crude Mix & Sourcing Strategy Crude Mix : Existing Refinery Overall Crude basket to become significantly heavier due to Coker configuration post Ultra Heavy expansion. 20% Light 25% Ultra heavy crude to increase from 20% currently to 60% of overall crude basket. Heavy / Medium 55% Avg API of c

Slide 19: Yield to shift towards high grade products
Yield to shift towards high grade products Product Mix : Existing Refinery Refinery Expansion Project to convert low margin Fuel Loss fuel oil into high value added products like 6% Gasoil, Gasoline & VGO. Heavy Light 26% 25% Substantial reduction in Fuel Oil from existing 25% to around 5% post

Slide 20: Product Evacuation Strategy
Product Evacuation Strategy Post Expansion, 55% of product output is expected to be sold in Domestic Market & balance 45% through Export in FY12. The Export share to reduce gradually due to robust domestic demand growth. Tied up with PSUs on long term contract for supply of products in domesti

Slide 21: Comparative Refinery Margin
Comparative Refinery Margin (Without Sales Tax) GRM expected to improve with increased complexity and capacity Utilization of Mangala Crude, Coal to further boost the GRM 20

Slide 22: Refinery Expansion Project Units & Facilities commissioned
Refinery Expansion Project Units & Facilities commissioned 21

Slide 23: ISOM Unit (Isomerization Unit)
ISOM Unit (Isomerization Unit) 22

Slide 24: Amine Regeneration Units (ARU)
Amine Regeneration Units (ARU) 23

Slide 25: Hydrogen Manufacturing Unit
Hydrogen Manufacturing Unit 24

Slide 26: Sour Water Stripper
ESSAR Sour Water Stripper

Slide 27: Effluent Treatment Plant
Effluent Treatment Plant 26 26

Slide 28: Demineralisation Plant, Caustic Pumps & Tanks
Demineralisation Plant, Caustic Pumps & Tanks Demineralisation Plant Caustic System Pumps & Tanks 27

Slide 29: Desal Plant, NG Station, Tanks Farm Area & OSBL Racks
Desal Plant, NG Station, Tanks Farm Area & OSBL Racks Tank Farm Area OSBL Pipe Rack Natural Gas Station Desalination Plant Natural Gas Station 28

Slide 30: Air Generations Unit & Raw Water Treatment Plant
Air Generations Unit & Raw Water Treatment Plant Air Generation Unit Raw Water Treatment Plant 29

Slide 31: Flare Drum and Racks & Cooling Towers
Flare Drum and Racks & Cooling Towers Flare Drum Area Flare Racks Cooling Tower – I Cooling Tower - II 30

Slide 32: Power Generation Facilities
Power Generation Facilities Vadinar – Liquid Fuel Vadinar - Gas based Power Plant Vadinar – Coal Based power plant • Capacity: 120 MW (77MW power • Capacity: 380 MW (220MW power & • Capacity: 510 MW (325MW power & & 230 T/H steam) 630 T/H steam) 900 T/H steam) • Fuel: Refinery residue / Liquid Fuel

Slide 33: Port & Terminal Facilities
Port & Terminal Facilities Ports & Terminals (owned by Essar Port Ltd) 1 SPM, Draft – 32 m crude; intake capacity: 27 mmtpa 2 Jetties (1+1) for product offtake : 14 mmtpa Pipelines & other supporting infrastructure facilities completed 32

Slide 34: Storage & Evacuation Facilities
Storage & Evacuation Facilities Tankages, Rail & Road Gantries (Owned by EPL) 136 tankages ( 106 + 30) for crude oils, products and Intermediates with capacity of ~ 2.94 Million KL (1.96 Mn KL earlier + 0.98 Mn KL expansion); Fully automated Loading Facilities; 3-White Oil truck Gantries, each 8

Slide 35: Refinery Expansion Project Units under commissioning
Refinery Expansion Project Units under commissioning 34

Slide 36: Diesel Hydrotreater (DHDT)
Diesel Hydrotreater (DHDT) 35

Slide 37: VGO HT (Hydrotreater Unit)
VGO HT (Hydrotreater Unit) 36

Slide 38: DCU (Delayed Coker Unit)
DCU (Delayed Coker Unit) 37 37

Slide 39: Sulphur Recovery Unit
-s” Sulphur Recovery Unit ariies

Slide 40: Exploration & Production
4 ESSAR’ OIL & GAS Exploration & Production 39

Slide 41: Project Progress at Raniganj
Project Progress at Raniganj Drilled 71 wells in the current Phase, producing approx. 22,000 scmd from 15 to 20 wells – reduced to minimise flaring, supply of Gas to end customers through pipeline started. Field Development Plan for drilling of 500 wells approved by DGH. Environmental Clearanc

Slide 42: Raniganj: Reservoir Certification by NSAI
Raniganj : Reservior Certification by NSAI NSAI , an independent agency issued a revised certification for Raniganj Reserves on 1st Sept, 2011 Reserve 1P Reserve 2P The certification envisages following reserves/ Reserve 3P resources. Contingent 2P (proven & probable) reserves are 113 bcf as c

Slide 43: Leading CBM Gas Player in India
Leading CBM Gas Player in India CBM Blocks Raniganj Rajmahal Sohagpur Talcher IB Valley Total M.P. & Place West Bengal Jharkhand Chhattisgarh Orissa Orissa Ownership 100% 100% 100% 100% 100% Acreage (km2) 500 km2 1128 km2 339 km2 557 km2 209 km2 2,733 km2 2P/2C resources (bcf) 558 558 Best Estimate

Slide 44: Financials
4 ESSAR’ OIL & GAS Financials 43

Slide 45: Financial Highlights – Q3 FY12
Financial Highlights – Q3 FY12 ( Rs in Crore) Net Worth excludes FCCBs of $ 262 million issued to EEPLC; (Rs 1396 crore for Q3 FY12 & Rs. 1174 crore for Q3 FY11) 44

Slide 46: Refinery & Marketing Financial Performance
Refinery & Marketing Financial Performance ( Rs in Crore) 45

Slide 47: Summary
Summary Vadinar Refinery set to become a world class refinery given its large scale, high complexity and low cost operations. Refinery Expansion to create flexibility in crude sourcing with ability to process various types of sour, tough & acidic crudes Long Term contracts executed for majorit

Slide 48: Thank You
Thank Yow “~~ ESSAR OIL & GAS

Slide 49: Supreme Court Judgment and Way forward
Supreme Court Judgment and Way forward Supreme Court Judgment On 17-Jan-2012, Supreme Court allowed the appeal of state government and set aside the judgment of Gujarat High Court The Order was silent regarding EOL’s liability to repay the tax collected so far. Current Status of Sales Tax (EOL)

Slide 50: Background of Sales Tax Scheme
Background of Sales Tax Scheme The Company obtained provisional registration of refinery project under Capital Investment Incentive to Premier/Prestigious unit Scheme 1995-2000 of Government of Gujarat. Under the Scheme, the units are eligible to retain proceeds of sales tax collected for a peri

Slide 51: Sales Tax Deferral Benefit Scheme
Sales Tax Deferral Benefit Scheme As per the Scheme, the Company was required to complete the refinery project by 15-Aug-2003 to be eligible to claim benefits. The Company couldn’t complete the project before the deadline due to: (a) severe cyclone which hit refinery site in June 1998 and (b) Stay

Slide 52: Sales Tax Liability & Accounting Treatment
Sales Tax Liability & Accounting Treatment Rs in Crore Sales Tax Collected till Dec-2011 6309 Less : Assignment to Group Company 1893 Less : Interest receivable on Assigned Liability 212 Less : Other adjustments (GGY reversal) 189 Net Sales Tax liability 4015 51

Slide 53: CDR Exit
CDR Exit Board of Directors formed a Committee to devise, negotiate and finalise the Company’s proposal for achieving CDR Exit in July, 2011 The Company submitted comprehensive CDR Exit proposal which was discussed in LMC held on Sept 15, 2011. Lenders requested for change in few terms for impro
Source: Internet Archive copy of essar.com
More decks from Essar Shipping Limited.
Essar — Investor Presentation (January 2026)44 slides · January 2026
Essar — Investor Presentation (January 2026)43 slides · January 2026
Essar — Investor Presentation (January 2025)42 slides · January 2025
Essar — Investor Presentation (September 2024)43 slides · September 2024
Essar — Investor Presentation (July 2024)44 slides · July 2024
Essar — Investor Presentation (February 2024)27 slides · February 2024