  1. Slide 1: Development of the Siana Gold Project – Annual General Meeting

    For personal use only RED 5 LIMITED – GREENSTONE RESOURCES DEVELOPMENT OF THE SIANA GOLD PROJECT Annual General Meeting November 23, 2010

  2. Slide 2: Location

    For personal use only Location

  3. Slide 3: Project information

    Project information For personal use only  Open pit and underground Mine – 850,000 oz +  Life of the Mine 11 Years Open Pit 5 Years Underground 6 Years  Project development cost US$75 million  Project development strategy - Mine and plant construction to major Filipino contractors - All other co

  4. Slide 4: Strong community support

    Strong community support For personal use only

  5. Slide 5: Production targets

    Production targets For personal use only Siana Mine Plan Open Pit Production

  6. Slide 6: Planned site layout

    For personal use only Planned site layout

  7. Slide 7: Innovations in Exploration, Design & Development

    Innovations in Exploration, Design & Development For personal use only 1. Resource Drilling techniques 2. Core handling procedures 3. Resource estimation 4. Underground Mining techniques 5. Tailings Dam design 6. EPCM & Project Management 7. Plant design 8. Flood analysis 9. Contracts and Procuremen

  8. Slide 8: Resource drilling

    For personal use only Resource drilling

  9. Slide 9: Resource drilling

    For personal use only Resource drilling

  10. Slide 10: Drillcore Handling Procedures

    Drillcore Handling Procedures For personal use only • Photographed (whole) wet & dry • Geological logging • Geotechnical logging & Point Load Testing • Specific Gravity determination 100% • Magnetic susceptibility • Packing tape wrapped Of • Cut according to core size • 5 meter slot cut for geochemi

  11. Slide 11: Drillcore Handling Procedures

    Drillcore Handling Procedures For personal use only

  12. Slide 12: Core Volume for analysis

    Core Volume for analysis For personal use only Lab Sample 20% Met Sample Lab Sample Met Sample 60% PQ 85mm Reference Sample 20% Lab Sample 30% Met Sample Lab Sample HQ 63mm Met Sample 50% Reference Sample 20% Met Sample Lab Sample Lab Sample 50% NQ 47mm Met Sample 20% Reference Sample 30%

  13. Slide 13: Long section

    For personal use only Long section

  14. Slide 14: Resource panels

    For personal use only Resource panels

  15. Slide 15: Mining Plan

    For personal use only Mining Plan

  16. Slide 16: Underground mining

    For personal use only Underground mining

  17. Slide 17: Roadheader Selection

    For personal use only Roadheader Selection

  18. Slide 18: Underground mining method

    Underground mining method For personal use only

  19. Slide 19: Underground Paste Fill

    Underground Paste Fill For personal use only

  20. Slide 20: Community Location

    For personal use only Community Location

  21. Slide 21: Tailings Dam Design

    For personal use only Tailings Dam Design

  22. Slide 22: Tailings Dam Design

    For personal use only Tailings Dam Design

  23. Slide 23: EPCM & Project Management

    EPCM & Project Management For personal use only • Project Director (David Jerdin) with client engineering, procurement, cost and document control team. • Embedded TWP Australia EPCM Project Manager (Bruce Ilford) • Embedded EPCM engineering, procurement & adjudication team. • Design by Contromation

  24. Slide 24: Plant Design

    Plant Design For personal use only • Process design by TWP Australia • 3D Plant design and engineering by (CES) • Workshop drawings automatically produced from system

  25. Slide 25: Plant design

    For personal use only Plant design

  26. Slide 26: Flood Analysis – 5Yr Event

    Flood Analysis – 5Yr Event For personal use only

  27. Slide 27: Flood Mitigation – 5Yr Event

    Flood Mitigation – 5Yr Event For personal use only

  28. Slide 28: Flood Analysis – 75Yr Event

    Flood Analysis – 75Yr Event For personal use only

  29. Slide 29: Flood Mitigation – 75Yr Event

    Flood Mitigation – 75Yr Event For personal use only

  30. Slide 30: Contracts & Procurement

    Contracts & Procurement For personal use only • Maximized Philippine procurement. • 100% Philippine Earthworks, Civil (Equi Parco), Fabrication & Construction (Aboitiz). • Philippine Mining Contractor (Delta).

  31. Slide 31: Employment Policy

    Employment Policy For personal use only • • Local Employment Policy: • Workers 95% • Earthmoving Operators 80% • High-skill Trades 60%

  32. Slide 32: Location

    For personal use only LOCATION

  33. Slide 33: Porphyry Model

    For personal use only PORPHYRY MODEL

  34. Slide 34: Mapawa Surface Mineralisation

    MAPAWA SURFACE MINERALISATION For personal use only

  35. Slide 35: Mapawa IP Results

    For personal use only MAPAWA IP RESULTS

  36. Slide 36: Mapawa geological cross-section

    Mapawa geological cross-section For personal use only

  37. Slide 37: Mapawa ground magnetics

    Mapawa ground magnetics For personal use only

  38. Slide 38: Mapawa gmag & surface gold

    Mapawa gmag & surface gold For personal use only

  39. Slide 39: Summary

    Summary For personal use only • Emerging gold producer in the Philippines • Excellent community relations • All major permits in place • Construction commenced • Final debt/equity financing announced • +10 year production profile • Enormous exploration potential in the region

  40. Slide 40: Competent Person statement

    For personal use only The information in this Public Report that relates to Exploration Results, Mineral Resources or Ore Reserves is based on, and accurately reflects, information compiled by Mr G C Edwards who is a full-time employee of Red 5 Limited and who is a Member of The Australasian Institu