APC Minerals Limited · ASX:APC

APC Minerals — Australian Potash — Investor Presentation (August 2020)

18 slides from APC Minerals's investor presentation, August 2020

  1. Slide 1: 2020 FEED Update Timeline

    2020 FEED UPDATE Timeline Offtake Approvals Funding

  2. Slide 2: Disclaimer

    Disclaimer Nature of this document This presentation has been prepared by Australian Potash Limited (APC or the Company). The information is based on publicly available information, internally developed data and other sources. By receiving this presentation, you acknowledge and represent to the Comp

  3. Slide 3: Realistic Timeline to Development

    The Lake Wells Sulphate of Potash Project Realistic Timeline to Development Q3 & Q4 Construction • Finalise Offtake Program • Finalise Debt Due Diligence • Village & NPI • Finalise EPC contracts • Pre-concentration ponds 2021 2023 • EPA Approval • Process plant and load out • Strategic Partner inves

  4. Slide 4: Q3 & Q4 2020 Newsflow

    Q3 & Q4 2020 Newsflow 01 02 Offtake Program Environmental Approval • Targeting 75% - 85% of DFS output under • Environmental Review Document being contracted sale agreements by end Q3 to finalised with EPA ‘bank’ LSOP offtake position • EPA 6-week window to prepare report to • Currently 86% the Mini

  5. Slide 5: Offtake Program

    The Lake Wells Sulphate of Potash Project Premium project Premium fertiliser Offtake Program • 130,000 tonnes per annum under binding offtake agreements • 86% of DFS output contract sold • FEED Program optimising output volume Tier 1 Trading Partners Redox 20,000 tpa Migao 50,000 tpa Mitsui 30,000 t

  6. Slide 6: Approvals Pathway

    Approvals Pathway Environmental Protection Authority and Other DMAs Agency COLUMN 1 COLUMN 2 COLUMN 3 COLUMN 4 COLUMN 5 COLUMN 6 Not applicable to APC • Endorsement of the Environmental Review Document (ERD) by EPA • 6 weeks to report to Minister for the Environment • Minor & Preliminary Works Appro

  7. Slide 7: Financing the Build

    Financing the Build NAIF, Commercial Debt, Equity Northern Australia Commercial Debt Equity Infrastructure 30% of total funding requirement 35% of total funding requirement Facility (NAIF) 35% of total funding requirement www.australianpotash.com.au 2020 Q3 Update 7

  8. Slide 8: Contracting Strategy

    Contracting Strategy Risk Mitigation Shareholder Protection 6 Packages EPC Contracted Why? Tender docs EOM AUG 2020: SOP process plant Schedule guarantee Tender docs WED 12 AUG: Borefield fit-out & HV network Price guarantee Bids due FRI 14 AUG: Power station Process guarantee Bids due FRI 14 AUG: C

  9. Slide 9: Renewable Power

    Renewable Power Low C Footprint PLUS Renewable Power Design & Construct Tender documents issued for D&C pricing Bids due FRIDAY 14 AUGUST 2020 Material impact on OPEX 30% saving indicated versus DFS OPEX Lowering the carbon footprint Future proofing against fiscal penalty regime Broadening market ap

  10. Slide 10: The Peer Space

    The Peer Space Companies with Offtake Agreements in Place Peer Comparison Peer Comparison SOP Reserve (Proven & Probable) 3.6Mt 5.4Mt1 5.13Mt4 SOP Resource (Measures & Indicated) – drainable 18.1Mt 4.0Mt1 11.58Mt4 Planned production 150ktpa 245ktpa 90ktpa CapEx $208m $264m2 $280m5 NPV(8) (Post-tax)

  11. Slide 11: Board Composition

    Board Composition Skills and Governance Jim Brett Rhett Matt Cathy Walker Lambert Brans Shackleton Moises Chairman Non-executive Director Project Director Managing Director & Non-executive Director CEO  Appointed Aug 2018  Appointed May 2017  Appointed NED May 2017  Appointed July 2014  Appoint

  12. Slide 12: Corporate Snapshot

    Corporate Snapshot Recent capital raising positions Company strongly with zero debt Capital Structure PRICE ($) VOLUME (M) $0.14 8.0 Share Price (25 August $0.105 $0.12 7.0 2020) 6.0 Shares on Issue 486,560,549 $0.10 5.0 $0.08 Listed options1 55,350,135 4.0 $0.06 Unlisted options & 3.0 22,275,708 Pe

  13. Slide 13: Project Delivery and Risk Management

    Project Delivery and Risk Management Skills and Governance  ASX Corporate Governance Structures  ISO45001 Framework (Gold Standard)  Continuous training and improvement  Deep Commercial and Technical Experience  1:25 OH&S Professionals on staff  Highly experienced and diversified Board  Frame

  14. Slide 14: Sustainability

    Sustainability Respect for Community, Environment, Indigenous Culture & Stakeholders Understand, Replacing a Respect, Protect material C footprint Employee Cultural Commitments High-penetration (c.60%) renewable power station Employment & being tendered Contracting Opportunities 2020 - 2023 STEM Cul

  15. Slide 15: Brine SOP = low cost, Organic soluble SOP

    Lake Wells branded SOP is a high-purity organically certifiable and soluble SOP Brine SOP = low cost Low cost, technically feasible bore- pumping operation to produce 17Gl of $12.000 Potash brine per year June 14/2022 Why MOP addition? $80,000 Capital efficiency: same bore-field, June 14/2022 same p

  16. Slide 16: SOP Market

    SOP Market Sulphate of Potash is the premium form of an essential non-substitutable plant fertiliser 7M TONNES Essential US$450/t US$3.5B Market Size <1% Chloride/17% Sulphur High-margin SOP Global Demand • SOP = 10% of the global • Potassium is essential • Solar salt = lowest quartile cost • 50% of

  17. Slide 17: SOP Market

    SOP Market SOP trades at a Premium to MOP • Suitability for higher value crops SOP premium to MOP • Suitability for chloride sensitive crops • Scarcity of primary deposits US$100/tonne SOP>MOP • Average cost to convert a tonne of MOP to SOP using Mannheim process • Mannheim process = 50% global supp

  18. Slide 18: Contact details

    Suite 31, 22 Railway Road, Subiaco WA 6008 admin@australianpotash.com.au +61 8 9322 1003